HomeMy WebLinkAboutAGENDA REPORT 2017 0315 CCSA REG ITEM 10F ITEM 10.F.
CITY OF MOORPARK,CALIFORNIA
City Council Meeting
MOORPARK CITY COUNCIL ACTION:
AGENDA REPORT ,
TO: Honorable City Council
FROM: Sean Corrigan, P.E., City Engineer/Public Works Director A-,
Prepared by: Shaun Kroes, Program Manager
DATE: March 3, 2017 (CC Meeting of 03/15/17)
SUBJECT: Consider Amendment No. 3 to Agreement with Filippin Engineering,
Inc., for Additional Construction Management and Inspection
Services
BACKGROUND
On September 13, 2013, the City of Moorpark (Moorpark) executed an Agreement with
Filippin Engineering, Inc. (Filippin), for construction management and inspection services
of the State Highway 118 (Los Angeles Avenue) Widening from Maureen Lane to Leta
Yancy Road (Project 8058) for a not-to-exceed amount of$135,462. The Agreement has
been amended twice, as detailed below:
1. Amendment No. 1 (executed March 27, 2015) increased the maximum Agreement
compensation $70,000 (from $135,462 to $205,462) for additional work performed
above the original scope of services and an increase in hourly rates that occurred
between 2013 and 2015.
2. Amendment No 2 (executed October 14, 2016) increased the maximum Agreement
compensation $40,000 (from $205,462. to $245,462) for additional inspection
services required due to additional work of Project 8058's Contractor (Griffith
Company) required by Caltrans and Calleguas Municipal Water District.
DISCUSSION
Filippin Engineering has informed City staff that in order to complete closeout of the
project, Filippin needs additional funding in the amount of $14,000. A summary of the
additional work is provided below:
1. Additional construction management time to meet with City, Caltrans, and
Contractor to review curb and gutter cracking related to lean concrete base (LCB)
reflective cracking and to develop a Caltrans acceptable curb and gutter repair
method.
50
Honorable City Council
March 15, 2017
Page 2
2. Additional construction management and inspection time to observe curb and
gutter removal work and determine that reflective cracking from LCB was the cause
and report back to the City.
3. Additional construction management time to meet with Caltrans to accept the curb
and gutter repair work and accept the project work.
4. Additional construction management time for reviewing Contractor extra work
requests.
FISCAL IMPACT
Amendment No. 3 will increase Filippin's Agreement an additional $14,000. There are
sufficient funds in expense line 2014.311.00030.55200. The project is funded by the
Los Angeles Avenue Area of Contribution — (Fund 2014). The developer of the property
fronting the project, Pacific Communities, will be conditioned to reimburse the City for its
costs to construct this project.
STAFF RECOMMENDATION
Authorize the City Manager to sign Amendment No. 3 to the Agreement with Filippin
Engineering, Inc., for Construction Management and Inspection Services, increasing the
Agreement $14,000 for a total not to exceed amount of $259,462, subject to final
language approval by the City Manager.
Attachment: Amendment No. 3
51
AMENDMENT NO. 3 TO AGREEMENT BETWEEN THE CITY OF MOORPARK AND
FILIPPIN ENGINEERING, INC., FOR CONSTRUCTION MANAGEMENT AND
INSPECTION SERVICES FOR STATE HIGHWAY 118 (LOS ANGELES AVENUE)
WIDENING FROM MAUREEN LANE TO LETA YANCY ROAD
PROJECT 8058
This Amendment No. 3 to the Agreement between the City of Moorpark, a
municipal corporation ("City"), and Filippin Engineering, Inc., a corporation
("Consultant"), for construction management and inspection services ("Agreement"), is
made and entered into the day of , 2017.
RECITALS
WHEREAS, on September 13, 2013 the City and Consultant entered into an
Agreement to have the Contractor provide construction management and inspection
services; and
WHEREAS, on March 27, 2015 the City and Consultant executed Amendment
No. 1 to the Agreement to increase the maximum Agreement compensation by seventy
thousand dollars ($70,000) to account for Consultant's hourly rate increase for a total
amount not to exceed two hundred five thousand four hundred sixty-two dollars
($205,462), and to correct the Consultant's official company name; and
WHEREAS, on October 14, 2016, the City and Consultant executed Amendment
No. 2 to the Agreement to increase the maximum Agreement compensation by forty
thousand dollars ($40,000) to account for additional inspection services required due to
additional work required by the California Department of Transportation for an additional
layer of Class III Aggregate Base for the road and a protective concrete cap; and
WHEREAS, additional funds are necessary for the Consultant to complete
contract closeout of the project as detailed in Exhibit E; and
WHEREAS, the City and Consultant now desire to amend the Agreement to
increase the compensation for services to be performed by Consultant from two
hundred forty-five thousand four hundred sixty-two dollars ($245,462), by a value of
fourteen thousand dollars ($14,000) for a total contract value of two hundred fifty-nine
thousand four hundred sixty-two dollars ($259,462) and document said agreement to
amend by jointly approving Amendment No. 3 to the Agreement.
