DATE: July 12, 2007 (CC Meeting of July 18, 2007)
SUBJECT: Consider Additional Design Fees for the City Hall, Library, and Civic
Center and Amendment of FY 2007-08 Budget
BACKGROUND
One of the City Council's top ten priority projects is the development of a new Civic
Center and City Hall. City Council selected GKK Architects for the design of the new
Civic Center and City Hall in 2005 for a total contract price of $762,276.00. In
subsequent periods a number of master plan designs for the Civic Center were
presented and an Ad Hoc Committee (Mayor Hunter and Council Member Millhouse)
was established to work with staff to refine the design and address a number of issues.
This Ad Hoc Committee was reappointed (Mayor Hunter and Councilmember Mikos)
after the City Council reorganized in December 2006. In January 2007 when the City
had assumed operational control of the County Library, GKK Works was directed to
integrate a new City Library into the Campus Master Plan which increased their total
contract to $812,326.00. As a result, a Campus Master Plan with a building site design
concept incorporating the new permanent facilities on High Street was prepared by GKK
Architects and approved by the City Council on May 16, 2007.
DISCUSSION
In order to include these expanded requirements, GKK-Works is requesting a overall
design fee increase of $1,140,031 for the 35,000 square foot City Hall and a 25,000
square foot Library. For the City Hall, the fee will cover the costs of redesigning the
existing parking area, researching the use of sustainable design and its use in the
building, incorporating the additional changes made to the City Hall design and
including these additions in the construction documents. The architect has also included
the preparation of models and virtual fly through animation for both buildings. Staff
believes these design tools provide better access and understanding of the design
process for the Council and the public as we present these very significant public
projects. For the library this fee will include a Space Needs Study utilizing a special
000145
Honorable City Council
July 18, 2007
Page 2
consultant with expertise in the design and space planning of libraries, conceptual
design and design drawings, and presentation boards. The fee will not include
construction drawings and bid documents for the Library.
Because of the high public profile of this project the architect has also included costs for
probable additional board or commission presentation meetings and for possible
meetings with the user groups,
It is estimated that the construction cost for the City Hall and all site work including the
redevelopment of the existing civic center parking facilities will be approximately $ 20
million. The probable construction cost for the new library based on the initial concepts
for the building will be $ 8.4 million. It should be noted that since the approval of the
initial design services agreement with GKK-Works in November 2004, there have been
significant increases in construction costs as well as design and supporting consultant
costs.
Staff feels that the significant expansion in the scope of the project and its high public
profile justifies the fee increase. If Council approves this fee increase, GKK Works'
amended contract amount will be $1,952,357.
Each of the added phases is discussed in more detail below.
EXPANDED PROJECT SCOPE — GKK's scope of design and construction proposes
additional design work for the new 25,000± square foot Library building. In addition, the
scope of the City Hall project was increased to include the design of the trellis at the
public plaza, and redesign of the current Civic Center parking areas adding parking
spaces and improving vehicle turning radii. The Library will be designed to a level of
completion for integration of utility locations and loads, and horizontal and vertical
controls into the Campus Master Plan infrastructure in order to minimize disruption to
the new City Hall and Campus when the Library is constructed. GKK will provide design
presentation materials for the Library that are suitable for public display and publication
to obtain voter bond approval. This information will be provided both in color hard copy
mounted on presentation boards and in computer digital format. The fee increase does
not contemplate all stages of the Library construction project. The additional fees for
these stages will be discussed and added at a later date as part of the Library
construction project.
DESIGN QUALITY — It is important that the City Hall and Library facilities design stand
out as civic landmarks differentiated from the adjacent High Street and Moorpark
Avenue commercial design. In addition to the GKK internal design team the
professional services of Lighting and Signage/Graphics consultants are included as
appropriate to achieve a landmark-quality design.
000146
Honorable City Council
July 18, 2007
Page 3
SUSTAINABLE DESIGN —The City Hall and Library design will incorporate state-of-the-
art sustainable design practices including innovative demonstration features. GKK will
address life-cycle energy costs, maintenance and operations issues, and aid the City in
obtaining sustainable design grants and rebates. For an optional fee, GKK will develop
documentation to obtain LEED Certification from the U.S. Green Building Council
(USGBC).
LABOR AND EXPENSE COST INCREASES — The additional fees that are requested
include professional labor rate increases for GKK and subconsultants, and increases in
the cost of project expenses that have occurred in the approximately two and one-half
years since the original contract was approved.
OTHER EXTRA SERVICES — Several extra services are recommended to complement
and complete the Civic Center design. They are presented here for Council information.
At this time, these optional services are not included in the overall fee increase
discussed above.
Water Feature Design — $50,000.000 — A water feature is recommended for the
plaza/courtyard between the new City Hall and Library Buildings.
City Hall LEED Certification for Sustainable Design — $75,000.00 — Sustainable design
certification under the LEED program of the U.S. Green Building Council (USGBC) is
recommended to document City Hall design and construction as a demonstration of a
sustainable design project. Nationwide there are currently 122 local government, and
116 state and federal LEED certified projects. LEED certification is currently required in
the cities of Calabasas, Long Beach, Pasadena, Santa Monica, and Los Angeles.
