HomeMy WebLinkAboutAGENDA REPORT 2006 0503 CC REG ITEM 09DMoorpark City Council
Agenda Report
rrEM q. -D .
.i TY OF MOORPARK, CALIFORNIA
City Council Meeting
ot_
ACTION:
TO: The Honorable City Council
FROM: Yugal K. Lail, City Engineer / Public Works Director qQqp�__
BY: Ken Gilbert, Public Works Consultant
DATE: April 27, 2006 (Council Meeting 05- 03 -06)
SUBJECT: Consider Approval of the Seven -Year Capital Improvement Program
(CIP) for Streets and Roads for FY 2005/06 — FY 2011/12
OVERVIEW
In March of 2005, the City Council approved the City's first Capital Improvement
Program (CIP) for Streets and Roads. Each year staff will be revising and updating the
CIP to delete completed projects, add new projects and otherwise revise and update
the descriptions, cost estimates and funding sources set forth in the document. This
presents for approval, the first update of that program, for the period beginning with FY
2005/06 and ending with FY 2011/12.
DISCUSSION
A. Final Draft Document
A copy of the final draft of the subject CIP has been distributed to the City Council
under separate cover.
B. Chances from Last Year
Completed Projects: Some of the projects listed in last year's CIP have been
completed and, removed from the subject program and added to Appendix I:
List of Completed Projects. The projects added to that list are the 2004 and
2005 projects listed on pages 12 and 13 of that Appendix.
2. Added Projects: The subject program includes some new projects not listed in
last year's CIP a list of those new projects is as follows:
PW/YKL0W271RPT/0427M 000103
FY2005/06 - FY2011/12 Capital Improvement Program
May 3, 2006
Page 2
Code I Description i Page
124 _ Lighted Crosswalk_ Moorpark Avenue /Second Street B -25
�f_._��
125 Curb Radii Modification ! B -26
308 i Misc. Traffic Signal Improvements _ ___ -B -45
410 Princeton Ave Median Modification at Campus Park Dr 13-57
506 Misc. Drainage Improvements B -65
507 Arroyo Simi Channel Imp rovements ! B -66 i
G-- _.- - - ---_ .— ___- .------------- - - - - - ---------___ .....------------ .___�...._ - - --
508 ! Happy Camp Canyon Improvements B -67
C. General Description / Purpose
The subject CIP sets forth a list of planned municipal improvement projects for City
streets and related improvements. Proposed improvements for parks, buildings
and facilities are not included. Also, costs for general public works maintenance
programs (i.e. street marking, striping, regulatory signs, tree trimming, etc.) are not
included in this program as this type of Public Works Operations and Maintenance
expense is set forth in the annual Departmental Operating Budget.
The purpose and focus of the City's CIP is to provide the City Council with a tool
for planning and programming major public works capital improvement projects
over the next several years.
D. Seven -Year Program / Congestion Management Program
The subject CIP provides for the planning and programming of projects over a
seven -year period. In this way the CIP has been made compatible with the
Ventura County Transportation Commission's (VCTC) Congestion Management
Program (CMP). The CMP requires a seven -year projection of projects which
might enhance the traffic capacity on any street on the CMP Roadway Network. A
map of the CMP network and a chart listing the projects on that network, are set
forth in Section D of the CIP.
E. Priorities and Planning
The funding year shown for each project listed in the CIP is an indication of its
relative priority. Should the City Council wish to revise or amend the project
priorities, as reflected by the funding year recommendations set forth in the subject
draft document, it may approve the document subsequent to directing that specific
changes be made to funding year(s) for those projects of concern. If such action is
taken, the City Council minute action will be attached to the CIP as an addendum.
An alternative to such an action would be direction to staff that the next annual
PW/"L0W27/RPT 10Q27/OB
C;0(P14t'4
FY2005/06 — FY2011/12 Capital Improvement Program
May 3, 2006
Page 3
F
G
lJ
update of the CIP include or address certain priority concerns of the City Council.
Fiscal Year 05/06
The first year of the subject CIP is FY 2005/06. The funding amounts and sources
cited in the CIP for FY 2005/06 are consistent with the adopted FY 2005/06
Budget, revised to reflect actual FY 2004/05 carryover appropriations.
GASB -34
City staff monitors and maintains an Infrastructure Valuation Program consistent
with the requirements of the Government Accounting Standards Board Statement
No. 34 (GASB -34). The initial analysis which established the valuation of the City's
infrastructure, inventoried, quantified, categorized and valued (replacement cost
estimate) all of the City's capital assets. The current updated valuation amount for
the City's infrastructure assets, is over $222 million, with "street- related"
improvements valued at over $67 million.
That program also found that the annual depreciation rate for the City's existing
"street- related" infrastructure is over $1 million. Implied in that finding is a need to
spend $1 million per year on the City's existing street systems, just to keep them
"maintained" at their current condition or value. A summary of the projects listed in
the draft CIP, which prolong the life cycle of the existing infrastructure, is listed as
follows:
Project Description
102 AC Overlays
201 Sidewalk Repair
Total ? -Yr.
Annual
Funding ($)
Average ($)
3,000,000
428,571
210,000
30,000
3,210,000
458,571
It should be noted that the above amount is less than one -half the amount
recommended by the GASB -34 report.
Planning Commission Review
Section 65401 of the Government Code of the State of California requires the
Planning Commission to review the City's Capital Improvement Program each year
for the purpose of reporting to the City Council on the conformity of said document
with the City's General Plan. On January 24, 2006, the subject draft CIP was
presented to the Moorpark Planning Commission. The Commission adopted a
Resolution finding the draft CIP to be in conformance with the Moorpark General
Plan, with the following exception:
'The Circulation Element of the Moorpark General Plan designates
Moorpark Avenue to be a two lane local collector. Project 113:
PWNKL06027/RPT/OU27lO6 0 0 0 1 ! '�, 5
FY2005/06 — FY2011 /12 Capital Improvement Program
May 3, 2006
Page 4
Moorpark Avenue Widening calls for the widening of Moorpark Avenue
to more than two (2) lanes. Said project is, therefore, inconsistent with
the provisions of the Circulation Element of the Moorpark General
Plan."
It should be noted that staff is working on a project to update and revise the City's
Circulation Element. The changes anticipated include a different designation for
Moorpark Avenue which will allow for more than two (2) lanes of traffic.
1. Annual Review: Transportation and Streets Committee
On March 6, 2006, the Transportation and Streets Committee (Councilmembers
Harper and Millhouse) reviewed and discussed the subject draft CIP. The
Committee made only one comment about the document. The Committee noted
that, in light of the recent rejection of the North Park development, the City Council
may want to consider one or more projects to make improvements at and near the
intersection of Campus Park Drive and Collins Drive.
The staff recommendation is to adopt the CIP as is. That action presumes that, if
in the near future the City Council directs staff to proceed with the development of
other projects, then such would be added to the CIP at the next update. The traffic
signal modification at Collins Drive /Campus Park Drive is included in the list of
projects to be considered in the next CIP update, set forth in Section J of this
report. The FY 2006/07 update is scheduled for November of 2006, subsequent
to determination of the FY 2006/07 carryover budget amounts.
J. Future Projects
Some of the projects to be considered to be added in the next update include the
following:
• Collins Drive / Campus Park Drive Traff ic Signal Modifications
• Wicks Road AC Overlay.
K. Moorpark Redevelopment Agency
Projects identified in the CIP include projects proposed to be funded by the
Moorpark Redevelopment Agency (MRA). Approval of those projects and
necessary funding appropriations will be submitted to the MRA as needed.
L. Program Content
In addition to known projects planned to be constructed by either the City, the
MRA or private developers, a number of projects have been included in the CIP in
PW!VKL 06027!RPT ;04,27,06 000106
FY2005/06 — FY2011/12 Capital Improvement Program
May 3, 2006
Page 5
order to fully address the needs described in certain infrastructure planning
documents, noted as follows:
1. Circulation Element. All of the "future" arterial and collector streets identified
in the Circulation Element of the Moorpark General Plan, have been included
in the program;
2. Master Drainage Study. All of the "future" drains identified in the 1995 Master
Drainage Study, have also been included in the program.
M. Program Format
The projects listed in the CIP are organized into five categories listed as follows:
• Streets (including underground utility projects);
• Trails and Walkways;
• Traffic Signals;
• Medians and Parkways; and
• Storm Drains.
In the introduction there is a total program cost summary broken down into these 5
categories of projects.
N. Program Cost Estimate
Section A of the CIP provides a general introduction to the program and includes a
listing of the total program cost estimate (exceeding $71 million), summarized as
follows:
Section
100
Streets
200
Trails / Walkways
300
Traffic Signals
400
Medians & Parkways
500
Storm Drains
Total
O. Project Descriptions
Estimated
Program Cost ($)
47,835,269
2,903,320
986,106
3,532,822
16,345,000
71,602,517
Section B of the CIP sets forth a "Project Description" page for each project. The
information provided on each Project Description page includes estimated project
costs, recommended funding year and recommended funding sources.
It should be noted that there has been no detailed preliminary engineering
performed for most of the projects listed. The cost estimates are, therefore, very
preliminary in nature and will be subject to change as the full scope and
requirements of each project are developed.
PW,YKLO6W7 ; T*4Q7= �.f V V !.i'
FY2005/06 — FY2011/12 Capital Improvement Program
May 3, 2006
Page 6
P. Program Expenditure Summary
Section C of the CIP sets forth a table listing all projects in the CIP along with total
estimated project costs for each fiscal year of the program.
Q. Past Projects
In order to document past projects, Appendix `I' of the CIP lists all known major
capital improvement projects (for Streets and Roads) constructed since the City's
incorporation in 1983.
R. Funding Sources: Definitions
Attached as Appendix 'll' is a listing of the major funding sources for the program,
along with a description for each.
S. Conclusion
The subject CIP is designed to serve many purposes.
• It is a budget planning document.
• It is a funding source reference.
• It is a plan for the future improvement of the City.
• It is a list of infrastructure needs.
• It sets forth the scope and estimated cost of specific projects.
• It is a tool for prioritizing and scheduling capital improvement projects.
• It provides a list of projects already completed.
• It documents compliance with requirements of the Congestion Management
Program.
• But most of all, it is a "hands -on" working reference document to identify,
define and describe future planned capital improvement projects.
STAFF RECOMMENDATION
Approve the FY 2005/06 — FY 2011/12 Capital Improvement Program for Streets and
Roads.
PW1YKLOBW7,WTA)4Q7M O OO1 s , h
FY2005/06- FY2011/12 Capital Improvement Program
May 3, 2006
Page 7
Exhibit 1: CIP
The draft Capital Improvement Program for FY 2005/06 — FY 2011/12 has been
distributed under separate cover.
PW/YKLOGW7,RPTAXn7/O6 000109
City of Moorpark
Seven Year
Capital Improvement Program
for Streets and Roads
PPp.K c,4t�
�O
p�� 9
� a
q
2
o9ao9
FY05 /06 — FY 11/12
January 2006
Table of Contents
A. Introduction
B. Project Descriptions
Page
►a
100 Streets
101
8002:
Slurry Seal
B-2
102
Asphalt Overlay
B -3
103
Walnut Canyon Road
B -4
104
8026:
Spring Road Widening
B -5
105
8012:
Princeton Avenue Widening
B -6
106
8013:
Los Angeles Avenue Widening: Spring Road to Moorpark Avenue
B -7
107
8003:
Los Angeles Avenue Widening: Beltramo Ranch Road to Maureen Lane
B -8
108
Los Angeles Avenue Widening at Shasta Avenue
B -9
109
Underground Utility Projects
B -10
110
8051:
Underground District: L. A. Ave. Transmission Lines
B -11
111
8066:
Underground Utilities: New L. A. Avenue at the Arroyo Simi Bridge
B -12
112
8039:
Rail Crossing Improvements: Spring Road
B -13
113
8040:
Moorpark Avenue Widening
B -14
114
Casey Road Extension
B -15
115
8061:
North Hills Parkway
B -16
116
8056:
South Metro Link Lot Access Improvements
B -17
117
8045:
Route 23 North Realignment
B -18
118
Spring Road North Extension
B -19
119
`C' Street
B -20
120
Gabbert Road Rail Crossing
B-21
121
High Street [West] Reconstruction
B -22
122
Broadway Extension
B -23
123
Arroyo Drive Improvements
B -24
124
8064:
Moorpark Ave Lighted Crosswalk at Second Street
B -25
125
Lengthen Curb Radii at Designated Intersections
B -26
126
Los Angeles Avenue Widening West of Tierra Rejada Road
B -27
200
Trails and Walkways
201
8001:
Sidewalk, Curb & Gutter Reconstruction
B -30
202
Pedestrian / Bicycle Projects
B -31
203
8035:
Arroyo Simi Trail
B -32
204
8050:
Downtown Trail
B -33
205
8060:
Metro Link Pedestrian Access Improvements
B -34
206
8052:
High Street Streetscape Improvements
B -35
207
8059:
Drain No. 2 Trail
B -36
Table of Contents (Cont.
300
Traffic Signals
301
8003:
Los Angeles Avenue and Maureen Lane
302
8047:
Los Angeles Avenue and Shasta Avenue
303
8004:
Los Angeles Avenue Traffic Signal Interconnect
304
8036:
Tierra Rejada Road Traffic Signal Interconnect
305
8048:
Los Angeles Avenue and Millard Street
306
Los Angeles Avenue West of Butter Creek Road
307
8046:
Los Angeles Avenue / Tierra Rejada Signal Modification
308
Traffic Signal Controller and Operations Improvements
400
Medians and Parkways
401
8033:
Parkway: Los Angeles Avenue and Tierra Rejada Road
402
8047:
Medians: Los Angeles Avenue Corridor
403
8026:
Medians: Spring Road
404
8042:
Medians: Tierra Rejada Road
405
8048:
Parkway: Poindexter Avenue
406
SR -23 / Tierra Rejada Rd Interchange Landscaping
407
Median: Mt. Trail Street: Cedar Springs St. to Mountain Meadow Dr
408
City Entry Signs / Statements
409
Peach Hill Parkways
410
Princeton Avenue Median Modifications at Campus Park Drive
500 Storm Drains
501 Master Drainage Study
502 Gabbert Canyon / Walnut Canyon System Improvements
503 Shasta Drain
504 8065: Millard Drain
505 Villa Del Arroyo Drain
506 Miscellaneous Drainage Improvements
507 Arroyo Simi Channel Improvements
508 Happy Camp Canyon Improvement
C. Program Expenditure Summary
• Total Program Project Costs: Spread to Funding Year
• FY2005/06 Total: Spread to Funding Sources
• Total Program: Spread to Funding Sources
Pale
B -38
B -39
B -40
B -41
B -42
B -43
B -44
B -45
B -48
B -49
B -50
B -51
B -52
B -53
B -54
B -55
B -56
B -57
:.1
C -1
D. Projects on the Congestion Management Plan [CMP] Road Network D -1
Appendix `I': List of Completed Projects
Appendix `II': Description of Funding Sources
Cip2005_lntro 12/1/05
City of Moorpark
Capital Improvement Program
A. Introduction
This is the first update of the Seven Year Capital Improvement Program [CIP] for Streets and Roads for
both the City of Moorpark and the Moorpark Redevelopment Agency (MRA), adopted last year. This
revised program is for the period covering FY 05/06 through FY 11/12.
The primary purpose of this CIP is to provide the City Council with a framework for identifying,
planning and prioritizing needed municipal capital improvements for streets and roads. The year each
project is recommended to be funded, is an indication of the priority given to each project. The figures
cited in the FY 05/06 column, should be equal to the appropriations approved in the FY 2005/06
Budget for capital improvement projects for streets and roads (8000 series).
Projects have been organized into the five (5) Sections noted below. The projects identified in this
program include both City funded projects as well as major projects which are likely to be constructed
by land developers. The projects listed in Section 100 include future streets which are identified in the
Circulation Element of the Moorpark General Plan. The projects listed in Section 500 include future
needed storm drains identified in the Moorpark Master Drainage Study. Also included in Section 500
this year are certain projects of importance to the City which are planned to be constructed by the
Ventura County Watershed Protection District.
A brief description of the contents of this program is as follows:
• A: this Introduction;
• B: a project description page for each project;
• C: a summary of total program expenses by fiscal year;
• D: a list of the projects on the CMP Network [Congestion Management Program];
• Appendix `I': a list of all projects completed prior to the end of FY04 /05.
• Appendix 'IF: a description of the funding sources referenced herein.
A summary of the total estimated program expenditures is as follows:
Section
FY 05/06 w._.....__.._....
FY06 /07
- -- ..;......._..........._....._
FY07 /08
._.........._......._.... _.__..
FY08 /09
_...._..._... ............._.._ ..... _ ...... _:
_..__.__...__....--.._._.._.._..._._...__..._.__.._.._._....._......_ ..............__..........._........._........._......._...._......----.._._._.........._......
100 Streets
9,285,269
._..._._........_...........__-
7,330,000
4,920,000
8,350,000
— --
_.......- -.._.....__......_....._ .............-..._......_..............._.......__....._............_..._....._...._ _......__._...._......._.......
200 Trails & Walkways
- - - - --
183,320
..
- .._......-
320 000
- -...-
320 ........
....... _._.
300 . .__....._.........._....
_ _ .....
400 Medians / Parkways
Y._...._ ._.. _.._.._.._....._........
1 269 822
__.�..........- �_...._ _.. ._._..
190,000
._.._... _.._.._..._..._......