NOW, THEREFORE, it is mutually agreed by and between the parties to the
Agreement as follows:
I. The third paragraph of Section 2, SCOPE OF SERVICES, is amended by
replacing this paragraph in its entirety as follows:
"Compensation for services to be performed by Consultant shall be
in accordance with Exhibit B, Exhibit C, Exhibit D, and Exhibit E.
Compensation shall not exceed the rates or total contract value of two
hundred fifty-nine thousand four hundred sixty-two dollars ($259,462) as
52
stated in Section 5, without the written Amendment to this Agreement
executed by both parties. Payment by the City to the Consultant shall be
in accordance with the provisions of this Agreement."
II. The second paragraph of Section 5, PAYMENT, is amended by replacing this
paragraph in its entirety as follows:
"The City agrees to pay Consultant monthly, in accordance with the
payment rates and terms of payment as set forth in Exhibit B, Exhibit C,
Exhibit D, and Exhibit E, based upon actual time spent on the above
tasks. This amount shall not exceed two hundred fifty-nine thousand four
hundred sixty-two dollars ($259,462) for the term of this Agreement unless
additional payment is approved as provided in this Agreement."
III. Remaining Provisions:
Except as revised by this Amendment No. 3, all of the provisions of the
Agreement shall remain in full force and effect.
In Witness Whereof, the parties hereto have caused this Amendment to be
executed the day and year first above written.
CITY OF MOORPARK FILIPPIN ENGINEERING, INC.
Steven Kueny Gino P. Filippin
City Manager President
Attest:
Maureen Benson
City Clerk
5 3
Amendment No. 3 to Agreement between City of Moorpark and Filippin Engineering. Page 2
Exhibit E
_ , ._'EERING
February 28,2017 LA Avenue Road Widening;FE No: 131601
City of Moorpark
Public Works Department
799 Moorpark Avenue
Moorpark,CA 93021
Attn: Sean Corrigan,P.E.
City Engineer/Public Works Director
SUBJECT: REQUEST FOR ADDITIONAL AUTHORIZATION FOR CONSTRUCTION MANAGEMENT&
INSPECTION SERVICES,STATE HIGHWAY 118(LOS ANGELES AVENUE)WIDENING FROM
MAUREEN LANE TO LETA YANCY ROAD
Dear Mr. Corrigan:
Filippin Engineering(FE)has exceeded our contract amount for construction management, inspection,and
materials testing services on the State Highway 118(Los Angeles Avenue)Widening from Maureen Lane to
Leta Yancy Road project. FE is requesting that the City authorize additional funds to provide construction
management and inspection services to complete contract closeout of the project.The reasons that we are
requesting additional authorization are due to additional task that were requested by the City that were
not included in our original scope of services.The following tasks were performed that were not included in
our original scope of services:
1. Additional Construction Management time to meet and confer with City,Caltrans,and Contractor to
review curb and gutter cracking related to LCB reflective cracking and to develop and Caltrans
acceptable curb and gutter repair method.
2. Additional Construction Management and Inspection time to observe curb and gutter removal work
and determine that reflective cracking from LCB was the cause and report back to the City.
3. Additional Construction Management time to meet with Caltrans to accept the curb and gutter repair
work and accept the project work.
In addition,Griffith Construction has submitted extra work requests that still need to be reviewed and
resolved to close out the construction contract. Based on the extent of the extra work requests and
documentation provided, FE estimates$14,000 in additional contract authorization to cover the cost of
additional work related to the LCB reflective cracking of the curb and gutter and to complete the review of
and prepare a Contract Change Order for the submitted extra work requests
Please let us know if you have any questions or would like to discuss this request further. I can be reached
at 805-451-8935 or you can contact Gino Filippin at 805-729-0041. We appreciate the opportunity to work
with you and the City,and we look forward to getting this project completed successfully.