HomeMy WebLinkAboutAGENDA REPORT 2017 1115 CCSA REG ITEM 09C ITEM 9.C.
CITY OF MOORPARK,CALIFORNIA
City Council Meeting
Of //-/.--aa 7
MOORPARK CITY COUNCIL ACTION: -
AGENDA REPORT /� �� -----
TO: The Honorable City Council
FROM: Jeremy Laurentowski, Parks and Recreation Director 31--
DATE:
StDATE: October 25, 2017 (CC Meeting of November 15, 2017) -
SUBJECT: Consider Seven Year Capital Improvement Program for the
Department of Parks Recreation and Community Services for FY
2017/18- FY 2023/24
BACKGROUND & DISCUSSION
A Seven Year Capital Improvement Program (CIP) for the Department of Public Works
(PW) is updated annually and presented to the City Council as a tool for planning and
programming major public works capital improvement projects over the coming years.
However, this document has not included proposed improvements for parks, facilities
and landscaping. In order to provide the City Council with a more complete listing of
citywide planned improvement projects to use for planning and programming purposes,
the Department of Parks, Recreation and Community Services (PRCS) has prepared a
draft Seven Year CIP that covers facilities, landscaping, open space, parks and trails. It
should be noted that there is some overlap between the two documents regarding future
trails. This will be addressed as part of the comprehensive CIP referenced below.
Additionally, the updated PW CIP presented to the City Council on November 1, 2017
provided a seven year plan that started in the prior fiscal year, in this case FY 2016/17.
However, both departments have determined that this document should be started in
the current fiscal year in order to project a full seven years. The draft PROS CIP
attached to this report identifies a start date of FY 2017/18. The CIP documents for
both departments will be updated once the final CIP has been compiled. Staff
anticipates that a comprehensive CIP document will be presented to the Transportation
and Public Works Committee during the first quarter of next year, and presentation to
the City Council no later than June, 2018.
The City of Moorpark Mission Statement, Priorities, Goals and Objectives for FY 17/18
and FY 18/19, approved by City Council on May 17, 2017 includes the following
Objective related to the CIP document (Section IV, A, Item No. 9):
32
Honorable City Council
November 15, 2017
Page 2
Upon approval of Parks/Facilities Capital Improvement Program, prepare a
comprehensive City Capital Improvement Program document for consideration
by June 30, 2018. (CE/PW& PRCS)
As with the PW CIP, the PRCS CIP schedules and prioritizes the department's projects
over a seven year period. It also describes each individual project and identifies
potential funding source(s). The listed projects involve capital outlays or nonrecurring
expenditures, and do not include routine maintenance activities or costs. Listed projects
include:
• New construction projects with a total cost of at least $10,000 over the life of
the project.
• Expansions or additions to existing facilities with a total cost of at least
$10,000.
• Major renovation, improvement, replacement, maintenance, or rehabilitation
projects with a cost of at least $10,000 useful life of at least 10 years.
• Purchases of major equipment with a total cost of $10,000 or more and a
useful life of at least 7 years.
On May 1, 2017 staff presented the draft PRCS CIP to the Parks and Recreation
Commission (Commission) and updated the Commission regarding the status of several
projects. The Commission did not recommend any additions or changes to the draft
CIP.
The projects are organized into five categories as follows:
1. Facilities
2. Landscape Maintenance Districts (LMD's) and General Landscaping
3. Open Space
4. Parks
5. Trails
The draft CIP document includes a list of potential projects and feasibility studies, a
list of maintenance and non-capital projects, a summary of completed projects, and is
designed to serve a variety of purposes:
• It is a budget planning document.
• It is a funding source reference.
• It is a plan for future citywide improvements.
• It is a list of infrastructure needs.
• It establishes the scope and estimated costs of specific projects.
• It is a tool for prioritizing and scheduling capital improvement projects.
• It provides a list of projects already completed and documents the City's
expenditures related to capital improvements.
• It provides a list of potential projects.
33
Honorable City Council
November 15, 2017
Page 3
• It is a hands-on working reference document to identify, define and describle
future planned capital improvement projects.