City Hall Furniture Design & Selection — $43,750.00 — Design and selection of City Hall
furniture to complement the building design. Alternately, furniture design and selection
may be performed directly by the city's furniture vendor with coordination by GKK
Architects.
The total cost for these optional services would add an additional $168,750 to the
project design costs.
The overall fee increase was not included in the FY 2007/2008 budget. Staff has
included a request to amend the budget for the project. Staff is also in the process of
identifying grants that could be used to offset the design costs of the library and LEED
certifications on both buildings.
00014'7
Honorable City Council
July 18, 2007
Page 4
STAFF RECOMMENDATION (ROLL CALL VOTE)
1. Approve Amendment to GKK Works agreement authorizing the additional $1,140,031
request for additional fees to perform expanded design and construction services for the
Civic Center, City Hall and Library, as outlined in this report.
2. Authorize the City Manager to approve the addition of the optional fee categories
outlined above, totaling $168,750, at a later date.
3. Adopt Resolution 2007- amending the 2007-2008 Capital Improvement Budget.
Attachment 1: Old vs. New Fees
Attachment 2: Design Fees — By Building/By Discipline/By Phase
Attachment 3: Work Plan
Attachment 4: Design Schedule
Attachment 5: Amendment No.3 to Agreement for Architectural Services
Attachment 6: Resolution No. 2007-
000148
ATTACHMENT 1
Moorpark City Hall & Library
Old vs. New Fees
6/6/2007
Current Invoiced/ Updated Contract
Contract Paid Contract Increase
City Hall&Site Work
10-Phase I Space Needs Study 16,142.00 16,142.00 16,142.00 -
20-Phase 11 Prelim Site/Campus Plan 58,236.00 58,236.00 58,236.00
30-Phase III Conceptual Design(Schematics-Old Scope) 171,052.00 29,078.84 29,078.84 (141,973.16)
30-Phase IIIA Conceptual Design(Schematics-New Scope) 296,020.00 154,046.84 _
40-Phase IVA Design Development 33,402.00 256,660.00 223,258.00
50-Phase IVB F&V Construction Document/Permit Approval 270,588.00 _ 591,840.00 321,252.00
60-Phase VI Bidding and Award 43,008.00 - 30,800.00 (12,208.00)
70-Phase VII Construction Administration 123,760.00 - 275,640.00 151,880.00
90-Phase VIII Close-out 25,588.00 - 23,810.00 (1,778.00)
Subtotal-City Hall&Site Work 741,776.00 103,456.84 1,578,226.84 836,450.84
Reimbursable Expense 2,500.00 - 29,500.00 27,000.00
Extra Services(Model&Fly Through Animation) 18,000.00 -_ 18,000.00
Subtotal-Reimburseables and Extra Services 20,500.00 - 47,500.00 27,000.00
Additional Services No. 1 -Master Planning 22,650.00 22,650.00 22,650.00 -
Additional Services No.2-Master Planning 27,400.00 27,400.00 27,400.00
Subtotal-Additional Services 50,050.00 50,050.00 50,050.00 -
Library -
Space Needs Study 28,860.00 28,860.00
Concept Design(Schematics) 123,440.00 123,440.00
Design Development 107,080.00 107,080.00
Reimbursable Expense 5,200.00 5,200.00
Extra Services(Model&Fly Through Animation) 12,000.00 12,000.00
Subtotal-Library 276,580.00 276,580.00
Total(before optional Extra Services) 812,326.00 153,506.84 1,9529356.84 1,140,030.84
Other Extra Services
Water Feature Design 50,000.00 50,000.00 _
City Hall-US Green Building Council LEED Certification 75,000.00 75,000.00
City Hall-Furniture Design&Selection 43,750.00 43,750.00
Subtotal 168,750.00 168,750.00
Total after optional Extra Services 812,326.00 153,506.84 2,121,106.84 1,308,780.84
000149