300,000
1,621,000
_. -.. - - -- _.
500 Storm Drains
......... __ ........ ...._.
195,000
100,000
50,00
200,000
Total .. _ .
11,719.,5.17
8,040,000
.._ ........._ ........._
5 690 000
....._... �_ _ _ �..
11,441,000
. .
....... _ ..... .. _..... _..- __ ..... _
Section
. _ ....... __ ..... _. _._ .... -__ ...... -............
FY 09/10
_ ... .... _....._.... ....... ........ ......... ..
FY10 /11
FYI 1/12
Total
... ...
100 Streets
....._._... - - - -- . _._..
6,450,000
6,000,000
5,500,000
47,835,269
_.
- ......
200 Trails & Walkways
... . Y..
................ . ......._ .
370,000
_......_. _.__ _.._.
270,000
... ....................
170,000
-
2,903,320
300 Traffic Signals
0
0
0
986,106
......... ._ ....__........._........._...._ .._........._....._ ..................._...........__........_.............._.._..._...
400 Medians / Parkways
-
._..........._....._._.._......
152,000
- - - - -;. _.
_....._._.__._ ...._.._.._ . _.........__._...._._.._....__.
0
...._ . ._ .....
__.._.._.__....._.._.._
0
.... ..___.__........._..._.___.__.;
3,532,822
- -.
500 Storm Drains
800,000
7,500,000
7,500,000
16,345,000
........._............ _......_ ......_........_ _ ... _ _ . ..............._ ....... .
Total
7,772,000
13,770,000
13,170,000
71,602,517
Cip2005_lntro
A - 1 12/1/05
City of Moorpark
Capital Improvement Program
B. Project Descriptions
Individual project descriptions are set forth in this section. Each project description
includes a location map, a project cost estimate, an implementation schedule, and
recommended funding sources.
The reader is advised that there has been no preliminary engineering performed for most
of the projects programmed in future years. Accordingly, the cost estimates provided for
those projects are very rough in nature and should not be relied upon to predict actual
costs. These "rough" estimates were included in the project descriptions in order to more
accurately depict the estimated total program costs. Individual project cost estimates
will be refined as preliminary engineering for each project is developed.
12/1/05
C ip2005_lntro
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name: Slurry Seal Program Code No. 101
Account No. 8002
Location Map
Various Streets (to be determined)
Project Description
This project provides for the application of slurry seal to various local and collector streets on a bi- annual
basis. Program objectives are to apply slurry seal to all such streets on a six (6) year cycle. The scope of
work often includes the removal and replacement of pavement in poor condition, and the application of
crack filler where needed. In that this is a reoccurring project, prior year costs are not shown. Past Slurry
Seal Projects are listed in Appendix `A'.
Project Funding Schedule Total Cost: $1,670,000 .
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Design 10,000
R -O -W
Construction 300,000
Inspection 10,000
Miscellaneous
Total N/A 320,000 0 400,000 0 450,000 0 500,000
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
2603: LTF 320,000 400,000 450,000 500,000
Total N/A 320,000 0 400,000 0 450,000 0 500,000
CIP2005 B -2 12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name: Asphalt Overlay Projects Code No. 102
Account No.
Location Map
Various Streets (to be determined)
Project Description
This project calls for the rehabilitation of certain City streets by constructing an Asphalt Overlay. The
scope of work often includes the removal and replacement of identified areas, the application of crack filler
where required and the use of pavement fabric to improve structural integrity and inhibit the reoccurrence
of existing cracks. The longevity of an Asphalt Overlay is approximately twenty (20) years. In that this is
a reoccurring project, prior year costs are not shown. Past A/C Overlay Projects are listed in Appendix `I'.
Project Funding Schedule Total Cost: $3,000,000 .
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Design
R -O -W
Construction
Inspection
Miscellaneous
Total N/A 0 1,000,0000 0 1,000,000 0 1,000,000 0
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
2603: LTF
Undetermined 1,000,000 1,000,000 1,000,000
Total N/A 0 1,000,000 0 1,000,000 0 1,000,000 0
CIP2005 B -3 12/1/05
City of Moorpark
!!
ram Capital Improvement Pro
P P g
!�
for Streets and Roads
Project Name:
Walnut Canvon Road
Code No. 103 .
Account No. - - --
Location Map
0 �
-z c �
�� wr
M ? D
I AVE
m;
ST.
{
1
Project Description
Construction
of additional pavement and a sidewalk on the west side of Walnut Canyon Road, north of
Casey Road. [Note: This project is proposed to be constructed by a developer.]
Project Funding Schedule Total Cost: $1,000,000
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10
FY 10 /11 FY 11/12
Design
R -O- W
Construction
Inspection
Miscellaneous
Total
0 0 1,000,000 0 0 0
0 0
Funding Sources
Source
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10
FY 10/11 FY 11/12
Undeter.
Developer
1,000,000
Total
0 0 1,000,000 0 0 0
0 0
CIP2005
B -4
12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
I
Project Name: Spring Road Widening: S/O New L. A. Avenue to Flinn Avenue Code No. 104 j
Account No. 8026
Location Map
--
L I !
F -A Y AVE. HARR
i I ]<10 I I �
rn '
SPRING rn R SPRING
=a■ ■■■■ Ran= ■■ ==MEN WWWOM ONE Wi ME ONENESS BEE W7 E
---1 �
z
r 11 EL] �D z
\, • N J I SCALE V = 300'
\ ;\ z I LLL, I� I
D , - - -- ITIl
rn
v�
Project Description
Construction of improvements and modifications to Spring Road from a point south of New Los Angeles
Avenue, northerly to Flinn Avenue. This project requires the acquisition of additional street right -of -way,
widening and new curb, gutter and sidewalk along the east side of the street. Ultimate improvements will
include four (4) travel lanes, six feet (6') wide bike lanes, a fourteen feet (14') wide landscaped median and
a double left -turn lane north of New L. A. Ave. The project extends south of New L. A. Avenue to
accommodate a shift of the centerline to the east. The project also includes new signal poles and New L. A.
Ave.
Project Funding Schedule Total Cost: 1,250,000
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Design 59,290 60,710
R -O -W 121,280 238,719
Construction 33,880 666,121
Inspection 70,000
Miscellaneous
Total 214,450 1,035,550 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
2501: L A AOC 214,450 1,035,550
Total 214,450 1,035,550 0 0 0 0 0 0
CIP2005 B -5 12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name: Princeton Avenue Realignment and Reconstruction Code No. 105
Account No. 8012
Location Map
W
9
5�
� Fz S ♦♦ �
A ♦♦♦ iR iN ♦♦ '�♦ ♦�
. ♦ ♦ ♦♦1 i R 5 b
MEMO
•♦ 7 PM 23 R
AAl ♦• 2
I•
♦� 10 PM 4 Ni
SCALE /* = 5 -00`
Project Description
Realignment and reconstruction of Princeton Avenue (formerly Los Angeles Avenue [East]) from a point
east of Spring Road easterly to South Condor Drive. Additional street right -of -way will be acquired to
provide an eighty -eight feet (88') corridor — sufficient to allow for future widening of the road to four
lanes. The project design provides for only one lane in each direction, with a paved median and paved
shoulders. The project plans call for the realignment and reconstruction of the street pavement, the
construction of storm drains and the construction of retaining walls as required. The walls on the north side
of the street will exceed twenty feet in height at some locations.
Project Funding Schedule Total Cost: $5,738,147
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Design 252,855 (8,608)
R -O -W 115,375 878,525
Construction 0 1,000,000 3,000,000
Inspection 0 100,000 400,000
Miscellaneous
Total 368,230 869,917 0 1,100,000 3,400,000 0 0 0
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
2501: L A AOC 368,230 869,917 1,100,000 3,400,000
Total 368,230 869,917 0 1,100,000 3,400,000 0 0 0
CIP2005 B -6 12/1/05
1
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name: Los Angeles Avenue Widening: Spring Road to Moorpark Avenue Code No. 106.
Account No. 8013
�I Location Map
-- ram -
PROJECT - -
:.:.:........ ......... c::_: : :::::::::::.: r��F....:.:..: ::::::::::::::::= :::....:::::..
a I J r IZ , - -
SCALE: V = 600'
Project Description
Widening of the street to provide for six (6) lanes of traffic. At Spring Road the centerline will be shifted to
the south to avoid taking right -of -way from the residential properties along the north side of the street. The
additional right -of -way will be taken from the south side of the street. At Moorpark Avenue the additional
street right -of -way will be acquired from the north side of the street. The project includes an additional
right -turn lane at Moorpark Avenue and a traffic signal at Millard Street.
Project Funding Schedule Total Cost: $2,751,789 .
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Design 351,388 185,433
R -O -W 436,669 724,055
Construction 24,900 926,770
Inspection 4,019 98,534
Miscellaneous
Total 816,976 1,934,793 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10 /11 FY 11/12
2501: L A AOC 816,976 1,138,023
2604: Grant 796,770
Total 816,976 1,934,793 0 0 0 0 0 0
CIP2005 B -7
12/1/05
r
i
City of Moorpark
j� Capital Improvement Program
I� for Streets and Roads
I
Project Name: - Los Angeles Avenue Widening at Beltramo Ranch Road Code No. 107 .
it AccoLlnt ':fro. 8003
Location Map
ii
I i �
I
j COMMERCE
j
i
01 V Y C T.
Lii
1 m
i PROJECT
Q SCALE: 1" = 300' �
1
t
LOS ANGELES AVE.
tr
NIGH i INGAL S
/ ? II
.� . i ! z
Project Description
The construction of street widening along the south side of Los Angeles Avenue from Beltramo Ranch
Road easterly to a point east of Maureen Lane. The project includes construction of a block walls, curb,
gutter, sidewalk, a paved shoulder, a storm drain in south Maureen Lane and a new traffic signal at
Maureen Lane. This project facilitates the placement of six (6) travel lanes once the highway widening
project east of Maureen Lane [Project 9108] is constructed.
Project Funding Schedule Total Cost: $1,664,375
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Design 176,171 13,806
R -O -W 129,780 4,920
Construction 73,759 1,165,938
Inspection 14,093 85,907
Miscellaneous
Total 393,803 1,270,571 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
2501: L A ACC 305,405 803,597
2604: Grant 466,975
Total 393,803 1,270,571 0 0 0 0 0 0
CIP2005 B -8 12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name: Los Angeles Avenue- Widening at Shasta Avenue Code No. 108
Account No. ----
wLocation Map
<
D I ty c DT SCOVE
----------
<
<
EVE EST
-J <
<
0 VEJ
0
Los Angeles Avenue
Project Description
This is a project to widen the south side of Los Angeles Avenue between a point east of Maureen Lane and
Leta Yancy Road, along the frontage of Tentative Tract 5053 [Pacific Communities]. The project is to
include a new traffic signal at the intersection of Los Angeles Avenue and Shasta Avenue. The City is
working with the Developer to enable the City to proceed with the construction of this project in advance
of the construction of the residential tract. Although the project is to be funded by the L A Ave AOC Fund,
all costs are to be reimbursed by the Developer.
Project Funding Schedule Total Cost: net: Zero
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Design 200,000
R-O-W
Construction 250,000 900,000 500,000
Inspection 50,000 100,000
Miscellaneous
Total 0 0 500,000 1,000,000 500,000 0 0 0
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Developer 0 0 500,000 1,000,000 500,000
Reimbursement
Total 0 0 500,000 1,000,000 500,000 0 0 0
CIP2005 B-9 12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name: Underground Utility Projects Code No. 109
Account No. N/A.
Location Map
Locations to be determined
Project Description
City costs related to the development and implementation of Underground Utility Projects and /or formation
of Underground Utility Districts for such purpose. This CIP project has been included in order to program
future "undergrounding" projects, the location and scope o which are to be determined. As projects are
identified, they will be added to the CIP as separate projects.
Project Funding Schedule Total Cost: 10,000,000 .
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10 /11 FY 11/12
Design
R -O -W
Construction
Inspection
Miscellaneous
Total 0 0 0 0 0 0 5,000,000 5,000,000
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10 /11 FY 11/12
Undetermined
Undetermined 5,000,000 5,000,000
Total 0 0 0 0 0 0 5,000,000 5,000,000
C1P2005 B -10 12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
a
Project Name: Underground Utility District: Los Angeles Avenue at Moorpark Avenue Code No. 110.. j
Account No. 8051. j
Location Map
I
- -a I -
PROJECT --
w; -- _- j-
m f �1 ,
_--
- LOS
t -! ANGELES ! %� I i AVE. . IF'
-- -
Ell
j� yI 1=-1 - it C - SCALE: 1 = 1000'
I II
Project Description
This project implements a new Underground Utility District proposed for the purpose of removing all poles
and "undergrounding" the six (6) high voltage transmission lines along the north side of Los Angeles
Avenue between Shasta Avenue and Moorpark Avenue. As noted below, a portion of the project funding is
proposed to come from the Southern California Edison Company, via PUC Rule 20A accruals.
Project Funding Schedule Total Cost: $1,496,448
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Design
R -O- W
Construction 240 726,208 770,000
Inspection
Miscellaneous
Total 240 726,208 770,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09 /10 FY 10 /11 FY 111112
2330: AD 92 -1 426,447
2501: LA ACC 240 299,761 470,000
Rule 20A 300,000
Total 240 726,208 770,000 0 0 0 0 0
CIP2005 B-11 12/1 /05
City of Moorpark
Capital Improvement Program
for Streets and Roads
ProJect Name: –Underground Utilities at the New Los Angeles Avenue Bridge
Code No. 111.
Account No. 8066
Location Map
= ___ -_=
- -- — -
TNN�PNNUN �J
AF
Project Description
This is a project to "underground" the overhead utilities wires on the north side of New Los Angeles
Avenue cast and west of the Arroyo Simi Bridge. Currently, project funding via the L A AOC is proposed
to be reimbursed from unexpended funds from the Community Facilities
District for the Moorpark
Marketplace project.
Project Funding Schedule
Total Cost: $300,000 .
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09
FY 09/10 FY 10/11 FY 11/12
Design 2,000
R-O-W
Construction 295,000 0
Inspection 3,000
Miscellaneous
Total 0 300,000 0 0 0
0 0
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09
FY 09/10 FY 10/11 FY 11/12
2501: LA AOC 300,000
Total 0 300,000 0 0 0
0 0 0
CIP2005 B-12
12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name:
Rail Road Crossing Improvements at Spring, Road
. Code No. 112)
.
Account No. 8039
Location Map
Princeton Avenue
HIGH ST.
PROJECT
zr!nk—�—, CIO
SCALE: 1 300'
Project Description
This project
will provide for widening the street and upgrading the rail crossing by adding a center median
and four (4)
crossing gates. The project also includes acquisition of additional right-of-way and street
widening on
the cast side of the street between the rail crossing and Princeton Avenue.
Project Funding Schedule
Total Cost: $380,000
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09
FY 09/10 FY 10/11 FY 11/12
Design
228 39,772
R-O-W
100,000
Construction
200,000
Inspection
40,000
Miscellaneous
Total
228 379,772 0 0 0
0 0 0
Funding Sources
Source
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09
FY 09/10 FY 10/11 FY 11/12
2603:LTF
114 189,886
2902: MRA
114 189,886
Total
228 379,772 0 0 0
0 0 0
CIP2005
B -1 3
12/1105
IF
City of Moorpark
Capital Improvement Program
for Streets and Roads
Pro ject Name:
I
Moorpark Avenue Widening Code No. 113.
Account No. 8040
.I
i
Location Map
I
o
I
I
j
_
CCNiiJEir AVE.
WRNETT AVE.
O
I
:;.
F NAVBMCFADDEN AVE. x- L-
>1 D _ PROJECT
AVE
h •.I•cmiL1_t_1— IT:. —
1 10 - --
Project Description
Widening to the west side of Moorpark Avenue between Casey Road and Third Street in order to provide
an additional southbound lane (when the project is completed, there will be two (2) southbound lanes and
one (1) northbound lane). The project design includes upgrading the rail crossing to add a center median
and four (4)
gates, and the realignment of First Street and Poindexter Avenue to eliminate the "off -set" at
this intersection.
The project will require acquisition of additional street right -of -way along the west side of
the street.
Project Funding Schedule Total Cost: $5,256,708
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09 /10 FY 10/11 FY 11/12
Design
179,761 820,239 0
R -O -W
600,000 200,000
Construction
156,708 3,000,000
Inspection
300,000
Miscellaneous
Total
336,469 1,420,239 3,500,000 0 0 0 0 0
Funding Sources
Source
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
2002: Traf Mit
90,336 709,664 1,750,000
2501: L A AOC
156,708 0
2902: MRA
89,425 710,575 1,750,000
0 0 0
Total
336,469 1,420,239 3,500,000 0 0
CIP2005
B -14 12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name: Casey Road Westerly Extension
Code No.
114
Account No. ----
Location Map
PROJECT
Vars Ty St
n
k� F6-
Moorpa k a`.
U,
2nd
Lrks An.--'i,
-'s Ave W Lo, AnqGIL, A*YG -n
)/-J'ikJfbwGF Ct Undo,- Anti
C I Park
Vista Levana br,
PGach Hill R
e ad C, w i Far
C% 51,
Co rk 70t, - - Pt �Lch Hill F'
G
Project Description
The Circulation Element of the Moorpark General Plan calls for the westerly
extension of Casey Road to
connect to Gabbert Road. This future project is to be constructed by one or more developers.
