SUBJECT: Consider Authorizing Recordation of the notice of
Completion for a Project to Construct Parkwy and Median
Landscaping Improvements on Princeton Avenue and Campus
Park Drive
On February 15, 1995, the City Council awarded a contract to
Cascade Sprinklers, Inc. for the construction of the subject
project.
The scope of the subject project included the construction of
irrigation and landscaping at the following locations:
• the parkways on the east and west sides of Princeton Avenue
(except the frontage of the commercial property);
• the medians on Princeton Avenue; and,
• the parkways on the south side of Campus Park Drive from
Columbia Street to Penn Street.
The construction of this project has been completed. The
ninety day maintenance period began on May 8, 1995. It is
anticipated that the improvements will be accepted for
maintenance by the City on August 9, 1995. Final payment of
the retention will be made at that time. It is appropriate,
therefore, to proceed with the recordation of the subject
Notice of Completion for this project.
R"5.cv
Parkway / Median Landscaping
June 1995
Page 2
C. Fiscal Impact
1. Total Project Cost Summary:
total project costs:
Design:
Construction:
Bid Price
Quantity Adjustments
Change Orders (a)
Inspection [ASA 92 -002]:
Contract Administration:
The following is a summary of
FY 1993194
8,000
8,000 (b)
72,915
0
5.445
Notes: (a) C. 0. 11: Renoval of buried asphalt in the median ......... 2,090.00
C. 0. 12: Reimbursement of utility service installation
costs per contract requirements ................ 3,445.40
5,445.40
(b) Inches design for Peach Hill Road parimays
78,450
475
0
78,925
2. FY 1994195 Budget: A re -cap of the approved budget for this
project is as follows:
Projected
Princeton Avenue 37,000 36,247 753
medians and parkways
023 - 400 - 903 -0221
Campus Park Drive 49.000 42,678 ¢.322
parkways
Total 86,000 78,925 7,075
Staff recommends that the City Council take the following actions:
1. Accept the work as completed, subject to satisfactory
completion of the maintenance period.
2. Instruct the City Clerk to file the Notice of Completion for
the project.
3. Authorize the release of the retention upon satisfactory
clearance of the thirty five (35) day lien period.