City of Moorpark Civic Center ATTACHMENT 2 gkkworks
Design Fees-By Building/By Discipline/By Phase
June 6,2007
CITY HALL,LIBRARY,&SITE WORK-COMBINED
Space Concept Design Construction Bid/ Construction
Needs Study Design Development Docs/Permit Award Admin Close-Out Total
gkkworks Architecture 11,760 136,360 110,440 248,240 7,000 163,690 7,610 685,100
Interior Design - 7,600 7,600 15,200 - 4,750 - 35,150
Specifications - - 7,000 10,000 - - - 17,000
Cost Estimating 7,500 13,500 10,000 - 31,000
Subtotal gkkworks 11,760 151,460 138,540 283,440 7,000 168,440 7,610 768,250
Page+Moris Library Programming 15,700 1,600 1,600 - - - - 18,900
Psomas Civil - 48,300 59,800 78,300 9,200 17,300 5,800 218,700
Professional Design Landscape - 10,800 22,900 30,500 1,500 4,400 1,000 71,100
Mactec Geotechnical - 35,700 - - - - - 35,700
Saiful/Bouquet Structural - 40,400 46,300 72,500 3,200 32,200 1,600 196,200
Gotama Mechanical/PlumtNng - 24,800 24,800 31,700 2,400 12,000 1,600 97,300
Electrical - 19,800 19,800 25,400 2,000 9,500 1,300 77.800
Low Voltage - 4,900 4,900 6,300 500 2,400 300 19,300
HLB Lighting - 8,800 11,700 20,500 2,900 11,700 2,900 58,500
SKA Design Signage&Graphics - 12,700 16,100 15,000 600 4,600 600 49,600
MCB Acoutics - 27,000 - - - - - 27,000
AudioNisual 13,200 - 13,200
Subtotal Consultants 15,700 248,000 207,900 280,200 22,300 94,100 15,100 883,300
Non-Reimbursable Expenses 1,400 20,000 17,300 28,200 1,500 13,100 1,100 62,600
Grand Total 28,860 419,460 363,740 591,840 30,800 275,640 23,810 1,734,150
CITY HALL&SITE WORK
Space Concept Design Construction Bid/ Construction
Needs Study Desion Development Docs/Permit Award Admin Close-Out Total
gkkworks Architecture - 73,120 59,360 248,240 7,000 163,690 7,610 559,020
Interior Design - 3,800 3,800 15,200 - 4,750 - 27,550
Specifications - - 4,000 10,000 - - - 14,000
Cost Estimating 4,500 6,000 10,000 20,500
Subtotal gkkworks 81,420 73,160 283,440 7,000 168,440 7,610 621,070
Page+Moris Library Programming - - - - - - - -
Psomas •Civil - 48,300 59,800 78,300 9,200 17,300 5,800 218,700
Professional Design Landscape - 10,800 22,900 30,500 1,500 4,400 1,000 71,100
Mactec Geotechnical - 24,200 - - - - - 24,200
Saiful/Bouquet Structural - 23,700 29,000 72,500 3,200 32,200 1,600 162,200
Gotama Mechanical/Plumbing - 15,900 15,900 31,700 2,400 12,000 1,600 79,500
Electrical - 12,700 12,700 25,400 2,000 9,500 1,300 63,600
Low Voltage - 3,200 3,200 6,300 500 2,400 300 15,900
HLB Lighting - 8,800 11,700 20,500 2,900 11,700 2,900 58,500
SKA Design Signage&Graphics - 12.700 16,100 15,000 600 4,600 600 49,600
MCB Acoutics - 27,000 - - - - - 27,000
Audio/Visual 13,200 13,200
Subtotal Consultants 200,500 171,300 280,200 22,300 94,100 15,100 783,500
Non-Reimbursable Expenses - 14,100 12,200 28,200 1,500 13,100 1,100 70,200
Total 296,020 256,660 591,840 30,800 275,640 23,810 1,474,770
LIBRARY
Space Concept Design Construction Bid/ Construction
Needs Study Design Development Docs/Permit Award Admin Close-Out Total
gkkworks Architecture 11,760 63,240 51,080 - - - - 126,080
Interior Design - 3,800 3,800 - - - - 7,600
Specifications - - 3,000 - - - - 3,000
Cost Estimating 3,000 7,500 - 10,500
Subtotal gkkworks 11,760 70,040 65,380 - - - - 147,180
Page+Moris Library Programming 15,700 1,600 1,600 - - - - 18,900
Psomas Civil - - - - - - - -
Professional Design Landscape - - - - - - - -
Mactec Geotechnical - 11,500 - - - - - 11,500
Saiful/Bouquet Structural - 16,700 17,300 - - - - 34,000