Project Funding Schedule
Total Cost: Developer
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09
FY 09/10 FY 10/11 FY 11/12
Design
R-O-W
Construction
Inspection
Miscellaneous
Total 0 0 0 0 0
0 0 0
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09
FY 09/10 FY 10/11 FY 11/12
Developer
Funded
Total 0 0 0 0 0
0 0 0
LCIP2005 B-15
12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name: —North Hills Parkway Code No. 115 .
Account No. 8061
Location Mar)
Dr.
chat"Vonsk-'ip
C:
C)
ez
U
PROJECT
4f
F1 I r —A
r) i a 0, 0 tl Y
T
. In 6L'.'iler All - IGH ST
rid -t
LassGn AVG
C,7
A,,,2 VV Lw Ar1(2-;k.5 AVG 71
aw"W" Project Limits
Roadway Alignment Identified in the Circulation Element
Project Description
The construction of a new east-west arterial street north of Casey Road. The westerly end of the street is
proposed to connect to Los Angeles Avenue, via a future railroad undercrossing, at a point west of Butter
Creek Road. Currently, the easterly terminus of this new street will be the northerly extension of Spring
Road. Segments of this project may be constructed by developers, and other segments funded by the
Citywide Traffic Mitigation Fund.
Project Funding Schedule Total Cost: 6,700,000
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Design 53,576 246,424 300,000 0
R-O-W 100,000 1,000,000
Construction 4,500,000
Inspection 500,000
Miscellaneous
Total 53,576 346,424 300,000 1,000,000 0 5,000,000 0 0
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
2002: Traf Mit 53,576 346,424 300,000 1,000,000 0 5,000,000
Total 53,576 346,424 300,000 1,000,000 0 5,000,000 0 0
C1132005 B-16 12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
i
Project Name:
%Metro Link South Lot Access
Code No. 116 .
Account No. 8056 .
Location Map
I 1 1 I 11
HIGH Z -
J
I
I
South Parking Lot
DOROTHY
FIRST ST. —\
U -- -
, L
-
w
Q
Q RUTH
- J
Project Description
This project
calls for the construction of a new access to the south Metro
Link parking lot from First Street.
When constructed the existing driveway on Moorpark Avenue would be
closed or restricted to right -turns
only. Traffic exiting the lot onto First Street would be able to access Moorpark Avenue at the signalized
intersection. This project is partially funded by a Federal CMAQ grant.
Project Funding Schedule
Total Cost: $497,795
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09
FY 09 /10 FY 10 /11 FY 11/12
Design
20,000
R -O -W
300,000
Construction
162,795
Inspection
15,000
Miscellaneous
Total
0 497,795 0 0 0
0 0 0
Funding Sources
Source
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09
FY 09/10 FY 10/11 FY 11/12
2603: LTF
365,000
2604: CMAQ
132,795
Total
0 497,795 0 0 0
0 0 0
CIP2005
B -17
12/1/05
I
City of Moorpark j
Capital Improvement Program
for Streets and Roads
II
i Project Name: Route 23 North Realiginment Code No. 117 .
Account No. 8045. j
Location Map
od
1.
l
- -- _-
South Connection
Alignment to be
Determined i
-�`
'll1
-
1
Project Description
The Circulation Element of the Moorpark General Plan calls for the construction of a new north -south
arterial street proposed to become the "realigned" Route 23 north of the freeway. Initial work requires
development of precise alignment study by a consultant to be retained by the City. That study would
include design concepts and cost estimates. One focus of that study will be to determine the feasibility of
relocating the Route 23 connection to the Highway 118 freeway, to a point other than New Los Angeles
Avenue.
Project Funding Schedule Total Cost: 4,550,000
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Design 150,000 100,000
R -O -W 1,000,000
Construction 3,000,000
Inspection 300,000
Miscellaneous
Total 0 150,000 100,000 1,000,000 3,300,000 0 0 0
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
2002: Trf. Mit. 150,000
undetermined 100,000 1,000,000 3,300,000
Total 0 150,0000 100,000 1,000,000 3,300,000 0 0 0
C1112005 B -18 12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name: Spring Road Extension
Code No. 118 .
jAccount
No. - - --
Location Map
Cn
m
I
O
.
6 , wwchc`i• j
1__
'
a
I
4' - -- "
_
-- —
1 _a, —� PRO"U,1,
.j
ail
r �+7`_� '- -- — -
S%'kING
(EXT ENSION'.
Project Description
The construction of the infrastructure by Pardee Homes, for Specific
Plan No. 2, to provide for the
extension of Spring Road northerly from Charles Street to connect to Walnut Canyon Road. Construction is
underway and is expected to be completed in FY 2005/06. There were no City funds used for the
construction of this new street. The project is shown here in order
to identify projects which are
implementing components of the Circulation Element of the General Plan.
Project Funding Schedule
Total Cost: Developer
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09
FY 09/10 FY 10 /11 FY 11/12
Design
R -O- W
Construction
Inspection
Miscellaneous
Total 0 0 0 0 0
0 0 0
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09
FY 09/10 FY 10 /11 FY 11/12
Developer
Funded
Total 0 0 0 0 0
0 0 0
CIP2005 B -19
12/1/05
City of Moorpark
i
Capital Improvement Program
for Streets and Roads
Project Name: `C' Street Code No. 119 . �I
Account No. - - --
Location Map
!L
1 7
PROJECT
ro
i Q
C;
C v
S� v
.� �ripui
4 ,� Canycr F +rk
a Si
�t�,
Project Description
The Circulation Element of the Moorpark General Plan calls for the construction of an east -west Local
Collector street along the northerly boundary of the City, from Grimes Canyon Road easterly to the
proposed "realigned" Route 23 [Project 117]. That portion of `C' Street west of Walnut Canyon Road was
provided via the construction of Championship Drive by the developer of the Moorpark Country Club
Estates [Tract 4928]. There are no plans to extend Country Club Drive east of Walnut Canyon Road. If
circulation needs in the area east of Walnut Canyon Road are to be met via other means, the Circulation
Element may need to be revised to delete this street segment. Until that action is taken, this project will
continue to appear in this Capital Improvement Program.
Project Funding Schedule Total Cost: Developer
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10 /11 FY 11/12
Design
R -O- W
Construction
Inspection
Miscellaneous
Total 0 0 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Developer
Funded
Total 0 0 0 0 0 0 0 0
CIP2005 B -20 12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name:
Gabbert Road Rail Crossing Improvements
Code No. 120
Account No. -
Location Map
'
i
i
I
PD OExtE� j
W �
u.
¢ w
m
m O
6' U
l7
O. W
Project Description
Construction
of street widening and related improvements on Gabbert
Road at the
rail crossing. It is
anticipated that this work will be undertaken by a developer.
Project Funding Schedule
Total Cost: Developer
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09
FY 09/10
FY 10/11 FY 11/12
Design
R -O- W
Construction
Inspection
Miscellaneous
Total
0 0 0 0 0
0
0 0
Funding Sources
Source
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09
FY 09/10
FY 10/11 FY 11/12
Developer
Total
0 0 0 0 0
0
0 0
CIP2005
B -21
12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name: High Street West
Code No. 121
Account No. ----
Location Map
EVERETT
STREET
'
�, �
o w
j
'
>
CHARLES
STREET
PROJECT
0 3
-J
HIGH
STREET
SCALE: 1" = 300'
Project Description
Widening, realignment, and reconstruction of High Street west of Moorpark Avenue.
The scope of work
would include a study to determine the precise alignment of this roadway project, as
well as the westerly
extension of the project to serve the properties
in this area.
Project Funding Schedule
Total Cost: $430,000
Prior Yrs FY 05/06
FY 06/07 FY 07/08 FY 08/09
FY 09/10
FY 10/11 FY 11/12
Design
30,000
R-O-W
80,000
Construction
300,000
Inspection
20,000
Miscellaneous
Total 0 0
110,000 320,000 0
0
0 0
Funding Sources
Source Prior Yrs FY 05/06
FY 06/07 FY 07/08 FY 08/09
FY 09/10
FY 10/11 FY 11/12
Undetermined
110,000 3320,000
Total 0 0
110,000 320,000 0
0
0 0
CIP2005
B-22
12,11/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name: Broadwav Extension Code No. 122
Account No. - - --
i
Location Map
=1
PROJECT
oil
(a itY .0 �Y ryccy,. y+
Project Description
The Circulation Element of the Moorpark General Plan calls for the easterly extension of Broadway to
connect to the Rt. 118 Freeway at a point east of the City. Although this street segment is not within the
City, it is shown in the Circulation Element in order to identify the long -term circulation needs of the City.
If all or any portion of this street segment is constructed, said construction will be undertaken by
developers. If alternative transportation routes are approved by the City, it may be necessary to revise the
Circulation Element.
Project Funding Schedule Total Cost: Undetermined.
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Design
R -O -W
Construction
Inspection
Miscellaneous
Total 0 0 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Undetermined
Total 0 0 0 0 0 0 0 0
CIP2005 B -23 12/1/05
City of Moorpark I
Capital Improvement Program
for Streets and Roads
Project Name:
Arroyo Drive Improvements Code No. 123 _ l
Account No. _
Location Map
I
1 AN ;.
REAG
'�,
_� . ; i� . _ ,y -. i _���• RONAED_.. I
I
.1
PSEO OEL�IATJJG VVY�
VEROE (PVT)
Project Description
The construction of street widening and other improvements on Arroyo Drive (formerly (Old) Los Angeles
Avenue], east
of Collins Drive. No funding source has yet been identified for this project.
Project Funding Schedule Total Cost: 1,000,000
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Design
R -O- W
Construction
Inspection
Miscellaneous
Total
0 0 0 0 0 1,000,000 0 0
Funding Sources
Source
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Undeter.
1,000,000
Total
0 0 0 0 0 1,000,000 0 0
CIP2005
B -24 12/ 1/05
i
City of Moorpark
Capital
Improvement Program
for Streets and Roads
Project Name:
Lighted
Crosswalk on Moorpark
Avenue at Second Street Code No. 124 .
Account No. 8064 .
Location Map
- :
IRS T S T. --
w
7
-cn-
Q
<
-
-
L _
w
N Q
w
- - -J E2 - - --
-
o
LJ-
SECOND S T.
_
a
-
-- - -- - cn
-
Q - -- — o
-
THIRD ST. m
Project Description
Construction of crosswalk lights in the
pavement at the crosswalk located on Moorpark Avenue [State
Route 23] and Second Street. This project is partially funded by a State Bicycle / Pedestrian facilities grant.
Project Funding Schedule Total Cost: $34,000
Prior Yrs
FY 05/06
FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Design
5,000
R -O -W
Construction
26,000
Inspection
3,000
Miscellaneous
Total
0
34,000
0 0 0 0 0 0
Funding Sources
Source
Prior Yrs
FY 05/06
FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10 /11 FY 11/12
2602: SB -821
13,000
2603: LTF
21,000
Total
0
34,000
0 0 0 0 0 0
C 1 P2005
B-25 12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name:
Lengthen Curb Radii at Designated Intersections on L. A. Avenue
Code No. 125 .
Account No. - - --
I
Location Map
Locations to be Determined
Project Description
This project
constructs
modifications to existing improvements on major arterials,
including the State
Highways, to lengthen the curb radii at certain corners to facilitate turning movements and ease congestion.
Project Funding Schedule Total Cost: $300,000
Prior Yrs
FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10
FY 10/11 FY 11/12
Design
50,000
R -O -W
100,000
Construction
150,000
Inspection
Miscellaneous
Total
0
0 50,000 100,000 150,000 0
0 0
Funding Sources
Source
Prior Yrs
FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10
FY 10 /11 FY 11/12
0
0
Undeter.
0
0 50,000 100,000 150,000
Total
0
0 50,000 100,000 150,000 0
0 0
CIP2005
B -26
12/1 /05
i
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name:
Los Angeles Avenue Widening West of Tierra Rejada Road
i
Code No. 126
Account No. k
jl
i
Location Map
i
i,
i
Los Angeles Avenue
; P
P
Project Description
The construction of street widening on Los Angeles Avenue west of Tierra Rejada
Road, as a function of
the development
of certain property in this area. This project is proposed to
be totally funded by
development.
It is shown here to reflect implementation of the Circulation Element of the Moorpark
General Plan.
Project Funding Schedule Total Cost: Developer .
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10
FY 10 /11 FY 11/12
Design
R -O -W
Construction
Inspection
Miscellaneous
Total
0 0 0 0 0 0
0 0
Funding Sources
Source
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10
FY 10 /11 FY 11/12
Total
0 0 0 0 0 0
0 0
CIP2005
B -27
12/1/05
h
CIP2005 B -28 12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name: Sidewalk,
Curb & Gutter Repair / Replacement
Code No. 201
Account No. 8001
Location Map
i
Various Locations (to be determined)
Project Description
Repair and reconstruction of curbs, gutters and sidewalks at various locations where required to remedy
damage incurred from tree
roots and other sources. This is an annually reoccurring project, thus no prior
year costs are shown.
Project Funding Schedule
Total Cost: $30,000 / year
Prior Yrs
FY 05/06 FY 06/07 FY 07/08 FY 08/09
FY 09/10 FY 10/11 FY 11/12
Design
R -O- W
Construction
30,000 30,000 30,000 30,000
30,000 30,000 30,000
Inspection
Miscellaneous
Total N/A
30,000 30,000 30,000 30,000
30,000 30,000 30,000
Funding Sources
Source Prior Yrs
FY 05/06 FY 06/07 FY 07/08 FY 08/09
FY 09/10 FY 10/11 FY 11/12
2605: Gas Tax
30,000 30,000 30,000 30,000
30,000 30,000 30,000
Total N/A
30,000 30,000 30,000 30,000
30,000 30,000 30,000
CIP2005
B -30
12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name: Bicycle / Pedestrian Facility Improvement Project Code No. 202
Account No. - - --
Location Map
I
I
The Location of Future Projects
To Be Determined
Project Description
The construction of bicycle
and/or pedestrian facility improvements, partially funded by a TDA Article 3
State grant [SB -821].
As projects are approved and added to the Budget, anew project will be added to the
CIP.
See Projects 124 and 205 for TDA Article 3 projects approved for FY 05/06.
Project Funding Schedule Total Cost: 240,000 .
Prior Yrs
FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Design
R -O- W
Construction
Inspection
Miscellaneous
Total 0
0 40,000 40,000 40,000 40,000 40,000 40,000
Funding Sources
Source Prior Yrs
FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
2603: LTF
20,000 20,000 20,000 20,000 20,000 20,000
2602: TDA -3
20,000 20,000' 20,000 20,000 20,000 20,000
Total 0
0 40,000 40,000 40,000 40,000 40,000 40,000
CIP2005
B -31 12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
i
Project Name: Arrovo Simi Trail Code No. 203
Account No. 8035
Location Map
Of
I.
_ .... y ��� : SIMI r
UJ
f _
Project Description
Prior Year costs are for the Arroyo Simi Trail Study. That study evaluated options for the possible future
development of a trail system, generally along the levee road of the Arroyo Simi, from the westerly City
Limit easterly to Madera Road in the City of Simi Valley. Future expenses are for projects to implement
segments of that system. FY 05/06 costs are for the design of "trail ramps" at the Tierra Rejada Road
Bridge. Ramps at the Spring Road bridge are included in the design for the channel improvements planned
by the Ventura County Watershed Protection District.
Project Funding Schedule Total Cost: $700,000.
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10 /11 FY 11/12
Design 150,000 50,000
R -O -W
Construction
Inspection
Miscellaneous
Total 150,000 50,000 50,000. 100,000 50,000 100,000 100,000 100,000
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
2001: TSM 0 50,000
2603: LTF 30,000
2604: CMAQ 120,000
undet. 50,000 100,000 50,000 100,000 100.000 100,000
Total 150,000 50,000 50,000 100,000 50,000 100,000 100,000 100,000
C IP2005 B -32 12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name: Downtown Trail Code No. 204
Account No. 8050
Location N'lap
El
Trail Routes to be Determined
o eT
❑ MDORPARK
CC MMUNITY
1� CENTER
MOORPARK ,�� _ 3 _ TTPI
J
COMMUNITY \ - - -_. _ it
SCHOOL �.' i
NUATION HIGH SCHOOL) �L 03 L H-
HIGH Si.
Project Description
Prior Year costs are for the Rail Trail Study. When that project proved to be not feasible, the scope of this
project was redirected to a study of the pedestrian and trail needs in the downtown area. This study will
draw heavily upon concepts set forth in the Downtown Specific Plan. A portion of the project is funded by
a TDA Article 3 State grant for bicycle / pedestrian improvements. The funding for future year projects has
not yet been determined. As of December 2005, the study was nearing completion.
Project Funding Schedule Total Cost: $376,755 .
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Design 58,919 17,836
R -O -W
Construction
Inspection
Miscellaneous
Total 58,919 17,836 100,000 50,000 50,000 100,000 0 0
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
2001: TSM 39,948 11,807
2602: TDA 18,891 6,029
Undetennined 100,000 50,000 50,000 100,000
Total 58,919 17,836 100,000 50,000 50,000 100,000 0 0
CIP2005 B -33
12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name:
Metro Link Pedestrian Access
Code No. 205
INTO. 8
Account N 060
Location Map
—J
:Z:
LLJ
CHARLES
cr_
I
G7 W
<
L L J ML
HIGH
S. P. R. R.
Project Description
This project is for the construction of a pedestrian walkway and ramp connecting the Metro Link Station
train platform
to High Street.
Project Funding Schedule
Total Cost: $32,000..
