MOORPARK CITY COUNCIL
AGENDA REPORT
TO: Honorable City Council
FROM: Yugal K. Lail, City Engineer /Public Works Director /
DATE: March 26, 2007 (CC Meeting of 04/04/07)
SUBJECT: Consider Notice of Completion for the Magnolia Park Street
Improvement Project
DISCUSSION
A. Background / Project Scope
The FY 2006/07 Budget includes Project 7816 for the construction of a park at the
intersection of Charles Street and Magnolia Street. The City undertook and
completed efforts necessary to vacate Magnolia Street between Charles Street
and a point just north of the Fire Station. The future park will include the vacant
property at the southwest corner of Charles Street and Magnolia Street, and the
vacated Magnolia Street right -of -way.
The subject project is for the construction of Phase 1 of the park improvements.
This work included the removal and /or modification of street improvements in the
vicinity of the future park. Phase II of the project, the construction of the park
improvement, will follow later this year.
B. Changes
1- Quantity Adjustments: As is typical with public works construction projects,
the actual quantities required for the job differed from the engineer's estimate.
This project required additional quantities of certain bid items resulting in an
additional cost of $3,737.00.
2. Change Orders: One Contract Change Order was approved for the removal and
replacement of damaged curb and gutter in the vicinity of the project and the
installation of a new water line connection.
city share/public works/everyone/staff reports/2007 /ApriVMagnolia Park comp ') n U U 1 9
Honorable City Council
April 4, 2007
Page 2
C. Fiscal Impact
Construction Cost Summary: The total project construction cost is
summarized as follows:
Description Amount (a)
Bid amount 67,332.50
Quantity Adjustment 3,737.00
Change Order 15,498.50
Total 86,568.00
2. Total Project Cost Summary. Total project costs are summarized as follows:
Phase 1
3. Budget There are sufficient funds appropriated for the design and
construction of both the subject street work and the future park improvements.
A preliminary estimate of budget requirements for both projects is as follows:
Project 7816 Current Estimated Future Est. Required
Magnolia Park Budget ($) Appropriation ($) Budget ($)
FY06 /07 Budget 532,044 0 532,044
Plus Prior Year Est. Costs 12,948 12,948
Total Appropriations 544,992 0 544,992
4. Funding Source: The funding source for this project is Fund 2904: Moorpark
Redevelopment Agency.
D. Final Inspection and Acceptance
The City has completed a final inspection of the project and has found the work to
be acceptable. At this time it would be appropriate for the City Council to accept
the project as complete so that the City Clerk may record the Notice of Completion
to start the final lien period. If no Stop Notices are received from subcontractors or
suppliers, the ten percent retention will be released thirty -five (35) days after the
date of the recordation of that notice.
taty shere/public works /everyone/staff reports /2007 /apriUM"noiia Park COMP 000020
Street
Park
Project
Element
Work ($)
Impr. ($)
Total ($)
Design
11,144
15,000
26,144
Street Vacation
4,260
0
4,260
Constructon
86,568
285,000
371,568
Inspection /Surveying
2,734
2,000
4,734
Total 104,706
302,000
406,706
3. Budget There are sufficient funds appropriated for the design and
construction of both the subject street work and the future park improvements.
A preliminary estimate of budget requirements for both projects is as follows:
Project 7816 Current Estimated Future Est. Required
Magnolia Park Budget ($) Appropriation ($) Budget ($)
FY06 /07 Budget 532,044 0 532,044
Plus Prior Year Est. Costs 12,948 12,948
Total Appropriations 544,992 0 544,992
4. Funding Source: The funding source for this project is Fund 2904: Moorpark
Redevelopment Agency.
D. Final Inspection and Acceptance
The City has completed a final inspection of the project and has found the work to
be acceptable. At this time it would be appropriate for the City Council to accept
the project as complete so that the City Clerk may record the Notice of Completion
to start the final lien period. If no Stop Notices are received from subcontractors or
suppliers, the ten percent retention will be released thirty -five (35) days after the
date of the recordation of that notice.
taty shere/public works /everyone/staff reports /2007 /apriUM"noiia Park COMP 000020
Honorable City Council
April 4, 2007
Page 3
STAFF RECOMMENDATION
Accept the work as complete and direct the City Clerk to record the Notice of
Completion.