Gotama Mechanical/Plumbing - 8,900 8,900 - - - - 17,800
Electrical - 7,100 7,100 - - - - 14,200
Low Voltage - 1,700 1,700 - - - - 3,400
HLB Lighting - - - - - - -
SKA Design Signage&Graphics - - - - - - - -
MCB Acoutics - - - - - - - -
AudioNisual
Subtotal Consultants 15,700 47,500 36,600 - - - 99,800.
Non-Reimbursable Expenses 1,400 5,900 5,100 - - - - 12,400
Total 28,860 123,440 107,080 - - 259,380
000150
Moorpark City Hall&Libra --- - --
Work Pla;June Last Update: 6,2007 C11 HeII& SCHEMATIC DESIGN->> DESIGN DEVELOPMENT»»>
2007
Weeks: 6/28 7/5 7/12 7/19 7/26 8/2', 819 8/16 8/23'. 8/30 9/6 9113 9/20 9/27 10/4 10/11 10/18 10/25 11/1 11/8'. 11/15 11/22
Position Rate 1 2' 3 4 5 6'. 7 8 9 10 11 12� 13 14 15 16 17 18 19 20 21 22
Steve Wagner $190 Hrs: 0 0 0 0 6 6 6 6 2 2 2 2'� 2 2 4 4 4. 4 4 4 4 4
Pdncl I/Pr t Marra r $: 1,140 1,140 1,140 1,140 380 380 380 380 380 380 760 760 760 760 760 760 760 760
Edmund Einy $175. Hrs: 0 0 0 0 6, 6 6 6 2 2 2 2 2 2 2 2 2', 21 2 2' 2 2
Director ofDesign $: 1,050 1,050 1,050 1,050 350 350 350 350 350 . 350 350. 350 .350 350 350 350 350 350
Amit Bhargava 8160 Hrs: 0 0' 0 0 6 6' 6 6 4. 4 4 4, 4 4 6 6 6 6 6 6 6 6
Project Architect $: 960 960 960 960 640 640 640 640 640 640 960 960 960 960 960 960 960 960
Bevan Mitchell $135 Hrs: 01 0 01 0, 40 40 401 401 10 101 101 101 101 10 81 81 8-. 81 8 8'� 6 8
Senior Des firer $: 5,400 5,400 5,400 5,400 1,350 1,350 1,350 1,350 1,350 1,350 1,080 1,080 1,080 1,080 1,080 1,280 1,080 1,080
TBD $110 Hrs: 0 0� 0 0 0 0 0 0 0 0 0 0 0 0 20 20 20, 20 20 20' 20 20
JobCe Captain $: 2,200 2,200 2,200 2,200 2,200 2,200 2,200 2,200
Scott Brady $95 Hrs: 01
0 0 0 40 40'. 40 40 10 10 10 10, 10 10 20 20 20 20 20 20 20 20
Project Designer $: 3,800 3,800 3,800 3,800 950 950 950 950 950 950 1,900 1,900 1,900 1,900 1,900 1,900 1,900 1,900 D
TBD $85 Hrs: 0 0� 0 01 0 0 0 0 0 0 0 0' 0 0 0 01 0! 0 0 01 0 0
CAD Support $: - - - - - - - - - - -
Geneva Pickering $B5 Hrs: 01 0 0 01 2. 2 21 21 2 2! 21 2 21 2 21 2j 2 21 21 2 21 2
Admin Support 170 170 170 170 170 170 170 170 170 170 170 170 170 170 170 170 170 170 D
Architecture-Weekly Totals: Hrs: 0 0 0 0 100 100. 100 100 30 30 30 30, 30 30 62I 62 62. 62 62 62 62 62 0
$: 0 0 0 0 12,520 12,520 12,520 12,520 3,840 3,840 3,840 3,840 3,840 3,840 7,420 7,420 7,420 7,420 7,420 7,420 7,420 7,426 \T�
Architecture-Phase Totals: Hrs
580 496 2
$73 120 $59 360
Lauren Dossey Hrs: 0 0, 0 0 0 0, 0 0 0 0 0 0 20 20 0 0 0 0 0 0 20 20
o
Interior Desl ner $95 $: - - - - 1,900 1,900 - - - - - 1,900 1,900 M
Interior Design-Phase Totals: Hrs: 1 40 40 Z
$: $3,800 $3,800
Carol Johnson $125. H$,s: 0 0. 0 0 0 0'. 0 0 0 01 01 0 0 0 0 0 0 0 0 0 16 16
S 7ficetlons writer : - - - - - - 2,000 2,000 W
Hrs: 0 1 32
Specifications-Phase Totals: $: $0 $4,000
Tom Jicha $125. Hrs: 0 0 0 0 0 0 0 0 0 0 12 12 6 6 0 0 0 0 0 0'. 24 24
Cost Estimator $: - - - - - 1,500. 1,500 750 750 3,000 3,000
Cost Estimating-Phase Totals: Hrs: i $4,500 36 48
$, $6,000
Weekly Totals-Net: Hrs: 0 0 0 0 100 100 100 100; 30. 30 42 42 56 56 62 62 62 62 62 62 122 122
$: 0 0 0 0 12,520 12,520 12,520 12,520 3,840 3,840 5,340 5,340 6,490 6,490 7,420 7,420 7,420 7,420 7,420 7,420 14,320 14,320
Hrs:
Phase Totals-Net: : $81,420 $73,160
O
O
O
N
VV
IA
Moor ark Ci Hall&Libra
Work Plan
Last Update:June 6,2007 _ _ -
Clt HeII&Sit.
CONSTRUCTION DOCUMENTS»»>
Weeks: 11129 12/6' 12113 12/20 12/27 1/3 1/10 1/17 1/24 1/31 2/7 2/14 2/21 2/28 3/6 3/13 3/20 3/27
Position Rate 23 24 25 26 27. 28. 29 30 31 32 33 341 35 36 37 381 39 40