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09
FY 09/10 FY 10/11 FY 11/12
Design
0 5,740
R-O-W
Construction
25,260
Inspection
1,000
Miscellaneous
Total
0 32,000 0 0 0
0 0 0
Funding Sources
Source
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09
FY 09/10 FY 10/11 FY 11/12
5000: TDA-8c
19,400
2602: TDA-' )
12,600
Total
0 32,000 0 0 0
0 0 0
CIP2005
B-34
12/1105
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name:
OJ
High Street Streetscape Code No. 206
Account No. 8052
Location Map
U)
0
1 CD
< <
S. P. R. R.
Project Description
Prior Year costs
were for a survey of High Street, and properties south of High Street, between Moorpark
Avenue and Spring Road. FY 05/06 and future year costs are for projects to construct improvements to
parking and pedestrian facilities along High Street. The funding for future year projects has not yet been
determined,
Project Funding Schedule Total Cost: $1,060,000
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Design
12,525 47,475
R-O-W
Construction
950,000
Inspection
50,000
Miscellaneous
Total
12,525 47,475 0 0 1,000,000 0 0 0
Funding Sources
Source
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
2902: MRA
12,525 0
2904: MRA
47,475
Undet.
1,000,000
Total
12,525 47,475 0 0 1,000,000 0 0 0
CIP2005
B-35 12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name: Drain No. 2 Trail Code No. 207
Account No. 8059
Location Map
00
cr
'is #
-J, ..........
NVOV
V4
ea
Project Description
This project is to provide for the construction of a trail extending from the cast end of Campus Park Drive,
across the watercourse referred to Drain No. 2, then south under the freeway through an existing access
tunnel to Los Angeles Avenue. Prior year and FY 05/06 costs are for the development of a feasibility study
to determine access and design requirements. As of December 2005, the study was nearing completion.
Future costs are for the acquisition of those access rights, preparation of the design and construction of the
project. Cost estimates for this project have not yet been developed and the funding for future year projects
has not yet been determined.
Project Funding Schedule Total Cost: $530,000.
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Design gn 23,991 6,009
R-O-W
Construction
Inspection
Miscellaneous
Total 23,991 6,009 100,000 100,000 1,00,000 100,000 100,000 0
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
2001: TSM 23,991 6,009
undetermined 100,000 100,000 100,000 100,000 100,000
Total 23,991 6,009 100,000 100,000 100,000 100,000 100,000 0
CIP2005 B-36 12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name:
Traffic Signal: Los Angeles Avenue & Maureen Lane
Code No. 301
Account No. 8003 II
Location Map
G
z
w
— UJ
DI V Y CT.
- - -- -
PROJECT
O
SCALE 1 ' = 300'
O
U
LOS ANGELES
AVE
I1
Project Description
The Los Angeles Avenue Widening Project at Beltramo Ranch Road [Project 107] included the
construction of a traffic signal at the intersection of Los Angeles Avenue and Maureen Lane.
Project Funding Schedule
Total Cost: See #107
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09
FY 09/10 FY 10/11 FY 11/12
Design
R -O -W
Construction
Inspection
Miscellaneous
Total
0 0 0 0 0
0 0 0
Funding Sources
Source
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09
FY 09/10 FY 10/11 FY 11/12
Total
0 0 0 0 0
0 0 0
CIP2005
B -38
12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name: Traffic Signal: Los Angeles Avenue & Shasta Avenue
Code No. 302
Account No. ----
Location Map
Li
SIEER
< LIJ
DI V Y CT.
<
2
Cf) EVE EST
< VE.
LOS ANGELES AVE.
PROJECT
SCALE: 1" = 300'
Project Description
The Los Angeles Avenue Widening Project at Shasta Avenue [Project 108] included the construction of a
traffic signal at the intersection of Los Angeles Avenue and Shasta Avenue.
Project Funding Schedule
Total Cost: See #108
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09
FY 09/10 FY 10/11 FY 11/12
Design
R-O-W
Construction
Inspection
Miscellaneous
Total 0 0 0 0 0
0 0 0
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09
FY 09/10 FY 10/11 FY 11/12)
Total 0 0 0 0 0
0 0 0
CIP2005 B-39
12/1/05
i
City of Moorpark
i
Capital Improvement Program
for Streets and Roads
I
I
�I Project Name: Traffic Signal Interconnect: Los Angeles Avenue Code No. 303
I� Account No. 8004
Location Map
PROJECT
Zi
i
�• e
' S i
It t r j L
n?� - -
f ,
Project Description
The construction of a "hardwire" traffic signal interconnect system to allow for the coordination of all of
the traffic signals along the Los Angeles Avenue / New Los Angeles Avenue corridor [SR 118]. The
objective of the project is to "platoon" the east -west traffic in a more effective way, in order to reduce
congestion and exhaust emissions. The project is partially funded by a Federal "air quality" grant.
Project Funding Schedule Total Cost: $248,215
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10 /11 FY 11/12
Design 34,439 25,561
R -O -W
Construction 18,215 130,000
Inspection 40,000
Miscellaneous
Total 52,654 195,561 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
2501: L A AOC 52,654 105,561
2604: CMAQ 90,000
Total 52,654 195,561 0 0 0 0 0 0
CIP2005 B -40 12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
I
Project Name: Traffic Signal Interconnect: Tierra Rejada Road Code No. 304
Account No. 8036
Location Map
I/
4 _ 3
1
PROJECT
Ii7,
� s £
Project Description
The construction of a "hardwire" traffic signal interconnect system to allow for the coordination of all of
the traffic signals along Tierra Rejada Road between Los Angeles Avenue (SR -118) and the Route 23
freeway. The objective of the project is to "platoon" the east -west traffic in a more effective way, in order
to reduce congestion and exhaust emissions. The project is partially funded by a Federal "air quality"
grant.
Project Funding Schedule Total Cost: $486,000
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10 /11 FY 11/12
Design 33,105 16,895
R -O- W
Construction 14,000 382,000
Inspection 40,000
Miscellaneous
Total 47,105 438,895 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09 /10 FY 10 /11 FY 11/12
2502: STRAOC 47,105 102,895
2604: CMAQ 336,000
Total 47,105 438,895 0 0 0 0 0 0
CIP2005
B -41 12/t;05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name: Traffic Siy-nal: Los Angeles Avenue & Millard Street Code No. 305
j Account No. - - --
Location Map
Y �® ,g T R
a
j 0 _ PROJECT — Q
I 0 MAN
LL-
( S T. HWY. 118 ) LOS ANGELES AVE.
FUTURE
STREET �� - - - -j� 1 SCALE r = soo'
Project Description
The Los Angeles Avenue Widening Project between Moorpark Avenue and Spring Road [Project 106]
includes the construction of a traffic signal at the intersection of Los Angeles Avenue and Millard Street.
This project will be partially funded by the developer of property south of the intersection [Shea Homes –
Tentative Tract 5133].
Project Funding Schedule Total Cost: See # 106
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Design N/A N/A 0 0 0 0 0 0
R -O -W
Construction
Inspection
Miscellaneous
Total 0 0 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09 /10 FY 10 /11 FY 11/12
Total 0 0 0 0 0 0 0 0
CIP2005 B -42 12/l/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name: Traffic Signal: Los Angeles Avenue West of Butter Creek Road Code No. 306
Account No. - - --
Location Map I
�, _ _10�� fat' r✓v i � � ��"� _
wyF E +;erettSl r b—_,, , Y'lPinia o11ny
Moorpa k
-Y, Ave r x
I 2nd St ro w cz
'`� -4-4- Lassen:AVe I= .` f,
oft*
t3(
Lc�s Angeles Aye ` W Los Angeles Ave K r
Unida Avg
:.
PROJECT Gle rill wROi Parl.. i1 (9 �r 2~�
Vita Levana DYE,,
X Pdach Hill P�
f, ��, A nuunra.in
d
0 °P�+,. Fle.x�u4J. Furl " TZ
..
Peadl Hill Park
Project Description
This project is for the construction of a traffic signal at the future intersection of Los Angeles Avenue and
the westerly terminus of the North Hills Parkway [see Project 115].
Project Funding Schedule Total Cost: See #115
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10 /11 FY 11/12
Design
R -O -W
Construction
Inspection
Miscellaneous
Total 0 0 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Total 0 0 0 0 0 0 0 0
I
CIP2005 B -43 12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name: Traffic Signal Modification: Los Angeles Avenue and Gabbert Road Code No. 307
Account No. 8046
Location Map
COMMERCE
t-
- Ct,
PROJECT w
m --
m - -- --
SCALE 1" = 300'
LOS ANGELES AVE.
NIGHTINGALE S 1 .
T_
Project Description
This project calls for the modification of the traffic signal at this intersection to provide protected phases
(Left Green Arrows) for the north and south legs of the intersection. The design will also evaluate the
possible use of permissive /restricted traffic controls.
Project Funding Schedule
Total Cost: 160,000
Prior Yrs
FY 05/06
FY 06/07 FY 07/08 FY 08/09
FY 09/10 FY 10 /11 FY 11/12
Design
8,350
21,650
R -O- W
Construction
127,000
Inspection
3,000
Miscellaneous
0 0 0
Total
8,350
151,650
0 0 0
Funding Sources
Source
Prior Yrs
FY 05/06
FY 06/07 FY 07/08 FY 08/09
FY 09/10 FY 10/11 FY 11/12
2501: L A AOC
8,350
151,650
Total
8,350
151,650
0 0 0
0 0 0
B -44
12/1/05
CIP2005
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name:
Traffic Signal
Controller and Operations Improvements
Code No.
308
Account No.
- - --
Location Map
Various Locations
Project Description
This project
is for the
construction of controller and other hardware,
improvements, and/or
for the
upgrading of
traffic signal
operations through improved software, at designated intersections.
Project Funding Schedule
Total Cost: 200,000
Prior Yrs
FY 05/06 FY 06/07 FY 07/08 FY 08/09
FY 09/10 FY 10/11
FY 11 /12
Design
R -O -W
Construction
Inspection
Miscellaneous
Total
0
0 100,000 100,000 0
0 0
0
Funding Sources
Source
Prior Yrs
FY 05/06 FY 06/07 FY 07/08 FY 08/09
FY 09/10 FY 10 /11
FY 11/12
Undetermined
100,000 100,000
Total
0
0 100,000 100,000 0
0 0
0
CIP2005
B -45
12/1/05
i
CIP2005 B -46 12/1/05
CIP2005
Medians & Parkways
LOU In
12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name: Parkways: Los Angeles Avenue and Tierra Rejada Road Code No. 401
Account No. 8033
Location Map
i
'I
Los Angeles Avenue - - -
-
i
- -, i
N
W E
7 _
- j s
Project Description
Prior year costs were for the replacement of parkway trees on the east side of Tierra Rejada Road at
Courtney Lane. Future costs are for the installation of irrigation and landscaping on the west side of Tierra
Rejada Road and along the south side of Los Angeles Avenue east and west of Tierra Rejada Road. The
scope of work will extend to the new parkways created by the recent widening east and west of Maureen
Lane. Past costs to Fund 2300 was funded by a developer fees.
Project Funding Schedule Total Cost: $293,673
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Design 4,727 2,272
R -O- W
Construction 36,899 244,7753
Inspection 5,000
Miscellaneous
Total 41,626 252,047 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
2150: Lndscpe 14,462 17,539
2300: AD84 -2 7,315 0
2501: L A AOC 1,882 216,970
2605: Gas Tax 17,968 17,539
Total 41,626 252,047 0 0 0 0 0
CIP2005 B -48 12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name: Medians:
Los Angeles Avenue Corridor Code No. 402
Account No. 8047
iiLocation
Map
1'
_ . ( PROJECT
' X11•
A ' <
(c'
I
Project Description
This project calls for the construction of raised center medians along Los Angeles Avenue and New Los
Angeles Avenue, from the
freeway westerly to Butter Creek Road. A detailed costs estimate for this project
has not yet been developed. A funding source for future maintenance has not yet been determined.
Project Funding Schedule Total Cost: $1,670,000.
Prior Yrs
FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Design
30,000 40,000 11600,000
R -O -W
Construction
Inspection
Miscellaneous
Total 0
30,000 40,000 0 1,600,000 0 0 0
Funding Sources
Source Prior Yrs
FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
2501: L A AOC
30,000 40,000 1,600,000
Total 0
30,000 40,000 0 1,600,000 0 0 0
CIP2005
B -49 l2ii /o5
City of Moorpark
Capital Improvement Program
i
for Streets and Roads
Project Name:
Medians: Spring Road
Code No. 40;
j
Account
No. 8026
!,
Location Map
ICI
_ __ } D -- f► - -- - -} -.. IL I
rn` _ I-1
HARRY AVE. HARRY
-- -i
- _ I
- --�-
1
SPRING RD.
—I
m
o
� SPRING RD. SPRING RD. C 7J7
C1T] Z
[ICFD� z PROJECT
—d/
St R GEO Cr. j
[ID LTTI
-
z
fill UB
CEII - MINOR ST.
m
— CEiI ® y T
— �: m
n
Eff
..
fly Fffl
® IBI `"
co
EE1 [Fil
Ila] EEO
1 /
[FT
�
EM ZACHAIRY
® (PVT.) T.
Y
i
Project Description
The Spring Road Widening Project [Project 1041 includes the construction of raised, landscaped medians
between New
Los Angeles Avenue and the rail crossing.
Project Funding Schedule
Total Cost:
See No. 104
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09
FY 09/10 FY
10/11 FY 11/12
Design
R -O -W
Construction
Inspection
Miscellaneous
Total
0 0 0 0 0
0
0 0
Funding Sources
Source
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09
FY 09/10 FY
10,111 FY 11/12
Total
0 0 0 0 0
0
0 0
CIP2005
B -50
12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name:
oJ
Medians: Tierra Reiada Road — East of Spring Road Code No. 404
Account No. 8042
Location Map
PROJECT
1, SCALE: 1 = 600'
it
15
Project Description
The installation of landscaping and irrigation in the existing raised median. Prior year costs were for the
installation of conduits connecting the median segments.
Figures below include Resolution No. 2005-2376 [9-7-05]
Project Funding Schedule Total Cost: $943,455.
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Design
30,366 1,634
R-O-W
Construction
40,314 866,141
Inspection
5,000
Miscellaneous
Total
70,680 872,775 0 0 0 0 0 0
Funding Sources
Source
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
2502: STR AOC
70,680 872,775
Total
70,680 872,775 0 0 0 0 0 0
CIP2005
B-51 12/1/05
I
City of Moorpark
Capital Improvement Program
for Streets and Roads i
Project Name: Parkway:
Poindexter Avenue Code No. 405
Account No. 8048
Location Map
i'!
I
PROJECT
ii
�--- UNION PACIFIC_ SCRRA - �=
LF
'Ct
I>
SCALE: 1" = 600'
� a
m �
Project Description
This project calls for the installation of trees and shrubs, with irrigation, along the north side of the street
east of Gabbert Road,
on railroad property. This project will require the approval by the Southern
California Regional Rail Authority [SCRRA] for the easterly portion, and the Union Pacific Railroad [UP]
for the westerly portion.
A funding source for future maintenance costs has not yet been determined.
Project Funding Schedule Total Cost: $115,000.
Prior Yrs
FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10 /11 FY 11/12
Design
10,000
R -O- W
Construction
100,000
Inspection
5,000
Miscellaneous
Total 0
115,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs
FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
2150: Trees
115,000
Total 0
115,000 0 0 0 0 0 0
CIP2005
B -52 12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
i
i
Project Name: _ Freeway Landscaping at the Tierra Rejada Road Interchange Code No. 406
i
Account No. - - --
Location Map
�I
I � �
z
Q
I
I
d
I
j
(ST. HWY. 23)
`cE cry
P /-�
CHOLARTREE CT
�. -- 29
Project Description
This project calls for the installation of irrigation and landscaping in the Tierra Rejada Road median at and
adjacent to the State Route 23 Freeway, and within the loop ramps at this freeway interchange. This project
will require a Cooperative Agreement with Caltrans related to City funding of both construction and future
maintenance of this landscaping. A project cost estimate has not yet been developed.
Project Funding Schedule Total Cost: $230,000
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09,10 FY 10 /11 FY 11/12
Design 30,000
R -O -W 200,000
Construction
Inspection
Miscellaneous
Total 0 0 30,000 200,000 0 0 0 0
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Undet. 30,000 200,000
Total 0 0 30,000 200,000 0 0 0 0
CIP2005 B -53 12n/05
r I
City of Moorpark
Capital Improvement Program
for Streets and Roads I
Project Name: Mountain Trail Median Code No. 407 I
Account No. - - --
' Location Map
.,° s re8i�,
S
r —1
-J r14
Ed , [� r
Project Description
This project is for the construction of a landscaped median in Mountain Trail Street from Cedar Springs
Street westerly to Mountain Meadow Drive. Preliminary survey engineering work for this project has been
completed. The source of funding for both construction and future maintenance costs has not yet been
determined.
Project Funding Schedule Total Cost: $120,000 .
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Design 20,000
R -O -W
Construction 100,000
Inspection
Miscellaneous
Total 0 0 0 0 20,000 100,000 0 0
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Undet.
Undeter, 20,000 100,000
Total 0 0 0 0 20,000 100,000 0 0
CIP2005 B -54 12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name:
City Entry Signs / Statements
Code No. 408
Account No. - - --
Location Map
Various Locations
i
Project Description
Installation of Entry Signs and /or Entry Statements at various entrances to the City.
