DATE: February 18, 1999 (City Council meeting of March 3,
1999)
SUBJECT: Consider the approval of additional soil import
and pad elevation changes for CPD 96 -3 and CUP 96 -2
(A. Deewayne Jones, D.D.S.)
On September 17, 1997, the City Council approved CPD 96 -3, CUP 96-
2 and a Tentative Parcel Map for A. DeeWayne Jones, D.D.S. to
construct two restaurants and an office retail building on a four
acre parcel. The location of the site is contiguous with the
southwest quadrant of Mission Bell - Phase 2. The development has
been approved with the import of up to, and not to exceed, 4,000
cubic yards of soil.
On November 4, 1998, the City Council approved Minor Modification
No. 1 to CPD 96 -3 and CUP 96 -2 for modification to the site plan
and architectural elevations.
DISCUSSION
Import of additional soil
A request has been made by the owner of commercial
development PM 5056 for approval of an additional 4,762 cubic
yards of import. The total quantity requested is now 8,762
cubic yards. Project condition 87 requires that a request for
additional import exceeding 4,000 cubic yards shall be
submitted in writing to the City Engineer and will require
additional Council approval prior to the commencement of the
additional hauling operations. A grading permit is required
prior to the hauling operations.
000111Z
HONORABLE CITY COUNCIL
CPD 96 -3 AND CUP 96 -2
MARCH 3, 1999
PAGE 2
The developer's reason for the additional import of soil is
the need to raise the elevation of the overall pad to
eliminate ramping to the Mission Bell Plaza to the east and
the depression at the southwest corner of the property. As
such, the pad elevations will be raised. The elevation of
Lot 1 (Building A at southeast corner) will increase 2.5 feet
from 485.2 feet to 487.7 feet. The elevation of Lot 2
(Building B at southwest corner) will increase 3.1 feet from
483.6 feet to 486.7 feet. The elevation of Lot 3 will
increase 2.0 feet from 486.0 feet to 488.0 feet. It is the
City Council policy to review and authorize all revisions to
approved pad elevations in excess of 2.0 feet.
The import of additional soil will come from Thousand Oaks
via SR 23 and Los Angeles Avenue (SR 118). Approximately 325
to 360 trucks are required for the additional import. A
total of 600 to 660 trucks will be required for the total
import of 8,762 cubic yards.
Property line wall
Project condition 88 requires that the proposed 8 feet high
masonry wall, proposed along the northerly and westerly
property lines, be constructed prior to the beginning of
grading operations. The purpose is to reduce noise during
the grading and construction operations.
The increase of the overall pad elevation will increase the
wall height up to 8.5 feet to 9 feet for the neighboring
properties to the north and west. The intent of the
condition is that the wall height be 8 feet to reduce noise
during the grading and construction operations from the
developer's property.
Copies of the approved Tentative Parcel Map and proposed grading
plan are available for review at the City Clerk's office.
The Planning Department has not reviewed the proposed revisions to
the grading plans and has not provided comments as to changes to
site improvements or increased roof ridge elevations, resulting
from the raised pad elevations as condition compliance fees for
review have not yet been paid to the Planning Department.
Planning Department review will be required prior to issuance of
any permits.
000 1.3
HONORABLE CITY COUNCIL
CPD 96 -3 AND CUP 96 -2
MARCH 3, 1999
PAGE 3
RECOMENMTION
1. Approve the request for the import of an additional 4,762
cubic yards of soil. (Total import of 8,762 cubic yards
after approval of grading permit).
2. Approve the request for the increase in pad elevations as
specified in this report.