Steve Wagner $190 Hrs: 8 8 8 8 8'. 8, 8 8 8� 8 8 8' 8 8 8 8', 8 8
Pdnc 1/P tMe 'r $: 1,520 1,520 1,520 1,520 1,520 1,520 1,520 1,520 1,520 1,520 1,520 1,520 1,520 1,520 1,520 1,520 1,520 1,520
EdmundEiny Hrs: 01 0 0 0 0 0 0 0 0'., 0 0 0 0 0 0 0'. 0 0
Director of Design $175 $., _ -
_
Amit Bhargava 1 $160 Hrs: - 81 81 81 8 8 81 81 8 81 8 - 8 - 8 - 8 - 8 - 8 - 8 - 8
Project Architect $: 1,280 1,280 1,280 1,280 1,280 1,280 1,280 1280 1,280 1,280 1,280 1,280 1,280 1,280 1,280,1 1;280 1;280 1,280'
an Mitchell $135. Hrs: 4 4 4 4 4 4 4 4 4 0 0 0 01
0 0 0 0 0
SeniorDeslrw $: 540 540 540 540 540 540. 540 540 540 - - - - -
TBD 1 $110 Hrs: 40 40 40 40 40' 40', 40 40 40. 40 40 401 40 40 40 40! 40 40
Job Captain $: 4,400 4,400 4,400 4,400 4,400 4,400 4,400 4,400 4,400 4,400 4,400 4,400 4,400 4,400 4,400 4,400 4,400 4,400
Scott Brady $95 Hrs: 40 40. 40 40 40 46 40 40 40. 40 40 40'. 40 40 40 40 40 40
Project Designer $: 3,800 3,800 3,800 3,800 3,800 3,800 3,800 3,800 3,800 3,800 3,800 3;800 3,800 3,800 3,800 3,800 3,800 3,800
TBD $85 Hrs: 0 0' 0 0 0 0 0 0 0 0 0� 40' 401 401 4UI 40 401 40
CAD Support $: 3,400 3,400 3,400 3,400 3,400 3,400 3,400
Geneva Pickering $85 Hrs: 2 2 2 2 2'. 2 2 2 2 2 2 2 2 2 2 2 2 2
AdminSupport 170 170 170 170 170 170 170 170 170 170 170 170 170 170 170 170 170 170
Architecture-Weekly Totals: Hrs: 102 102. 102 102 102'. 102 102 102 102' 98 98 138 138 138 138 138 136 138
$: 11,710 11,710 11,710 11,710 11,710 11,710 11,710 11,710 11,710 11,170 11,170 14,570 14,570 14,570 14,570 14,570 14,570 14,570
Architecture-Phase Totals: Hrs' 2080
Lauren Dossey Hrs: 0 0 0 0 0 0 0 40 40 0 0i 0 0 0 0 0 40 40
InterlorDest ner $95 $: 3,800 3,800 - - - 3,800 3,800
Interior Design-Phase Totals: Hrs: 160
Carol Johnson 1 $125 Hrs: 01 0 0 01 0 0 01 01 0' 0 01 0 01 01 01 0 401 40
S 1/fcat7ons Writer $: - - - - 5,000 5,000
Specifications-Phase Totals: Hrs 80
Tom Jicha $125 Hrs: 01 0. 01 0 0 0 01 01 0. 01 0 0 01 0 01 0 401 40
Cost Estimator - - - - - 5,000 5 000
Cost Estimating-Phase Totals: Hrs 80
Weekly Totals-Net: Hrs: 102 102 102 1021 102 102'. 1021 1421 142 981 98 138 1387 1381 1381 138' 2581 258
$: 11,710 11,710 11,710 11,710 11,710 11,710 11,710 15,510 15,510 11,170 11,170 14,570 14,570 14,570 14,570 14,570 28,370 28,370
Phase Totals-Net: Hrs' (80 sheets @ 30 hr/sheet) 2400
Q
Q
Q
U't
Moorpark City Hall&Libra
Work Plan
Last Update:June 6,2007
Crt Hall Slte PLAN CHECK»»> CORRECTIONS&BACK CHECK»»> BIDDING A AWARD»»> CONSTRUCTION CLOSE-OUT
Weeks: 4/3 4/10 4/17 4/24 5/1 5/8 5/15 5122 5/29 6/5 6112 6/19 6/26 7/3 7/10 7/17 69 Weeks
Position Rate 41 42 43 44 45 46 47 48 49 50 51 52 53� 64 55 56 Total- Weekly Total Totals
Steve Wagner $190 Hrs: 21 2 21 2 2 2 21 2 11 1. 1 11 1 11 11 1 1 OOT 1.4 16 352
PrinctwillProfect Ma er $i 380 380 380 380 380 380 380 380 190 190 190 190 190 190 190 190 19,000 275 3,040 66,880
Edmund Einy $175 Hrs: 0 0' 0 - 0 0 0'. 0 0 0 0 0 0 0, 0 0 0 0 0.0 0 52
Director of Design - - - 9,100
Amit Bhargava 1 $160 Hrs: 0 - 0 37 - 8 8 - 8 - 8 - 1 - 1 - 11 11 1 11 11 1 507 0.7 0 330
Project Architect $ 1,280 1,280 1,280 1,280 160 160 160 160 160 160 160 160 8,000 116 52,800
Devan Mitchell $135 Hrs: 0 0 0 0 0, 0 0 0 ul 0 01 01 0 01 01 0 501 0.7 0 370
Senior Designer $: - - - 6,750 96 49,950
TBD $110 Hrs: 2 2 2 2 20 20 20 20 4 4 41 41 4 4 j 41 11047 16.0 40 2144
Job Captain $: 220 220 220 220 2200 2,200 2,200 2,200 440 440 440 440 440 440 440 440 121,440 1,760 4,400 235,840.