A project cost estimate
has not yet been determined.
Project Funding Schedule Total Cost: $120,000
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10
FY 10/11 FY 11/12
Design
20,000
R -O -W
Construction
100,000
Inspection
Miscellaneous
Total
0 0 20,000 100,000 0 0
0 0
Funding Sources
Source
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10
FY 10 /11 FY 11/12
Undet.
20,000 100,000
Total
0 0 20,000 100,000 0 0
0 0
CIP2005
B-55
12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name: Peach Hill Parkways Code No. 409 _
Account No. - --
Location Map
_J I AOI FN
PL 9 T�A
r' �= °R.Y � PEACH HILL
r� ?��� =�rs���•rrrt��•�t111�
�I
T E
s
10NEYBEE
Project Description
Installation of Parkway Landscaping on both sides of the "east- west" segment of Peach Hill Road between
Mesa Verde Drive and Rolling Knoll Road.
Project Funding Schedule
Total Cost:
$53,000
Prior Yrs FY 05/06
FY 06/07 FY 07/08 FY 08/09
FY 09/10 FY 10 /11
FY 11/12
Design
1,000
R -O -W
0
Construction
50,000
Inspection
2,000
Miscellaneous
Total
1,000
52,000
Funding Sources
Source Prior Yrs FY 05/06
FY 06/07 FY 07/08 FY 08/09
FY 09/10 FY 10/11
FY 11/12
Undet.
1,000
52,000
Total
1,000
52,000
CIP2005
B -56
12/1/05
i
City of Moorpark
IF Capital Improvement Program
for Streets and Roads
I
Project Name: Princeton Avenue Median Modification at Campus Park Drive Code No. 410
Account No.
Location Map
LO
v Q �0
i
O
IERS T
ST.
i
Project Description
Modification of the median on Princeton Avenue near Campus Park Drive to reduce the number of left -turn
lanes from two to one and to widen the existing landscaped median.
Project Funding Schedule Total Cost: $100,000
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Design
R -O -W
Construction
Inspection
Miscellaneous
Total 0 0 100,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10 /11 FY 11/12
Undet. 100,000
Total 0 0 100,000 0 0 0 0 0
CIP2005 B -57
ivvos
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name: Master Drainage Study Update
Location Map
Entire City
Code No. 501
Account No. - - --
Project Description
This project is for costs to retain a consultant to prepare an update to the 1995 Citywide Master Drainage
Study. This project will be undertaken subsequent to adoption of the new Digital Flood Insurance Rate
Maps [DFIRM] by the Federal Emergency Management Agency [FEMA].
Design
R -O- W
Construction
Inspection
Miscellaneous
Total
Source
Undet.
Total
CIP2005
Project Funding Schedule Total Cost: 100,000 .
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
100,000
0 0
Prior Yrs FY 05/06
0 0
100,000 0 0 0 0 0
Funding Sources
FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12 iI
100,000 N
100,000 0 0 0 0 0
B -60 12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name: Gabbert Canyon / Walnut Canyon Improvements Code No. 502
Account No.
Location Map
I
WALNUT
CANYON
DRAIN
GABBERT - '
CANYON ��,��w•�•.s•�t _ _
-
DRAIN _
1
_ E ,
Project Description
The existing Ventura County Watershed Protection District [VCWPD] facilities within the Gabbert Canyon
and Walnut Creek watersheds are inadequate. This project calls for the construction of detention, diversion
and capacity improvements to those existing facilities, consistent with the conceptual design set forth in a
Study commissioned by the VCWPD. The 1998 cost for those improvements was estimated to be
$12,000,000 plus financing costs. No implementation or financing plan has yet been developed.
Project Funding Schedule Total Cost: 15,000,000 .
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10 /11 FY 11/12
Design
R -O -W
Construction
Inspection
Miscellaneous
Total 0 0 0 0 0 0 7,500,000 7,500,000
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
No Funding
Source
Identified
Total 0 0 0 0 0 0 7,500,000 7,500,000
CIP2005 B -61
12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name: Shasta Drain Code No. 50
Account No. - - --
Location Map
w �•�•� EXISTING DRAIN
{ 1IU111*13 uw PROJECT
I
Project Description
Construction of a storm drain to serve the residential area north of the intersection of Los Angeles Avenue
and Shasta Avenue, as identified in the City's Master Drainage Study. No funding source has been
identified for this project. The 1995 cost estimate for this project was $188,000. However, the full scope
and cost of this project has never been determined.
Design
R -O -W
Construction
Inspection
Miscellaneous
Total
Source
Undetermined
Total
CIP2005
Project Funding Schedule Total Cost: $800,000-
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
0
111
0 0 0 800,000 0 0
Funding Sources
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
800,000
0 0 0 0
B -62
0 800,000
0 0
12/1/05
AV
1
I
Q
I
1 i I I
W
0
Q ,d
IN I HM
Q
O
i
, I W
J
<
,
W W
i
W
l'7
Q
jI jI
_
Q
d 1 S `�
H S
wnuunnnuilumlu�nlmmuununnuu�Innunulnnun��•
a
J
w �•�•� EXISTING DRAIN
{ 1IU111*13 uw PROJECT
I
Project Description
Construction of a storm drain to serve the residential area north of the intersection of Los Angeles Avenue
and Shasta Avenue, as identified in the City's Master Drainage Study. No funding source has been
identified for this project. The 1995 cost estimate for this project was $188,000. However, the full scope
and cost of this project has never been determined.
Design
R -O -W
Construction
Inspection
Miscellaneous
Total
Source
Undetermined
Total
CIP2005
Project Funding Schedule Total Cost: $800,000-
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
0
111
0 0 0 800,000 0 0
Funding Sources
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
800,000
0 0 0 0
B -62
0 800,000
0 0
12/1/05
Project Name: Millard Dra
( PVT. ) ST.
UIQ
CD
_LPVT. ..N
City of Moorpark
Capital Improvement Program
for Streets and Roads
Location Map
Code No. 504
Account No. 8065
Existing Storm Drain
_._....___ ._.._ __..... .nnomw Proposed New Drain Line
Millard Street
Project Description
Construction of a storm drain similar in function to that identified in the City's Master Drainage Study as
the "Freemont Drain ", located north of the intersection of Los Angeles Avenue and Millard Street. The
current design concept for this project anticipates a storm drain running easterly along the north side of Los
Angeles Avenue from the existing Los Angeles Avenue culvert to Millard Street, and then northerly along
the east side of Millard Street for a short distance.
Project Funding Schedule
Total Cost: $195,000 .
Prior Yrs
FY 05/06
FY 06/07 FY 07/08 FY 08/09
FY 09/10
FY 10/11 FY 11/12
Design
25,000
-
R -O- W
Construction
150,000
Inspection
20,000
Miscellaneous
Total
0
195,000
0 0 0
0
0 0
Funding Sources
Source
Prior Yrs
FY 05/06
FY 06/07 FY 07/08 FY 08/09
FY 09/10
FY 10/11 FY 11/12
2904: MRA
195,000
Total
0
195,000
0 0 0
0
0 0
CIP2005
B -63
12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name: Villa Del Arrovo Drain _ Code No. 505
Account No. - - --
Location Map
LEGEND
EXISTING DRAIN P
[SCOPE OF PROJECT
YET TO BE DETERMINED]
Project Description
There is a culvert under Los Angeles Avenue at the entrance to the Villa Del Arroyo Mobile Home Park,
which connects to a storm drain pipe owned by the Mobile Home Park. This "private" drain line extends
southerly to the arroyo. It has been determined that the function of that storm drain is impaired and that
remedial action must be taken in order to provide adequate drainage for both the City street and the Mobile
Home Park. Consistent with the provisions of a Settlement Agreement between the City and the Mobile
Home Park, the property owner is required to take corrective action to remedy this problem.
Project Funding Schedule Total Cost: By Property Owner
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Design
R -O -W
Construction
Inspection
Miscellaneous
Total 0 0 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10 /11 FY 11/12
Total 0 0 0 0 0 0 0 0
CIP2005 B -64 1211/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name:
Miscellaneous Drainage Improvements
Code No. 506
Account No. - - --
Location Map
Location of Improvements To Be Determined
Project Description
This project
is for the
construction of miscellaneous drainage improvements, throughout the City, as
required.
Project Funding Schedule
Total Cost: $250,000
Prior Yrs
FY 05/06 FY 06/07 FY 07/08 FY 08/09
FY 09/10 FY 10 /11 FY 11/12
Design
R -O -W
Construction
Inspection
Miscellaneous
Total
0
0 0 50,000 200,000
0 0 0
Funding Sources
Source
Prior Yrs
FY 05/06 FY 06/07 FY 07/08 FY 08/09
FY 09/10 FY 10 /11 FY 11/12
Undetermined
50,000 200,000
Total
0
0 0 50,000 200,000
0 0 0
CIP2005
B -65
12/1/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
I
Project Name: Arrovo Simi Channel Improvements Code No, 5.0 -7
Accottnt No. - --
Location Map �
IVEY
OR -
'i
` A _
W.
r
- ,
l �����rr � � _ 3=.i __'� r— --
�I x
.W
J.
- - -- - - - -. _.
f
_la o J
Project Description
A number of projects, to be undertaken by the Ventura County Watershed Protection Agency, to construct
improvements to the Arroyo Simi to render it capable of containing storm follow from a 100 year storm
event, in a manner satisfactory to the Federal Emergency Management Agency [FEMA]. When those
projects are completed, a Letter of Map Revision [LOMB] will be processed to remove significant portions
of the City from various flood zones, as now depicted on the new draft DFIRM map..
Project Funding Schedule Total Cost: b VCWPD .
� g v
Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12
Design
R -O- W
Construction
Inspection
Miscellaneous
Total 0 0 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 1 1 /12
Total 0 0 0 0 0 0 0 0
CIP2005 B -66 12,11/05
City of Moorpark
Capital Improvement Program
for Streets and Roads
Project Name: Happy Camp Canyon Improvements
Code No. 508
Account No. - - --
Location Map
Location of Improvements To Be Determined
I
Project Description
The construction of or
more projects, to be undertaken by the Ventura County
Watershed Protection
Agency, to prevent flooding from Happy Camp Canyon.
Project Funding Schedule Total Cost: by VCWPD .
Prior Yrs
FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10
FY 10/11 FY 11/12
Design
R -O -W
Construction
Inspection
Miscellaneous
Total 0
0 0 0 0 0
0 0
Funding Sources
Source Prior Yrs
FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10
FY 10 /11 FY 11/12
Total 0
0 0 0 0 0
0 0
CIP2005
B -67
12/1/05
i
CIP2005 B -68 12/1/05
City of Moorpark
Capital Improvement Program
C. Program Expenditure Summaries
Cip2005_Intro
• Total Program Project Costs: Listed By Fiscal Year C -3
• FY 2005/06 Total: Spread to Funding Source C -7
Total Program [All Seven Years}: Spread to Funding Sources C -11
C -1
12/1/05
I
I
I
IFf
Cip2005_Intro C -2 12/1/05
Total Program Project Costs
Listed by Fiscal Year
Cip2005_Intro C -3 12/1/05
Page C -4
C. Program Summary
Account
Prior
FY 05/06 - FY 1 1/12
Code Project Name Number
Years
FY 05/06
FY 06/07
FY 07/08
FY 08/09
FY 09/10
FY 10/ 1 1
FY 1 1 / 12
Total
Street Improvements
101 Slurry Seal 8002
N/A
320,000
0
400,000
0
450,000
0
500,000
1,670,000
102 A/C Overlay - - --
N/A
0
1,000,000
0
1,000,000
0
1,000,000
0
3,000,000
103 Walnut Canyon Road - --
0
0
1,000,000
0
0
0
0
0
1,000,000
104 Spring Rd Widening 8026
214,450
1,035,550
0
0
0
0
0
0
1,035,550
105 Princeton Ave. Widening 8012
368,230
869,917
0
1,100,000
3,400,000
0
0
0
5,369,917
106 L A Ave: Spg to Mpk 8013
816,996
1,934,793
0
0
0
0
0
0
1,934,793
107 L A Ave: Beltramo 8003
393,803
1,270,571
0
0
0
0
0
0
0
0
1,270,571
2,000,000
108 L A Ave: Shasta - - --
0
0
500,000
1,000,000
500,000
0
0
0
0
0
0
0
5,000,000
5,000.000
10,0007000
109 Underground Utilities - - --
0
0
0
0
1,496,208
110 L A Ave Utility Dist 8051
240
726,208
770,000
0
0
0
300,000
111 Undrgmd @ N L A Brg 8066
0
300,000
0
0
0
0
0
0
379,772
112 Rail Xing: Spring Rd 8039
228
379,772
0
0
0
0
0
0
4,920,239
113 Moorpark Ave Widen 8040
336,469
1,420,239
3,500,000
0
0
0
114 Casey Rd Extension - - --
115 North Hills Parkway 8061
- --
53,576
----
346,424
----
300,000
- - --
1,000,000
- --
0
5,000,000
0
0
6,646,424
116 Metro Link South Lot 8056
0
497,795
0
0
0
0
0
0
0
0
497,795
4,550,000
117 Route 23 Realignment 8045
0
150,000
100,000
1,000,000
3,300,000
0
--
- - --
118 Spring Road North - - --
-- --
----
- - --
- - --
- - --
- -
- - --
119 C Street ----
- - --
- - --
----
- ---
- --
120 Gabbert Rd. Rail Xing - - --
- ---
----
- - --
- - --
- - --
0
- - --
0
- - --
0
- - --
0
430,000
121 High Street -- West - - --
0
0
110,000
320,000
0
122 Broadway Extension - - --
0
0
0
0
0
0
0
0
0
1,000,000
0
0
0
0
1,000,000
123 L A Ave E/O Collins - - --
0
0
0
0
0
0
0
34,000
124 MPk / 2nd X -walk 8064
0
34,000
0
0
0
0
300,000
125 Lengthen Curb Radii - - --
0
0
50,000
100,000
150,000
126 L A Ave East of T. R. Rd - - --
-- --
----
----
- - --
-`
Sub -Total
2,183,992
9,285,269
7,330,000
4,920,000
8,350,000
6,450,000
6,000,000
5,500,000
47,835,269
Trails & Walkways
201 Sidewalks 8001
N/A
30,000
30,000
30,000
30,000
30,000
30,000
30,000
210,000
202 Ped / Bicycle Project - - --
N/A
0
40,000
40,000
40,000
40,000
40,000
40,000
240,000
203 Arroyo Trail 8035
150,000
50,000
50,000
100,000
50,000
100,000
100,000
100,000
550,000
204 Downtown Trail 8050
58,919
17,836
100,000
50,000
50,000
100,000
0
0
0
317,836
32,000
205 Metro Link Ped Access 8060
0
32,000
0
0
0
0
0
0
0
0
1,047,475
206 High St Streetscape 8052
12,525
47,475
6,009
0
100,000
0
100,000
1,000,000
100,000
100,000
100,000
0
506,009
207 Drain #2 Trail 8059
23,991
Sub -Total
245,435
183,320
320,000
320,000
1,270,000
370,000
270,000
170,000
2,903,320
Page Total
2,429,427
9,468,589
7,650,000
5,240,000
9,620,000
6,820,000
6,270,000
5 .670 D00
50.738,589
C. Program Summary
Page C -5
Account
Prior
FY 05/06- FY 11/12
Code Project Name Number
Years
FY 05/06
FY 06/07
FY 07/08
FY 08/09
FY 09/10
FY 10/11
FY 11/12
Total
Traffic Signals
301 L A Ave / Maureen 8003
see 107
- --
- --
- --
- --
- --
- --
---
---
302 L A Ave / Shasta - --
see 108
- --
- --
- --
- --
- --
- --
- --
- --
303 L A Ave Interconnect 8004
52,654
195,561
0
0
0
0
- --
0
195,561
304 T R Rd Interconnect 8036
47,105
438,895
0
0
0
0
--
0
438,895
305 L A / Millard - --
see 106
- --
- --
- --
- --
- --
- --
- --
- --
306 L A / Town Center - --
- --
- --
- --
---
- --
- --
- --
- --
- --
307 L A / Near ButterCreek - --
see 115
- --
- --
- --
- --
- --
- --
- --
- --
308 L A/ T R Rd Mod. 8046
8,350
151,650
0
0
0
0
0
0
151,650
309 Signal Upgrades - --
0
0
100,000
100,000
0
0
0
0
200,000
Sub -Total
108,109
786,106
100,000
100,000
0
0
0
0
986,106
Medians and Parkways
401 T R/ L A Pkwy 8033
41,626
252,047
0
0
0
0
0
0
252,047
402 L A Ave Medains 8047
0
30,000
40,000
0
1,600,000
0
0
0
1,670,000
403 Spring Median 8026
See 104
- --
- --
- --
- --
- --
- --
- --
- --
404 T R Rd Median 8042
70,680
872,775
0
0
0
0
0
0
872,775
405 Poindexter Pkwy 8048
0
115,000
0
0
0
0
0
0
115,000
406 Freeway at T. R. Rd. --
0
0
30,000
200,000
0
0
0
0
230,000
407 Mt. Trail Median --
0
0
0
0
20,000
100,000
0
0
120,000
408 City Entry Signs - --
0
0
20,000
100,000
0
0
0
0
120,000
409 Peach Hill Parkways --
0
0
0
0
1,000
52,000
0
0
53,000
410 Princeton Median Mod. --
0
0
100,000
0
0
0
0
0
100,000
Sub -Total
112,306
1,269,822
190,000
300,000
1,621,000
152,000
0
0
3,532,822
Storm Drains
501 Mstr Drge Stdy Update - --
0
0
100,000
0
0
0
0
0
100,000
502 Gabbert /Walnut
- --
- --
- --
7,500,000
7,500,000
15,000,000
503 Shasta Drain --
0
0
0
0
0
800,000
0
0
800,000
504 Millard Drain 8065
0
195,000
0
0
0
0
0
0
195,000
505 Villa Del Arroyo Drain - --
0
0
0
0
0
0
0
0
0
506 Misc. Drainage Impr. --
0
0
0
50,000
200,000
0
0
0
250,000
507 Arroyo Simi Channel --
0
0
0
0
0
0
0
0
0
508 Happy Camp Canyon - --
0
0
0
0
0
0
0
0
0
0
195,000
100,000
50,000
200,000
800,000
7,500,000
7,500,000
16,34.5,000
Sub -Total
Prior Year Costs
Not Included
Page Total
220,415
2,250,928
390,000
450,000
1,821,000
952,000
7,500,000
7,500,000
20,863,928
Grand Total
2,649,842
11,719,517
8,040,000
5,690,000
11,441,000
7,772,000
13,770,000
13,170,000
71,602,517
it
�i
Cip2005_Intro C -6 12/1/05
FY 2005/06 Total Project Costs
i
Spread to Funding Sources
Cip2005_lntro C -% 12/1/05
FY 200512012 Capital Improvement Program Page C -8
Year FY05 /06 Funding Sources
Account 1000 2000 2001 2002 23xx 2501 2502 2602
Code Project Name Number General Fund Traf Safety TSM Traf Mitigation AD84 -2 L A AOC STR AOC TDA Art 3