Scott Brady $95 Hrs: 0 0'. 0 0 0 0 0 0 0 0. 0 0 0. 0 0 0 0 0.0 0 1100
Pro t De ner $: 104,500
TBD $85 Hrs: 0 0 0 0 0 0, 0 0 0 0'i 0 0 0. 0 0 0 0 0.0 0 280
CAD Support $: - - - - 23,800
Geneva Pickering 1 $85 Hrs: 01 0 01 0 2, 2 21 2 11 1 11 11 1 11 11 1 1001 1.4 2 190
Admin Support $: 170 170 170 170 85 85 85 85 85 85 85 85 8,500 123 170 16.150
Architecture-Weekly Totals: Hrs: 4 4' 4 4 32 32 32 32 7 7 7 7 7 7 58
7 7 20.3
$: 600 600 600 600 4,030 4,030 4,030 4,030 875 875 875 875 875 875 875 875 2,372 7,610
Architecture-Phase Totals: Hrs. I 1 1 2224 56 14041 4818
$248,240 7,000 16300 49 920
Lauren Dossey 1 Hrs: 0 0 0 0 0' 0 0 0 0 0'. 0 0 0'I, 0 0 0 50 0.7 0 296
Interior Desi ner $95 $: - - 4,750 69 27,550
Interior Design-Phase Totals: Hrs: 1 1 160 1 1 1 1 1 0
$: $15,200 $0
Carol Johnson $125 Hrs: 01 0 01 0 0 0, 01 0 01 0 01 01 0 01 01 0 F7-o0 0 112
Specifications Writer $: - - - - - 14,000
Specifications-Phase Totals: Hrs: 80 0
$: $10,000 $0
Tom Jicha $125 Hrs: 01 0 01 0 0 0 0 0 01 0 01 01 0 01 01 0 0 0.0 0 164
Cost Estimator - - - - - 20,500
Cost Estimating-Phase Totals: Hrs: 80 0
$: $10,000 $0
Weekly Totals-Net: Hrs: 4 4 41 32. 32 321 32 71 7 71 71 7 7r- 71 7 21.1
$7 600 600 600 6001 4,030 4,030 4,030 4,030 875 875 875 875 875 875 875 875 2,441
Phase Totals-Net: Hrs: 1 1 2544 1 1 1 1 1 56 1454 58 5384
$: $283,440 $7000 $168440 $7,610 1621,070
�k k,.�,./o - -
O
O
O
N
CA
Cj
Moorpark City Hall&Ubrar ---_
Work Plan
Last Update: June 6,2007
Library SPACE NEEDS STUDY»»> SCHEMATIC DESIGN»»> DESIGN DEVELOPMENT»»>
2007 --- - ---
_Weeks: 6/28 7/5 7/12 7/19 7/26 812 8/9 8/16 8/23 8/30 916 9113 9/20 _ 9/27 10/4 10/11 10/18 10/25 11/1 11/8 11/15 11/22
--- - - - -_ --_. -._- _._- _.-
Position Rate 1'. 2 3 - 4 5� 6 7 8 9 10 11 12 13 14 -15 16. 17 18 19 20 21 22 Totals
Steve Wagner $190 Hrs: 8' 8 8 8 2 2 2 2 6 6 6 6 6 6 4 4'.. 4. 4 4 4 4 4 108
Princl llPro ect Manager $.. 1,520 1,520 1,520. 1,520 380 360 380 360 1,140 1,140 1,140 1,140 1,140 1,140 .760 760 760 760 760 760 760 760 20,520
Edmund Einy $175 Hrs: 2 2 2 2 2. ----27---27 2 6 6 6 6 6 6 1 1 1 1 1 1 1 1 60
Director Of Design $: 350 350 350 350 350 350 350 350 1,050 1050 1,050 1050 1,050 1,050 175 175 175 175 175 175 175 175 10,500
Amit Bhargava $160 Hrs: 0 0 0 0 0', 0 0 0 8 8 8': 8 8 8 4 4 4. 4 4 4', 4 4 80
Pr ' t Architect $: 1,280. 1,280 1,280 1,280 1,280 1,280 640 640 640 640 640 640 640_. 640 12,800
Devon Mitchell $135 Hrs: 01 0 0 0 0' 01 0 0 30 30 301 30 30 30 4 4 4 4 4 4'! 4 4 212
Senior Designer $: 4,050 4,050 4,050 4,050 4,050 4,050 540 540 540 540 540 540 540 540 26,620
Jo $110 Hrs: 0' 0 0 0 0 0 0 0 0 0 0. 0 0 0 20 20. 20 20 20 20 20 20 160
Job Captain $: - 2,200 2,200 2,200 2,200 2;200 2,200 2,200 . 2;200 17600
Scott Brady Hrs: 0 0 0 0 0 0 0 0 30 30 30 30 30 30 20 20' 20' 20 20 20' 20 20 340
Project Designer $95 $: - 2,850 2,850 2,850 2,850 2,850 2,850 . 1,900 1,900 1,900 1,900 1,900 1,900 1,900 1,900 32,300
TBD 1 $85 Hrs: 0 0' 0 0 0', 0 0 0 0 0 0 0 0 0 0 0' 01 0 0 0 0 0 0
CAD Su $: - - - - - - - - - - - - -
Geneva Pickering Hrs: 2 2 2 2 21 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2�. 2 2 44
Adm/nSu rt $85 $: 170 170 170 170 170 170 170 170 170 170 170 170 170 170 170 170 170 170 170 170 170 170 3,740
Architecture-Weekly Totals: Hrs: 12 12 121 121 6 6 61 6 821 821 82. 821 821 82 551 55 55 551 551 55 551 55 1004
$.- 2,040 2,040 2,040 2,040 900 900 900 900 10,540 10,540 10,540 10,540 10,540 10,540 6,385 6,365 6,385 6,385 6,385 6,365 6,385 6,365 126,080
Architecture-Phase Totals: Hrs 1 1 72 1 492 1 1 1 1 440
$.- $11,760 $63,240 $51,080