Streets & Trails
101 Slurry Seal 8002
102 A/C Overlay - --
103 Walnut Canyon Rd - --
104 Spring Rd Widening 8026
1,035,550
105 Princeton Ave. Widening 8012
869,917
106 L A Ave: Spg to Mpk 8013
1,138,023
107 L A Ave: Beltramo 8003
803.597
108 L A Ave : Shasta - --
109 Undergrounding - - --
110 L A Ave Undergrounding 8051
299,761
111 Undrgmd: New L A Ave 8066
300,000
112 Rail Xing: Spring Rd 8039
113 Moorpark Ave Widen 8040
709,664
114 Casey Rd Ext. - - --
115 North Hills Parkway 8061
346,424
116 Metro Link South Lot 8056
117 Rt 23 Realignment 8045
150,000
118 Spring Rd North Ext. –
119 'C' Street –
120 Gabbert Rd Rail Xing - - --
121 High Street West - - --
122 Broadway Extension --
123 L A Ave E/O Collins - --
124 Mpl 12nd X -Walk 8064
13,000
125 Lengthen Curb Radii --
126 L. A. Ave West of T. R. Rd. --
0
0
0
1,206,088
0
4,446,848
0
13,000
Sub -Total
Trails & Walkways
201 Sidewalks 8001
202 Ped / Bicycle Project --
203 Arroyo Trail Study 8035
50,000
204 Downtown Trail 8050
11,807
6,029
205 Metro Link Access 8060
12,600
206 High St. Streetscape 8052
207 Drain #2 Trail 8059
6,009
0
0
67,816
0
0
0
0
18,629
Sub -Total
Traffic Signals
301 L A Ave / Maureen 8003
see 107
302 L A Ave I Shasta —
see 108
303 L A Ave Interconnect 8004
105,561
304 T R Rd Interconnect 8036
102,895
305 L A / Millard --
see 106
306 L A / Town Center - --
307 L A / Near ButterCreek --
see 115
308 LA I TR Rd Modification 8046
151,650
309 Signal Upgrades - --
Sub -Total
0
0
0
0
0
257,211
102,895
0
Medians and Parkways
401 T R / L A Pkwy 8033
402 L A Ave Medain 8047
216,970
30,000
403 Spring Median 8026
404 T R Rd Median 8042
see 104
872,775
405 Poindexter Pkwy 8048
406 T R at Freeway ---
407 Mt Trail Medain —
408 City Entry Signs - --
409 Peach Hill Pkwy –
410 Princeton / Campus Pk Median --
Sub -Total
0
0
0
0
0
246,970
872,775
0
Storm Drains
501 Master Drainage Study - --
502 Gabert / Walnut —
503 Shasta Drain - --
504 Millard Drain 8065
505 Villa Del Arroyo Drain —
506 Misc. Improvements –
507 Arroyo Sim Channel Impr. - --
508 Happy Camp Cnyn Impr.
Sub -Total
0
0
0
0
0
0
0
0
Total
0
0
67,816
1,206,088
0
4,951,029
975,670
31,629
FY 2005/2012 Capital Improvement Program
Year FY05 /06 Funding Sources
Page C -9
Account
2603
2604
2605
2150
2800
2902
Code Project Name Number
LTF
Fed Grant
Gas Tax
Trees
Other
Endowment
MRA
Total
Streets & Trails
-
101 Slurry Seal 8002
320,000
320.000
102 A/C Overlay -
103 Walnut Canyon Rd - --
0
104 Spring Rd Widening 8026
0
105 Princeton Ave. Widening 8012
1, 035, 550
106 L A Ave Spgto Mpk 8013
796,770
869 917
1,934,793
107 L A Ave: Beltramo 8003
466,975
1,270,572
108 L A Ave . Shasta - --
109 Undergrounding - - --
0
110 L A Ave Undergrounding 8051
426,447
0
726,208
111 Undrgmd: New L A Ave 8066
112 Rail Xing: Spring Rd 8039
189,886
189,886
300,000
379,772
113 Moorpark Ave Widen 8040
710,575
1,420,239
114 Casey Rd Ext. - --
0
115 North Hills Parkway 8061
346,424
116 Metro Link South Lot 8056
365,000
132,795
497,795
117 Rt 23 Realignment 8045
150,000
118 Spring Rd North Ext. - --
0
119 'C' Street -
0
120 Gabbert Rd Rail Xing --
0
121 High Street West --
0
122 Broadway Extension --
0
123 L A Ave E/O Collins - - --
0
124 Mpl /2nd X -Walk 8064
21,000
34,000
125 Lengthen Curb Radii -
0
126 L. A. Ave West of T. R. Rd. - --
0
Sub -Total
895,886
1,396,540
0
0
426,447
0
900,461
9,285,270
Trails & Walkways
201 Sidewalks 8001
30,000
30,000
202 Ped / Bicycle Project - - --
0
203 Arroyo Trail Study 8035
50,000
204 Downtown Trail 8050
17,836
205 Metro Link Access 8060
19,400
32,000
206 High St. Streetscape 8052
47,475
47,475
207 Drain #2 Trail 8059
6,009
0
0
30,000
0
66,875
0
0
183,320
Sub -Total
Traffic Signals
301 L A Ave / Maureen 8003
0
302 L A Ave / Shasta -
0
303 L A Ave interconnect 8004
90,000
195,561
304 T R Rd Interconnect 8036
336,000
438,895
305 L A / Millard --
0
306 L A / Town Center -
0
307 L A / Near ButterCreek --
0
308 LA / TR Rd Modification 8046
151,650
309 Signal Upgrades --
0
Sub -Total
0
426,000
0
0
0
0
0
786,106
Medians and Parkways
401 T R / L A Pkwy 8033
17,539
17,739
252,248
402 L A Ave Medain 8047
30,000
403 Spring Median 8026
0
404 T R Rd Median 8042
872,775
405 Poindexter Pkwy 8048
115,000
115,000
406 T R at Freeway -
0
407 Mt Trail Medain -
0
408 City Entry Signs - --
0
409 Peach Hill Pkwy -
0
410 Princeton /Campus Pk Medial --
0
Sub -Total
0
0
17,539
132,739
0
0
0
1,270,023
Storm Drains
501 Master Drainage Study - --
0
502 Gabert 1 Walnut -
0
503 Shasta Drain - --
0
504 Millard Drain 8065
195,000
195,000
505 Villa Del Arroyo Drain -
0
506 Misc. Improvements - --
0
507 Arroyo Sim Channel Impr. -
0
508 Happy Camp Cnyn Impr. -
0
0
0
0
0
195,000
0
0
195,000
Sub -Total
Total
895,886
1,822,540
47,539
132,739
688,322
0
900,461
11,719,719
11,719,719
I
it
ii
li
i
I
Cip2005_Intro C -10 12/1/05
Total Program
FY 2005/06 Thru FY 2011/12
Spread to Funding Sources
Cip2005_lntro C -1 1 12/1/05
FY 200512012 Capital Improvement Program Page C -12
Funding Sources Totals: FY2005106 thru FY 2011/12
Account 1000 2000 2001 2002 23xx 2501 2502 2602
Code Project Name Number General Fund Traf Safety TSM Traf Mitigation AD84 -2 L A AOC STR AOC TDA Art 3
Streets & Trails
101 Slurry Seal 8002
102 A/C Overlay - --
103 Walnut Canyon Rd - --
104 Spring Rd Widening 8026
1,035,550
105 Princeton Ave Widening 8012
5,369,917
106 L A Ave: Spg to Mpk 8013
1,138,023
107 L A Ave. Beltramo 8003
803,597
108 L A Ave Shasta - --
109 Undergrounding - - --
110 L A Ave Undergrounding 8051
769,761
111 Undrgrnd: New L A Ave 8066
300,000
112 Rail Xing: Spring Rd 8039
113 Moorpark Ave Widen 8040
2,459,664
114 Casey Rd Ext. --
115 North Hills Parkway 8061
6,646,424
116 Metro Link South Lot 8056
117 Rt 23 Realignment 8045
150,000
118 Spring Rd North Ext. - - --
119 'C' Street - - --
120 Gabbert Rd Rail Xing - - --
121 High Street West - - --
122 Broadway Extension –
123 L A Ave E/O Collins - - --
124 Mpl /2nd X -Walk 8064
13,000
125 Lengthen Curb Radii - - --
126 L. A. Ave West of T. R. Rd.
0
0
0
9,256,088
0
9,416,848
0
13,000
Sub -Total
Trails & Walkways
201 Sidewalks 8001
202 Ped / Bicycle Project - --
120,000
203 Arroyo Trail Study 8035
50,000
204 Downtown Trail 8050
11,807
6,029
205 Metro Link Access 8060
12,600
206 High St. Streetscape 8052
207 Drain #2 Trail 8059
6,009
0
0
67,816
0
0
0
0
138,629
Sub -Total
Traffic Signals
301 L A Ave / Maureen 8003
see 107
302 L A Ave / Shasta --
see 108
303 L A Ave Interconnect 8004
105,561
304 T R Rd Interconnect 8036
102,895
305 L A / Millard --
see 106
306 L A / Town Center —
307 L A / Near BufterCreek —
see 115
308 LA / TR Rd Modification 8046
151,650
309 Signal Upgrades
0
0
0
0
0
257,211
102,895
0
Sub -Total
Medians and Parkways
401 T R / L A Pkwy 8033
216,970
402 L A Ave Medain 8047
1,670,000
403 Spring Median 8026
see 104
404 T R Rd Median 8042
872,775
405 Poindexter Pkwy 8048
406 T R at Freeway –
407 Mt Trail Medain --
408 City Entry Signs –
409 Peach Hill Pkwy —
410 Princeton 1 Campus Pk Median --
Sub -Total
0
0
0
0
0
1,886,970
872,775
0
Storm Drains
501 Master Drainage Study --
502 Gabert / Walnut
503 Shasta Drain - --
504 Millard Drain 8065
505 Villa Del Arroyo Drain —
506 Misc. Improvements - --
507 Arroyo Sim Channel Impr. 0
508 Happy Camp Cnyn Impr. --
Sub -Total
0
0
0
0
0
0
0
0
Total
0
0
67,816
9,256,088
0
11,561,029
975,670
151,629
FY 2005/2012 Capital Improvement Program
Funding Sources Totals: FY2005106 thru FY
2011/12
Page C -73
Account
2603
2604
2605
2150
2800
2902
Code Project Name Number
LTF
Fed Grant
Gas Tax
Trees
Other
Endowment
MRA
Total
Streets & Trails
101 Slurry Seal 8002
1,670,000
102 A/C Overlay - --
1,670,000
103 Walnut Canyon Rd - --
3,000,000
3,000,000
104 Spring Rd Widening 8026
1,000,000
1,000,000
105 Princeton Ave. Widening 8012
1,035,550
106 L A Ave: Spg to Mpk 8013
796,770
5,369,917
107 L A Ave: Bekramo 8003
466,975
1,934,793
108 L A Ave : Shasta - - --
2,000,000
1,270.572
2,000,000
109 Undergrounding --
10,000,000
10,000,000
110 L A Ave Undergrounding 8051
726,447
1,496,208
111 Undrgmd: New L A Ave 8066
112 Rail Xing: Spring Rd 8039
189,886
300,000
113 Moorpark Ave Widen 8040
189,886
379,772
114 Casey Rd Ext. - --
2,460,575
2460575
4920239
4,920,239
115 North Hills Parkway 8061
116 Metro Link South Lot 8056
365,000
132,795
6,646,424
117 Rt 23 Realignment 8045
4,400,000
497,795
4,550,000
118 Spring Rd North Ext. - --
119 'C' Street - - --
0
120 Gabbert Rd Rail Xing - - --
0
121 High Street West --
430,000
0
430,000
122 Broadway Extension - - --
123 L A Ave E/O Collins -
1,000,000
0
1,000,000
124 Mpl /2nd X -Walk 8064
21,000
125 Lengthen Curb Radii - --
300,000
34,000
300,000
126 L. A. Ave West of T. R. Rd. - --
0
Sub -Total
2,245,886
1,396,540
0
0
22,856,447
0
2,650,461
47,835,270
Trails &Walkways
201 Sidewalks 8001
210,000
210,000
202 Ped / Bicycle Project -
120,000
203 Arroyo Trail Study 8035
500,000
240,000
550,000
204 Downtown Trail 8050
300,000
317,836
205 Metro Link Access 8060
19,400
32,000
206 High St. Streetscape 8052
1,047,475
1,047,475
207 Drain #2 Trail 8059
500,000
506,009
120,000
0
210,000
0
2,366,875
0
0
2,903,320
Sub -Total
Traffic Signals
301 L A Ave / Maureen 8003
302 L A Ave / Shasta
0
303 L A Ave Interconnect 8004
90,000
0
304 T R Rd Interconnect 8036
336,000
195,561
305 L A / Millard - --
438,895
306 L A /Town Center -
0
307 L A !Near ButterCreek -
0
308 LA ! TR Rd Modification 8046
0
309 Signal Upgrades -
200,000
151,650
200,000
Sub -Total
0
426,000
0
0
200,000
0
0
986,106
Medians and Parkways
401 T R / L A Pkwy 8033
17,539
17,539
252,048
402 L A Ave Medain 8047
403 Spring Median 8026
1,670,000
404 T R Rd Median 8042
0
405 Poindexter Pkwy 8046
115,000
872 775
406 T R at Freeway -
230,000
115,000
230,000
407 Mt Trail Medain -
120,000
120,000
408 City Entry Signs -
120,000
120,000
409 Peach Hill Pkwy -
53,000
53,000
410 Princeton / Campus Pk Mediai -
100,000
100,000
Storm Drains Sub -Total
0
0
17,539
132,539
623,000
0
0
3,532,823
501 Master Drainage Study -
100,000
100,000
502 Gabert ! Walnut -
15,000,000
15,000,000
503 Shasta Drain - --
800,000
800,000
504 Millard Drain 8065
195,000
195,000
505 Villa Del Arroyo Drain - --
506 Misc. Improvements -
250,000
0
250,000
507 Arroyo Sim Channel Impr. 0
508 Happy Camp Cnyn Impr. -
0 0
Sub -Total
0
0
0
0
16,345,000
0
0
16,345,000
Prior Year Casts
Not Icluded
Total
2,365,886
1,822,540
227,539
132,539
42,391,322
0
2,650,461
71,602,519
71,602,519
a.^ ,� ♦. \ y,%6(t r f�} to �.� ?`� ll` J�(...�,ttty :,i � _
II • � �
.
'
y
do
ji
71v
{ 5 rr ir-j
we
zj
OLe1n I�Ll1iiBFf7i1�.1 -°"�'�r 1 x /w.a t
�Bf."1,.
CITY OF MOORPARK
CMP NETWORK
City of Moorpark
Capital Improvement Program
D. Congestion Management Program
The purpose of the Ventura County Transportation Commission's (VCTC) Congestion Management
Program (CMP) is to monitor certain street segments and /or intersections on the CMP Road Network
(see Map), to confirm that the Level of Service (LOS) [a measurement of the level of congestion] on
those segments, or at those intersections, does not deteriorate below certain stipulated levels. Increased
traffic generated by development is one of the major causes of increased traffic congestion and,
therefore, the deterioration of the LOS. The CMP requires each Agency to identify projects designed to
increase capacity and/or otherwise improve the efficient and effective movement of traffic. The
projects set forth in this seven year program, which are on the CMP Road Network and which could
reduce congestion, are listed on the following page.
Cip2005_Intro
D -1
12/1/05
E. Projects on the Congestion Management
Account
Code Project Name Number
Street Improvements
Program RCMP)
Prior
Years
Road Network
FY 05/06
FY 06/07
FY 07/08
FY 08/09
FY 09/10
FY 10/11
FY 11/12
FY 05/06 - FYI I /12
Total
106 L A Ave: Spg to Mpk 8013
816,996
1,934,793
0
0
0
0
0
0
1,934,793
107 LA Ave:Beltramo 8003
305,405
11196,069
0
0
0
0
0
0
1,196,069
108 L A Ave: Shasta - - --
0
0
500,000
1,000,000
500,000
0
0
0
2,000,000
113 Moorpark Ave Widen 8040
336,469
1,420,239
3,500,000
0
0
0
0
0
4,920,239
117 Rt 23 Realignment - - --
0
150,000
100,000
1,000,000
3,300,000
0
0
0
4,550,000
Sub -Total
1,458,870
4,701,101
4,100,000
2,000,000
3,800,000
0
0
0
0
14,601,101
Traffic Signals
301 L A Ave / Maureen - --
See #107
- --
_ --
___
- --
- --
- --
302 L A Ave / Shasta - --
See #108
- --
- --
- -_
- --
- --
___
- -_
303 L A Ave Interconnect 8004
52,654
195,561
0
0
0
0
0
- -_
0
_
304 T R Rd Interconnect 8036
47,105
438,895
0
0
0
0
0
0
195,561
305 L A / Millard - --
See #106
- --
_ --
- --
- --
- --
- -_
438,895
306 L A / Near ButterCreek - --
See # 115
- --
- --
___
- --
- -_
- -_
- -_
307 L A/ T R Rd Modification 8046
8,350
151,650
0
0
0
0
0
___
0
_
Sub -Total
108,109
786,106
0
0
0
0
0
0
151,650
786,106
d
w
Page Total
1,566,979
5,487,207
4,100,000
2,000,000
3,800,000
0
0
0
15,387,207
Appendix 'I'
Completed Projects
The following is a list of known Streets and Roads Projects constructed subsequent to the incorporation
of the City in 1983.
Project Name Description
1985
Streets & Trails
Sidewalk Construction East Side of Moorpark Avenue, Third Street to Los Angeles Avenue
Sidewalk Construction West side of Moorpark Avenue from Community Center to High Street
Sidewalk Construction West side of Moorpark Avenue from North of Poindexter to Third Street
Asphalt Overlay Various Streets including High Street, Gabbert Road, Third Street, Bard
Street, Sherman Avenue, Second Street and Sarah Avenue
1987
Streets & Trails
Asphalt Overlay Spring Road South of Williams Ranch Road (by Developer)
Sidewalk Construction South side of Williams Ranch Road (by Developer)
Slurry Seal Project Various Streets throughout the City
Railroad Crossing Construction of rubberized railroad crossing on Old Los Angeles Avenue
(east of College View Avenue)
Traffic Signals
Los Angeles Avenue Construction of a traffic signal at Los Angeles Avenue & Tierra Rejada Road
& Tierra Rejada Road / Gabbert Road
Los Angeles Avenue & Construction of a traffic signal at this intersection
Condor Drive
Parkways and Medians
Campus Park Drive Construction of landscape improvements to medians on Campus Park Drive
(two Developers)
Tree Replacement Removal and replacement of parkway trees on a number of streets in the
downtown area
Spring Road & Peach Construction of landscape improvements at the southwest corner
Hill Road
Storm Drains
Spring Road Drainage Construction of a box culvert on the west side of Spring Road south of Los
Improvement Angeles Avenue
Cip2005_hist
Page 1
12/1/05
ect Name De
1988
Streets & Trails
Tierra Rejada Bridge Construction of a four lane (with median) bridge across the Arroyo Simi
Traffic Signals
Traffic Signal: Los Construction of a traffic signal at this intersection
Angeles Avenue &
Princeton Avenue
1989
Streets & Trails
Spring Road Railroad Construction of rubberized railroad crossing on Spring Road
Crossing
Moorpark Avenue Construction of rubberized railroad crossing on Moorpark Avenue
Railroad Crossing
Curb /Gutter /Sidewalk North side of High Street, east of Magnolia Street
Construction
Asphalt Reconstruction Various streets including Millard Street, Harry Street, Dorothy, Esther,
& Overlay Roberts Avenues, Laurelhurst Road, Campus Park Drive & Maureen Lane
Traffic Signals
Los Angeles Avenue &
Construction of a traffic signal at this intersection
Science Drive
Tierra Rejada Road &
Construction of a traffic signal at this intersection (Developer)
Peach Hill Road
Tierra Rejada Road &
Construction of a traffic signal at this intersection (Developer)
Walnut Creek Road
Tierra Rejada Road &
Construction of a traffic signal at this intersection (Developer)
Mt. Meadows Drive
Storm Drains
Moorpark Avenue Construction of storm drain improvements north of High Street (by Caltrans)
1990
Streets & Trails
Slurry Seal Project Various streets throughout the City
Sidewalk Construction East side of Spring Road, Los Angeles Avenue to Roberts Avenue (by
Developer)
Sidewalk Replacement of damaged sidewalks (including tree limb and root pruning)
Reconstruction throughout the City
Traffic Signals
Los Angeles Avenue & Major reconstruction of the traffic signal at this intersection (by Developer)
Spring Road II
Cip2005_hist Appendix `P — Page 2 12/1/05
ect Name
Traffic Signal: Campus
Park Drive & Delfen
Street
Parkways and Medians
Tierra Rejada Road
Median
Tierra Rejada Road
Parkway
1991
Streets & Trails
High Street & Spring
Road
Descri
Construction of a traffic signal at this intersection
Construction of landscape improvements to Tierra Rejada Road medians from
the Edison Easement easterly to a point east of Southhampton Road
Construction of landscape improvements to the parkway on the north side of
Tierra Rejada Road east of Peach Hill Road (Developer)
Reconstruction of curb, gutter & sidewalk at southeast corner (by Caltrans)
Avenida Colonia & Reconstruction of these two streets including the construction of new curbs,
Nogales Street gutters and sidewalks and the construction of a portion of the Happy Camp
Canyon covered box culvert to allow for the connection of these two streets
Los Angeles Avenue North side street improvements from Liberty Bell Road to Maureen Lane,
Widening including an additional westbound travel lane, curb, gutter and sidewalk
Sidewalk Construction West side of Spring Road, Los Angeles Avenue to Roberts Avenue
Sidewalk Construction North side of Los Angeles Avenue between Spring Road and Millard Street
Sidewalk Construction West side of Spring Road between Roberts Avenue and the railroad tracks
Handicap Access Construction of handicap access ramps at various locations throughout the
Ramps City
Traffic Signals
First St. / Poindexter Construction of a traffic signal at this intersection to fulfill the City's portion
Avenue @ Moorpark of a City /State Agreement to signalize both this intersection and Moorpark
Avenue Avenue / High Street
Storm Drains
Happy Camp Box Construction of a covered box culvert for the Happy Camp drain at Los
Culvert Angeles Avenue crossing (Unit III) and at the intersection of Nogales Street
and Avenida Colonia
1992
Streets & Trails
Sidewalk The reconstruction of the sidewalk on the east side of Tierra Rejada Road
Reconstruction south of Los Angeles Avenue, including the replacement of street trees
High Street Storm Construction of a storm drain from Walnut Street to Magnolia Street and a
Drain and Sidewalks sidewalk on the north side of the street between Bard Street and Magnolia
Street
Charles Street Reconstruction of the street from Moorpark Avenue to Bard Street, including
Cip2005_hist
Appendix `I' — Page 3
(2/1/05
Project Name
Description
Reconstruction (Ph. I)
the construction of a storm drain and new curbs, gutters and sidewalks
Traffic Signals
Replacement of the street trees on the east side of the street south of Los
Spring Road & Peach
Construction of a traffic signal at this intersection
Hill Road
area
Collins Dr. & Campus
Construction of a traffic signal at this intersection by Caltrans as a part of the
Park Dr.
freeway construction project
High St. & Moorpark
Construction of a traffic signal at this intersection by Caltrans to fulfill
Avenue
Caltrans' portion of a City/State Agreement to signalize this intersection and
Poindexter Avenue /First Street /Moorpark Avenue
Peach Hill Rd & Spring Construction of a traffic signal at this intersection
Rd
Parkways and Medians
Williams Ranch Road
Construction of a landscaped barrier across Williams Ranch Road near the
Landscape Barrier
Edison Easement
East side Tierra Rejada
Replacement of the street trees on the east side of the street south of Los
Road @ Los Angeles
Angeles Avenue in conjunction with the reconstruction of sidewalks in that
Avenue
area
1993
Streets & Trails
Asphalt Overlay
Construction of an asphalt overlay on the following streets: 1) Tierra Rejada
Project
Road at the Route 23 Freeway; 2) Peach Hill Road; & 3) Campus Park Drive
Slurry Seal Project
Construction of Type I and Type II Slurry Seal on various streets throughout
the City
Los Angeles Avenue @
Construction of street improvements, storm drains, traffic signals, landscaping
Park Lane, etc.
and related improvements on Los Angeles Avenue, Park Lane, Lassen
Avenue and Liberty Bell Road required for the construction of the Mission
Bell Plaza, funded by Assessment District 92 -1 [* *CMP].
Peach Hill Road East
Extension of Peach Hill Road east of Spring Road to the future Science Drive
of Spring Road
(constructed by the developer of the Carlsberg Specific Plan to serve the
Mesa Verde Middle School)
Traffic Signals
Tierra Rejada Rd &
Spring Rd
Los Angeles Ave &
Park Lane
Los Angeles Avenue &
Liberty Bell Road
Parkways & Medians
Sherman Avenue
Property Wall
Street widening project included the construction of a "permanent" traffic
signal to replace the temporary traffic signal at this location [* *CMP]
Construction of a traffic signal at this intersection as a part of the street and
storm drain improvements funded by Assessment District 92 -1 [* *CMP]
Construction of a traffic signal at this intersection as a part of the off -site and
storm drain improvements funded by Assessment District 92 -1 [* *CMP]
Replacement of the rear property walls for the properties on the south side of
Sherman Avenue (north side of Los Angeles Avenue between Spring Road
and Millard Street)
Cip2005_hist Appendix `I' — Page 4 12/1/05
Project Name
Los Angeles Avenue:
Spring Road to Millard
Street
Tierra Rejada Road /
Peach Hill Road Slope
Repair
Storm Drains
Sunnyslope Place
Debris Basin Access
Road
1994
Streets & Trails
Lassen Alley
Improvements
Charles Street
Reconstruction (Ph. II)
Spring Road Berm
Description
Construction of parkway landscaping on the north side of Los Angeles
Avenue between Spring Road and Millard Street
Repair of a slope failure on the south side of Tierra Rejada Road east of Peach
Hill Road
Construction of an access road to facilitate the maintenance of a storm water
debris basin north of Sunnyslope Place
Construction of pavement improvements to complete the drainage
improvements at the south end of McFadden Avenue and Cornett Avenue
Reconstruction of the street from Bard Street to Spring Road, including the
construction of a storm drain and new curbs, gutters and sidewalks
Construction of an asphalt berm on the east side of the street north of Peach
Hill Road in order to prevent erosion of the slope supporting the street
Flory Area Sidewalks Construction of sidewalks on certain streets in the vicinity of Flory
Elementary School, partially funded by an SB -821 pedestrian facility grant,
including Second Street, Bard Street, Third Street, Flory Avenue, Millard
Street, Roberts Avenue, and Harry Street
Tierra Rejada Road
Realignment and
Reconstruction
Grimes Canyon Road
Park Lane and Lassen
Avenue
Traffic Signals
Tierra Rejada Road &
Mountain Trail Street
Tierra Rejada Rd &
Arroyo Vista Access
Rd / Countrywood
Drive
Tierra Rejada Road @
Shopping Center Entry
Parkways & Medians
Tierra Rejada Rd
Cip2005_hist
Realignment and reconstruction of Tierra Rejada Road east of Spring Road,
increasing the roadway to four lanes and adding a center raised median
[* *CMP]
Street improvements (including widening) near the entrance (Turfway Road)
to Tract 4081 (constructed by the developer)
Improvements to Park Lane north of Los Angeles Avenue and Lassen
Avenue, to serve the Mission Bell Plaza Shopping Center (AD 92 -1)
Construction of a traffic signal at this intersection (Developer) [* *CMP]
Construction of a traffic signal at this intersection (Developer) [* *CMP]
Construction of a traffic signal at this intersection (Developer) [* *CMP]
Installation of landscaping in the extension of the center median in Tierra
Appendix `I' — Page 5
12/1/05
Project Name Description
Median at Spring Rd Rejada Road just west of Spring Road
Shasta Avenue / Los Construction of a block wall and landscaping at the northeast corner of Los
Angeles Avenue Wall Angeles Avenue and Shasta Avenue to meet right -of -way acquisition
[NE Corner] requirements
Last Side Spring Road Construction of parkway landscaping on the east side of Spring Road south of
South of Peach Hill Peach Hill Road
Road
Los Angeles Avenue @ Construction of parkway landscaping on the north side of Los Angeles
Shasta Avenue Avenue at Shasta Avenue
Storm Drains
AD 92 -1 Construction of storm drains along the north side of Los Angeles Avenue,
Park Lane, and within easements on the Mission Bell Plaza property
1995
Streets & Trails
High Street Decorative Installation of underground conduits for electrical, telephone, cable television,
Street Lights street lights and a decorative lighting system, plus the installation of nostalgic
decorative street lights on High Street
Freeway Connector Construction of bridges and related improvements required to connect the
Project Route 23 Freeway to the Route 118 Freeway (Caltrans) [ * *CMP]
City Maintenance Yard Conversion of property at 675 Moorpark Avenue to a City Maintenance
facility
Metro Link Parking Construction of the south Metro Link parking lot and access driveway
Lot / Driveway (SCRRA) [ * *CMP]
Lassen Avenue @ Modifications to Lassen Avenue to provide entrances to the north end of the
Mission Bell Plaza Mission Bell Plaza Shopping Center parking lot from Sierra Avenue and from
Park Lane
Slurry Seal Project Application of slurry seal and related work to approximately one -third of the
residential streets in the City
Tecolote, Canario, Etc. Construction of an asphalt overlay on Tecolote Court, Canario Court, and a
portion of North Granadilla Drive
Walnut Canyon Road Widening of Route 23 by Caltrans to provide a center turning lane at Wicks
@ Casey Road Road and Casey Road
First Street / Bard Reconstruction of First Street and Bard Street including reconstruction of
Street pavement, curb, gutter and sidewalks
Parkways & Medians
Moorpark Estates Entry Installation of entry signs at Shasta Avenue and Los Angeles Avenue and at
Poindexter Avenue and Sierra Avenue
Shasta Avenue /Los Construction of a block wall and landscaping at the northwest corner of Los
Angeles Avenue Wall Angeles Avenue and Shasta Avenue to meet right -of -way acquisition
[NW Corner] requirements
Cip2005_hist
Appendix `I' — Page 6
12/1/05
Proiect Name Description
Poindexter Avenue @ Construction of parkway landscaping on the south side of Poindexter Avenue
Sierra Avenue at Sierra Avenue
Princeton Avenue Construction of parkway and median landscaping on Princeton Avenue
Campus Park Drive Construction of parkway landscaping on the south side of Campus Park Drive
east and west of Princeton Avenue
Tierra Rejada Road Restoration of slope slippage on the south side of Tierra Rejada Road near
Slope Restoration Peach Hill Road
Bard Wall Construction of a wall at the north end of Bard Street, just north of First Street
Virginia Colony Construction of a landscaped planter at the corner of Virginia Colony Place
Planter and Los Angeles Avenue
Irrigation Crossover Construction of conduits for future irrigation water lines and valve control
Conduits wires at a number of locations including: Tierra Rejada Road at Courtney
Lane; Courtney Lane on the west side of Tierra Rejada Road and
Southhampton Road at Tierra Rejada Road
Spring Road Parkway Removal and replacement of damaged sidewalks and the installation of tree
Trees well grates along the west side of Spring Road south of Peach Hill Road, to
preserve existing parkway trees.