Lauren Dossey $95 Hrs: 0 0. 01 01 0. 01 01 0 01 01 0 01 201 20 01 0'. 0 01 01 0, 201 20 80
tnterforDesigner $: 1,900 11900 1,900 11900 7,600
Interior Design-Phase Totals: Hrs: 0 1 1 1 1 40 1 40
$; 0 $3,800 $3,800
Carol Johnson $125 Hrs: 0 0' 0 0 0 0 0 0 01 0 0, 01 0 0 0 0 0 0 01 0 72 12 24
Hlcat/ons Writer $: 1,500 1,500 3,000
Specifications-Phase Totals: Hrs: 0 0 24
$.- 0 $0 $3,000
Tom Jicha $125 Hrs: 0 0 0 0 0 0 0 0 0 0 0 0 12 12 0 0 0'; 0 0 0' 40 20 84
Cost Estimator $: - - 1,500 1,500 - - 5,000 2,500 10,500
Cost Estimating-Phase Totals: Hrs: 1 24 60
$: 0 $3,000 $7,500
Weekly Totals-Net: Hrs: 12 12. 12 12, 6 61 61 6 821 82 82 82 114, 114---55-F-55 55 55 55 55 127 107
$.- 2,040 2,040 2,040 2,040 900 900 900 900 10,540 10,540 10,540 10,540 13,940 13,940 6,385 6,365 6,385 6,385 6,385 6,365 14,785 f2,285
Phase Totals-Net: Hrs: 1 1 72 1 1 1 559---7 1 1 1 564 1192
$; $11,760 $70 040 $65,380 147,180
$11.760 $70,040 $65,360 $747,780
O
O
uu0
VR�
gkk orkl City of Moorpark Updated: 6/6/07
City Hall & Library
Design Schedule
2008 2009 20 I.
ID Task Name Duration Start Finish a Jun':Jul Aug', e Oct o Dec Jan a Ma lr a Jun 1. Jul Aug e Oct: o De Jan a Mar .Apr,. a Jun Jul Aug e Oct o DecJan
1 Notice to Proceed O days Wed 6/27/07 Wed 6/27/07 1: 6/27
2 8 wks Thu 6/28/07 Wed 8/22/07 '2 - .....................Programmmg-Library -
3 City Mtg No.1 0 days Wed 7/11/07', Wed 7/11/07 3 7/1
4 i; 12 wks Thu 7/12/07 Wed 10/3/07,....-; 4 ._......... ......... ----_.-.. ......... ----...-.. ...---...... .---------- --....---- ..........---------
Schematic Design(SD)-City Hall
-- -..._.............
................. ...... .. - _..... .. _............ ..............
5 City Mtg No.2 0 days Wed 7/25/07 Wed 7/25/07 5 7 25
6 City Mtg No.3 0 days Wed 8/8/07 Wed 8/8/07' 6 /8
...... .... ............-
7 City Mtg No.4 0 days Wed 8/22/07 Wed 8/22/07
8 Finalize Programming-Library 6 wks Thu 8/23/07 Wed 10/3/07 8
.....- -............_-
9 Schematic Design(SD)-Library 6 wks Thu 8/23/07 Wed 10/3/07 9
10 City Mtg No.S O days Wed 9/5/07 Wed 9/5/07 10
1 i Preliminary Cost Estimates 2 wks Thu 9/8/07 Wed 9/19/07. 11
..
12 City Mtg No.6 0 days Wed 9/19/07 Wed 9/19/07: 12 /19
. ................. ..... ....... - ... _....... ..... . .. .........1--- ..
.... -..-- .....
13 City Council Presentation and Approval 0days Wed 10/3/07' Wed 10/3/07; 13 10/3 D
....... ....._ .. ......... - .. ........ ......... ......
14 Design Development(DD)-City Hall 10 wks Thu 10/4/07', Wed 12/12/07 1
15 Design Development(DD)-Library 10 wks Thu 10/4/07 Wed 12/12/07 1
.....
16 City Mtg No.7 0 days Wed 10/17/07 Wed 10/17/07 1 1 10/1
............
17 City Mtg No.8 0 days Wed 10/31/07 Wed 10/31/07 17 10/11
18 City Mtg No.9 0days Wed 11/21/07 Wed 11/21/07 18 1121
19 Update Cost Estimates 3 wks Thu 11/22/07 Wed 12/12/07. 19 Z
... ....- _. ------ ...
20 City Review 3 wks Thu 11/22/07 Wed 12/12/07 20 y
21 City Mtg No.10-DD Approvals 0 days Wed 12/12/07 Wed 12/12/07 21 12/12
22 Construction Documents(CD)-City Hall 18 wks Thu 12/13/07 Wed 4/16/08 22
....
23 City Mtg No.11 0 days Wed 1/9/08 Wed 1/9/08 1/9
24 City Mtg No.12 0 days Wed 2/13/08 Wed 2/13/08 24 �/13
_. - -
25 City Mtg No.13 0 days Wed 3/19/08' Wed 3/19/08 25 119
26 :Update Cost Estimates
4 wks Thu 3/20/08 Wed 4/16/08 26
27 City Review 4 wks Thu 3/20/08 Wed 4/16/08 27
....... ......... _... _....... .. _.. -
28 City Mtg.No.14-CD Approvals 0 days Wed 4/16/08 Wed 4/16/08 28 4/16
29 Plan Check Review 4 wks Thu 4/17/08 Wed 5/14/08 29
30 'Corrections&Back Check 4 wks Thu 5/15/08 Wed 6/11/08 30
. .........._ ........_ ..... - ............
31 Council Presentation&CD Approval 0 days Wed 6/25/08 Wed 6/25/08 31 6/25
.......... ........... .... ..... ........... .......... . - ....... . ......
32 Bidding&Award 8 wks Thu 6/26/08 Wed 8/20/08 32
.. ........
33 Construction-City Hall 16 mons Thu 8/21/08 Wed 11/11/09 33
34 Construction Complete 0 days Wed ll/11/09 Wed l l/11/09 34♦ 11/11
o _
Library: Programming/SD/DD Design Task ( -j City Task
o City Hall: SD/DD/CD/Construction
070518_Moorpark_Design_Sched --- Page 1 of 1
ATTACHMENT 5
THIRD AMENDMENT TO AGREEMENT
FOR SERVICES
THIS THIRD AMENDMENT TO THE AGREEMENT FOR SERVICES ("Third
Amendment"), is made and entered into this day of June, 2007, ("the Effective
Date") between the City of Moorpark, a municipal corporation, hereinafter referred to
as "CITY", and GKK Works, a California Corporation, hereinafter referred to as
"ARCHITECT".
WITNESSETH:
WHEREAS, November 4, 2004, the CITY and the ARCHITECT entered into an
Agreement for architectural design and consulting services for a new City Hall/Civic
Center; and
WHEREAS, in October 2006, the CITY and the ARCHITECT entered into a First
Amendment to the Agreement for Services for additional master planning work; and
WHEREAS, in May 2007, the CITY and the ARCHITECT entered into a Second
Amendment to the Agreement for Services for additional master plan and design work;
and
WHEREAS, the ARCHITECT needs to increase their fees due to an expanded
scope of work; and
WHEREAS, the CITY wishes to amend the Agreement for Services a third time
to reflect this fee increase.
NOW, THEREFORE, in consideration of the mutual covenants, benefits, and
premises herein stated, the parties hereto agree as follows:
CITY does hereby appoint ARCHITECT in a contractual capacity to perform the
services in accordance with the terms and conditions hereinafter set forth in
Exhibit "A", for a not to exceed fee of $1,140,030.84, with the authorities, and
responsibility ordinarily granted to this type of architectural work. In addition, the
City Manager is authorized to approve optional services for an additional fee not
to exceed $191,750, as needed to complete the scope of work. All other terms
and conditions of the original agreement shall remain in full force and effect.
[SIGNATURES ON PAGE 2]
Professional Services Agreement Page 1 of 2
Third Amendment Between City of Moorpark and GKK Works
000156
ARCHITECT
CITY OF MOORPARK GKK WORKS
By: By:
Steven Kueny Stephen B. Wagner, AIA
City Manager Government Studio Lead
Date: Date:
ATTEST:
Deborah S. Traffenstedt, City Clerk
Attachment: Exhibit A — Architects Proposal and Fee Sheets
Professional Services Agreement Page 2 of 2
Third Amendment Between City of Moorpark and GKK Works
O001S'i
ATTACHMENT 6
RESOLUTION NO. 2007 -
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
MOORPARK, CALIFORNIA, AMENDING THE FY 2007/2008
CAPITAL IMPROVEMENT PROJECT BUDGET BY
ALLOCATING $1,308,781 FROM THE CITY HALL FACILITIES
FUND FOR ADDITIONAL ARCHITECTURAL DESIGN FEES
WHEREAS, on June 20, 2007, the City Council adopted the budget for Fiscal
Year 2007/2008; and
WHEREAS, on July 18, 2007, the City Council authorized Additional Architectural
Design services for the Civic Center Campus project; and
WHEREAS, a budget amendment is required to fund these costs.
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF MOORPARK
DOES HEREBY RESOLVE AS FOLLOWS:
SECTION 1. That a budget amendment in the amount of $1,308,781, as
described in Exhibit "A" attached hereto, is hereby approved.
SECTION 2. The City Clerk shall certify to the adoption of this resolution and
shall cause a certified resolution to be filed in the book of original Resolutions.
PASSED AND ADOPTED this 18th day of July, 2007.
Patrick Hunter, Mayor
ATTEST:
Deborah S. Traffenstedt, City Clerk
Exhibit A— Budget Amendment Resolution
000158
EXHIBIT A
BUDGET AMENDMENT FOR
CITY HALL FACILITIES FUND
CITY MANAGER'S DEPARTMENT
FY 2007-08
FUND ALLOCATION FROM:
Fund Account Number Amount
City Hall Facilities Fund 4001-5500 $ 1,308,781.00
Total $ 1,308,781.00
DISTRIBUTION OF APPROPRIATION TO EXPENSE ACCOUNTS:
Account Number Current Budget Revision Amended Budget
4001.2100.2007.9601 $ 665,161.00 $ 1,308,781.00 $ 1,973,942.00
$ - $ -
Total $ 665,161.00 $ 1,308,781.00 $ 1,973,942.00
Approved as to Form:
000159