1996
Streets & Trails
Millard Street Area Construction of sidewalks on Sherman Avenue, Esther Avenue, Roberts
Sidewalks Avenue and other streets
Poindexter Avenue Complete reconstruction of this street west of Chaparral Middle School
Everett Street Complete reconstruction of this street, including curb, gutter and sidewalk
Walnut Street Complete reconstruction of this street, including curb, gutter and sidewalk
Bard Street Complete reconstruction of this street between Charles Street and High Street
Magnolia Street Complete reconstruction of this street north of Charles Street
Tierra Rejada Road Construction of an asphalt overlay on this street east of Spring Road
Spring Road Construction of an asphalt overlay on this street south of Peach Hill Road
Old Los Angeles Construction of an asphalt overlay on this street east of the rail crossing
Avenue located east of Collins Drive
Flory Avenue Construction of an asphalt overlay on this street
Magnolia Street Construction of an asphalt overlay on this street south of Charles Street
Goldman Avenue Construction of an asphalt overlay on this street
Cip2005_hist
Appendix `I' — Page 7
12/1/05
Project Name Description
Spring Road Median / Construction of modifications to the south leg of the intersection of Spring
Double Left Turn Lane Road and Los Angeles Avenue to provide for a double left turn lane and a
raised center median
Painted Sky Street Repair of street improvements damaged by a street subsidence
Subsidence Repair
Public Works Yard Construction of additional improvements to expand the City Maintenance
Expansion Yard at 675 Moorpark Avenue
Traffic Signals
Collins Drive & Construction of a traffic signal at this intersection by Caltrans, as a apart of
Campus Park Drive the Freeway Connector construction project
Moorpark Road & Construction of a traffic signal at this intersection by the City, with partial
Tierra Rejada Road funding from the County of Ventura
Parkways & Medians
Home Acres Buffer Construction of a landscaped buffer area, including an emergency access road
Area and a flood control maintenance road, at the west end of Shadyridge Drive in
Tract 4021 (funded by Zone 8 of AD 84 -2)
Storm Drains
Tierra Rejada Road Construction of a sub -drain system along Tierra Rejada Road between Walnut
Sub -Drain System Canyon Road and Mountain Trail Street to convey subsurface water to storm
drain inlets
Tierra Rejada Road Installation of a catch basin on the north side of the center median on Tierra
Inlet East of Spring Rejada Road east of Spring Road
Road
1997
Streets & Trails
Flinn Avenue
Reconstruction of Flinn Avenue east of Spring Road, constructed in
Reconstruction
conjunction with the Spring Road storm drain project
Moorpark Avenue
Construction of an asphalt overlay on this street, constructed in conjunction
[South] A/C Overlay
with the construction of the Moorpark Avenue storm drain project
Arroyo Vista
Construction of a pedestrian, equestrian, emergency access bridge across the
Arroyo Vista Community Park to Liberty Bell Road
Community Park
Arroyo Simi, to connect
Access Bridge
Arroyo Vista
Construction of a paved surface between the end of the park access road and
Community Park
the Arroyo Vista Park Access Bridge, partially funded by an SB -821 bicycle
Bike Path
facilities grant
Storm Drains
Moorpark Avenue
Construction of a storm drain system extending from the south side of Los
Stone Drain System
Angeles Avenue northerly to a point north of First Street, with storm drain
laterals serving Flory Avenue and the Metro Link parking lot
Spring Road Storm
Construction of a storm drain system extending from the south side of Los
Drain System
Angeles Avenue northerly to Flinn Avenue, and then extending easterly on
Cia2005 hist
Appendix `P — Page 8 12/1/05
Project Name Description
Flinn Avenue
1998
Streets & Trails
Downtown Alley Reconstruction of the alleys south of First Street
Reconstruction
Valley Road Reconstruction of the street
Wicks Road Slope Construction of retaining walls and related improvements required to provide
Stabilization slope stabilization to support Wicks Road
Wicks Road A/C Construction of an asphalt overlay on the westerly portion of this street
Overlay
Bonnie View Street Construction of an asphalt overlay on this street
A/C Overlay
Maureen Lane Reconstruction of Maureen Lane south of Los Angeles Avenue
Reconstruction
Storm Drains
Science Drive Storm Construction of two storm drain systems serving the Carlsberg Specific Plan
Drain System (by Developer), one serving the streets and a separate system conveying run-
off from common areas to vernal ponds
1999
Streets & Trails
Peach Hill Road Widening to the south side of the street east of Spring Road, in order to
provide a westbound left -turn lane.
Poindexter Avenue Widening to the north side of the street east of Gabbert Road, including new
curb, gutter and sidewalk, and the re- striping of the street to provide a painted
median and Bike Lanes.
New Los Angeles Widening to the south side of the street to provide six (6) lanes of traffic
Avenue Widening (by Developer). [ * *CMP]
Spring Road Widening Construction of widening to the east side of Spring Road from Tierra Rejada
Road northerly to the Arroyo Simi Bridge (by developer).
Casey Road Widening Widening to the south side of the street west of Walnut Canyon Road.
Old L. A. Avenue Surface crossing improvements to the rail crossing (by SCRRA).
Rail Crossing
Gabbert Road Surface crossing improvements to the rail crossing (by Union Pacific)
Miller Parkway Construction of a new collector street between Tierra Rejada Road and New
Los Angeles Avenue (by developer).
Tierra Rejada Road Improvements to the north side of the street, just west of the freeway (by
developer).
Cip2005_hist
Appendix `P — Page 9
12/1/05
Protect Name
Descri
Traffic Signals
Casey Road / Walnut
Construction of a traffic signal, funded by the City, Caltrans and the
Canyon Road
Moorpark Unified School District. [* *CMP]
Peach Hill Road and
Installation of a new traffic signal at this new intersection (by developer).
Miller Parkway
The construction of an asphalt overlay and related improvements to the
Tierra Rejada Road and
Installation of a new traffic signal at this new intersection (by developer).
Miller Parkway
[* *CMP]
Commercial Entry and
Installation of new traffic signal at this new intersection (by developer). This
Miller Parkway
signal is to be made operational when the center is opened.
New Los Angeles
Modifications to the traffic signal at the intersection of New Los Angeles
Avenue & Miller
Avenue and Science Drive, to accommodate the addition of Miller Parkway
Parkway
as the south leg of the intersection. (by developer) [* *CMP].
New Los Angeles
Installation of traffic signals at the on and off -ramps to the freeway, in order
Avenue at the Route 23
to allow ingress and egress traffic to and from White Sage Road (private) [by
Freeway
Caltrans and the developer].
Parkways & Medians
Spring Road Medians Construction of new landscaped medians and parkways (east side) from
and Parkways Tierra Rejada Road northerly to the Arroyo Simi Bridge (by developer).
2000
Streets &Trails
Spring Road Bridge
Reconstruction of the Spring Road Bridge at the Arroyo Simi, to provide
sidewalks, bike lanes and a raised median.
Asphalt Overlay
The construction of an asphalt overlay and related improvements to the
following streets: Talmadge Rd.; Marquette St.; Gabbert Rd. (north of
Poindexter Ave.); Spring Road (north of High St.); Fitch Ave.; Minor St.;
Robert St.; Harry St.; Ruth Ave.; Dorothy Ave.; Mt. Trail (east of Walnut
Creek Rd.); Collins Dr.; Campus Park Dr.; Princeton Ave.; High Street;
Spring Road (New L. A Ave. to Bridge); and Christian Barrett Drive.
Spring Road
Rehabilitation of Spring Road between New Los Angeles Avenue and High
Rehabilitation
Street. The cost of this project was reimbursed by Caltrans as required by a
Highway Relinquishment Agreement.
Los Angles Avenue
Rehabilitation of Los Angeles Avenue between High Street and Princeton
Rehabilitation
Avenue. The cost of this project was reimbursed by Caltrans as required by a
Highway Relinquishment Agreement. Upgrades to the middle portion of this
street segment are being deferred until the Los Angeles Avenue East project
is constructed.
Parkways & Medians
Freeway Landscaping Installation of freeway landscaping from Collins Drive to a point west of
Princeton Avenue (by Caltrans).
Cip2005_hist Appendix `I' —Page 10
12/1/05
Project Name
Storm Drains
Tierra Rejada Road
Inlets
L. A. Ave. Drain
2001
Streets & Trails
New Los Angeles
Avenue Bridge
Widening
Los Angeles Avenue:
Moorpark Avenue to
Park Lane
Des
Construction of additional storm drain inlets to better handle peak storm
flows.
Installation of new inlets east of Spring Road to eliminate flooding.
Widening to the south side of the New Los Angeles Avenue [SR -1 18] bridge
over the Arroyo Simi to provide six (6) lanes of traffic. [* *CMP]
Widening to the south side of the street to provide three (3) eastbound lanes
(by Developer). [* *CMP]
Los Angeles Avenue: Construction of street widening to the south side of the street at the old
East of Leta Yancy Rd Caltrans Maintenance Yard, in order to provide three (3) eastbound lanes,
curb, gutter and sidewalk. [* *CMP]
Traffic Signals
Los Angeles Avenue & Modifications to the striping to provide a double left -turn lane at the east leg
Tierra Rejada Road of the intersection.
Parkways & Medians
Los Angeles Avenue Installation of median landscaping and irrigation in the new raised median on
Los Angeles Avenue south of the Princeton Avenue freeway ramps.
Tierra Rejada Road Installation of parkway landscaping on the north side of Tierra Rejada Road
east and west of Southhampton Road, funded by the Zone 2 improvement
assessment [AD84 -2].
2002
Streets & Trails
Underground Utility The undergrounding of all overheard utilities, other than high voltage
District No. 2000 -1 electrical lines, on Los Angeles Avenue between Gabbert Road and Millard
Street. Project was constructed by SCE and funded by SCE pole replacement
monies and Rule 20A undergrounding accruals.
Miller Parkway / Peach Construction of widening at the northeast corner to allow south -to -north U-
Hill Road U -Turn Turn movements.
2003
Streets & Trails
Arroyo Trail Study Feasibility Study and Implementation Plan for an arroyo levee trail from the
westerly City limit to Madera Road in the City of Simi Valley.
Moorpark Road City costs related to a County of Ventura Road Department Project to
Realignment construct a new, realigned Moorpark Road intersecting Tierra Rejada Road at
Miller Parkway.
C ip2005_h ist
Appendix T— Page 1 1
12/1/05
Protect Name Description
Curb Ramp Project Construction of curb ramps at a number of locations (mainly "T- intersections ")
throughout the City.
2003 Slurry Sea] Application of Slurry Seal to approximately one -third of the streets in the
Project City.
2003 AC Overlay Construction of an asphalt overlay on a number of streets throughout the City.
Project
GASB -34 Preparation of a study to inventory, quantify, categorize and determine the
Infrastructure value of the City's infrastructure improvements. Depreciation rates and
Inventory Report replacement cost estimates were also derived from that effort.
Curb / Gutter Repair Replacement of damaged curb and gutter at numerous locations throughout
Project the City.
Parkways & Medians
Peach Hill Road Construction of parkway landscaping on Peach Hill Road between Mesa
Parkway Verde Drive and Peach Hill Park. This project was constructed by the Peach
Hill HOA.
Traffic SilInals
New L. A. Avenue at Installation of a new traffic signal by the developer of the shopping center.
the Marketplace
Shopping Center
Miller Parkway & Installation of a new traffic signal by the developer of the shopping center.
Patriot Drive
2004
Streets & Trails
Flinn Avenue The realignment of Flinn Avenue to align with Second Street. The project
Realignment included the widening of Spring Road north of Flinn Avenue, the construction
of a raised median on Spring north of Flinn Avenue and the construction of a
traffic signal at the intersection of Spring Road and Second Street.
Civic Center Driveway The widening of the driveway into City Hall.
Modification
Street Light A CDBG funded project to relocate and add street lights in the neighborhood
Modification — Millard southeast of Moorpark Avenue and First Street.
Tract
Traffic Signals
Double Left -Turn Construction of improvements to provide a double left -turn lane for
Lane on Spring Road southbound traffic.
at Tierra Rejada Road
Spring Rd and Second Construction of a traffic signal at the intersection of Spring Road and Second
Street Street / Flinn Avenue.
Parkways & Medians
Spring Road Parkway Removal of existing eucalyptus trees and the construction of new tree wells,
West side with deep root irrigation, between Peach Hill Rd. and Christian Barrett Drive.
Cip2005 —hist
Appendix `I' — Page 12
12/1/05
roject Name Description
Tierra Rejada Rd Removal of existing trees and installation of new tree wells, with deep root
Parkway, East side irrigation, between Harvester and Courtney.
Spring Road Median Installation of median landscaping north of Second Street.
Storm Drains
Loraine Drain Construction of storm drainage facilities northwest of the Spring Road Bridge
(by a developer) to meet needs identified in the Master Drainage Study as the
"Loraine Drain" or the "No Name Drain ",
2005
Streets & Trails
Grimes Canyon Road Construction of roadway improvements by a Developer. City costs related to
at Championship Drive the acquisition of needed rights -of -way were reimbursed by the Developer.
Traffic SiLynals
Casey Signal The modification of the traffic signal at Casey Road and Walnut Canyon
Modification Road [State Route 23] to provide a left -turn arrow for northbound traffic
[funded by developer (Pardee Homes)].
Parkways & Medians
Storm Drains
Little Hollow
Construction of a sub -drain to intercept subsurface water and convey same to
SubODrain
a storm drain in an effort to prevent future damage to the asphalt pavement.
* *CMP: Denotes that the project was on the CMP Road Network and is related to congestion management.
Cip2005 —hist
Appendix `1' —Page 13
12/1/05
Appendix `II': Description of Funds
Page 1
Fund
1000 — General Fund: Revenues derived
from property tax, sales tax, motor vehicle
in lieu fees and other non - restricted
2000 — Traffic Safety Fund: Revenues
derived from vehicle code fines, which are
restricted to construction and
maintenance of traffic control devices,
streets, equipment, and supplies for traffic
enforcement, accident prevention and
crossing guards.
2001 — Traffic Systems Management:
Revenues derived from fees based on the
air quality impacts of land development
projects. Said funds are to be used on
projects or programs designed to mitigate
those air quality impacts.
2002 — Citywide Traffic Mitigation:
Revenues derived from development fees
to fund mitigation measures designed to
better accommodate the increased traffic
flow generated by those development
projects.
23xx — Assessment Districts: Revenues
derived from maintenance & improvement
district assessments, which have been
earmarked for improvement projects. A
separate Fund has been established for
each District and /or Zone within a District.
Also included in this category are
Community Facility District Funds.
Cip2005 funds
Remarks
With rare exception, capital improvement projects
have not been funded by the General Fund. It
should be noted that State law requires the City to
maintain an established level of effort of General
Fund expenditures for streets [called a Maintenance
of Effort (MOE)], in order to continue to receive
State AB2928 Congestion Relief monies [see Fund
2610]. Although currently suspended, the current
annual MOE amount is $510,432.
Revenue to this Fund is only about $125,000 per
year. In recent years this fund has been used
primarily to fund the Crossing Guard program.
There are no project proposed to be funded by this
source.
In the past these funds have been used to fund
such things as the acquisition of low emission
vehicles. The projected FY 04/05 year -end Fund
Balance is $3.8 million. A list of candidate projects
for this funding was recently reviewed and approved
by the City Council.
The draft program currently shows almost $7 million
in projects, funded by this source, over the seven -
year cycle. The projected FY 04/05 year -end Fund
balance for Fund 2002 is $6.5 million.
Project 401 - Los Angeles Avenue / Tierra Rejada
Road parkway landscaping includes $7,315 from
Fund 2300, which is an amount paid by a developer
as mitigation for unauthorized tree removal. The Los
Angeles Avenue Undergrounding Project [ #111] is
partially funded by Fund 2330 [AD92 -1: Mission
Bell Plaza].
Appendix `II': Description of Funds
Page 2
Fund
2501 — Los Angeles Avenue AOC:
Revenues derived from fees paid by land
development projects located within a
designated area, for the purpose of
constructing roadway improvements
within that area. The properties subject to
this fee consist of all of the areas of the
City located north of the Arroyo Simi, plus
the property south of the Arroyo and east
of the freeway [S.D.I. Property].
2502 — Spring Road / Tierra Rejada
Road AOC: Revenues derived from fees
paid by land development projects
located within a designated area, for the
purpose of constructing roadway
improvements within that area. The
properties subject to this fee consist of all
of the area of the City located south of the
Arroyo Simi.
2503 — Casey Rd / Gabbert Rd AOC:
Revenues derived from fees paid by land
development projects located in that area
generally located northwest of Walnut
Canyon Road (Moorpark Avenue) and the
rail corridor, for the purpose of
constructing roadway improvements
within that area.
Remarks
The various projects to be financed by this Fund
include: 1) a number of projects required in order to
provide six (6) lanes of traffic along the New Los
Angeles Avenue /Los Angeles Avenue corridor, and
2) the reconstruction and realignment of Los
Angeles Avenue east of High Street.
Projects funded or partially funded by this source
include the Tierra Rejada Traffic Signal Interconnect
System and the Tierra Rejada Road median
landscaping project.
No appropriations have yet been made to projects
from this Fund.
............. _ ..... . - -_. ......_._ _ .................. _ _ _ ... . ..._....
2602 — TDA Article 3: A portion of State These funds are allocated to the cities in the County
sales tax revenues which is restricted to by the Ventura County Transportation Commission
the construction or improvement of (VCTC) via a competitive grant process.
pedestrian and /or bicycle facilities.
2603 — TDA Article 8A: TDA Article 8
monies are derived from a portion of
State sales tax revenue, which is
apportioned to each city based on
population. The City allocates these
monies between TDA Article 8C funds,
which become revenues to the City's
Transit Fund (Fund 5000), and TDA
Article 8A funds, which become revenues
to the Local Transportation Fund [LTF]
(Fund 2603) to fund street improvement
and maintenance.
Cip2005 funds
._...
Histo . rically, these monies have been used to fund
major street improvement and maintenance
projects, such as slurry seal application and asphalt
overlay projects.
Appendix `II': Description of Funds
Page 3
Fund
2604 — Federal Grants: Revenues
received via various federal grant
programs, including: the Surface
Transportation Program (STP) and
Congestion Mitigation Air Quality
(CMAQ).
2605 — Gas Tax: Revenues derived from
a tax on motor vehicle fuel sales,
apportioned to local agencies based on a
formula using population, road miles and
other factors. These revenues are
restricted to expenditures for street
maintenance and related costs.
2609 — Other Grants: Revenues derived
from various State grant programs.
Remarks
Federal highway grant programs are usually
authorized by Congress every six (6) years. The
current cycle of funding was to commence in 2003,
but to date has not yet been appropriated by
Congress.
In recent years O &M costs charged to this Fund
have exceeded revenues. The ability of this Fund
to finance capital projects is, therefore, becoming
very limited.
None.
2902 — MRA Operations: Revenues None
from tax increment derived from property
taxes levied upon properties within the
Redevelopment Project Area. .
Cip2005 funds