Additionally, the CIP provides for planning and programming for future recreational
needs, as outlined in the Parks and Recreation Master Plan (PRMP). The last PRMP
update was approved by the City Council in 2009. Staff has included an update to the
PRMP as a CIP project that will be completed within the next few years. It is anticipated
that the future PRMP update will include additional park facilities, as trends in recreation
have changed over the last several years. It should be noted that the PRMP identifies
the need for two additional parks, and a study to determine if there is a need for the
expansion of existing parks, such as Glenwood Park. The two additional parks noted in
the PRMP include a 10 acre park located in the general location of the City owned
property referenced in the CIP as Buttercreek Park, as well as a 20+ acre Community
Park located in the general location of the future Hitch Ranch project located on the
north side of Poindexter Avenue, west of City Hall. The Community Park has not been
included in the CIP as a current or future project, as the need for a park of this size is
most likely not warranted until the Hitch Ranch project has been completed. However, it
should be noted that there may be a need to provide additional fields to accommodate
the needs of our local youth sports leagues and the residents of Moorpark in the future.
This could include shifting more of the games and practices to other parks, adding
additional field lighting at Arroyo Vista Community Park (AVCP), or other parks, or as
previously referenced, adding park acreage.
Within the last several years, most of the youth sports leagues have expanded the
length of their seasons. In addition, all of the youth sports leagues have requested an
increase to the number of tournaments allowed under their respective agreements.
There has also been an increase in requests by new youth sports leagues, such as a
new soccer league and a lacrosse league, to enter into an agreement with the City for
use of the City's facilities. Except as noted below, in order to minimize the impacts to
Moorpark residents, the City has an established practice where athletic fields at many of
the neighborhood parks are not rented to the youth sports organizations or other outside
leagues. This is due to several reasons, but primarily due to noise and traffic impacts,
available parking, and the City's desire give priority use of neighborhood parks to
Moorpark residents.
Currently, several of the major sports leagues, such as the American Youth Soccer
Organization (AYSO), Moorpark Girls Softball Association, and Moorpark Musketeers
Youth Football utilize the fields at AVCP. Moorpark Little League•utilizes the fields at
Poindexter Park, Moorpark Soccer Club utilizes the fields at Campus Canyon Park, and
the United States Youth Volleyball League utilizes the fields at Mammoth Highlands
Park. Because of the high number of youth sports leagues, the availability of athletic
fields has reached its capacity and many of the youth sports leagues have had to work
together to schedule practices, games and weekend tournaments. AYSO has
expressed some concern regarding the future growth of their organization due to certain
scheduling limitations and the availability of athletic fields. Even though the leagues pay
34
Honorable City Council
November 15, 2017
Page 4
for use of the athletic fields, at a substantially reduced rate, the revenue generated by
these fees does not equal the maintenance costs associated with the impact to the
fields. In an effort to stay on top of turf maintenance activities, and to keep overall
maintenance costs low, the City purchased turf maintenance equipment several years
ago. Regular turf maintenance practices, such as aeration, seeding, and supplemental
fertilization are now completed by the City's in-house staff, which ultimately has placed
some limitations on other regular maintenance activities, as well as the completion of
minor improvement projects. As discussed later in this report, the revenue generated
from the Special Benefit Assessment for park maintenance only covers a portion of the
total maintenance costs needed to support regular maintenance operations. It should
be noted that additional park acreage, or additional parks in general, will require
increased General Fund contribution to maintain the City's parks.
The high impact to the City's parks may also be attributed to the fact that there is not a
local regional park within close proximity to Moorpark. Typically, a regional park would
be available for recreational purposes in a more urbanized area. In addition, the fields
managed by Moorpark Unified School District (MUSD) have had limited use by the
youth sports leagues to supplement recreational services and facilities. With the
exception the Moorpark High School stadium, which is used for youth football and track,
there are very few other uses of the district's fields by the youth sports leagues. Several
neighboring Park Districts have use agreements with the local school district to
supplement public recreation needs. Staff intends to explore this option with MUSD in
the future to see if there are opportunities for both agencies. Staff believes that both
agencies would benefit from a greater use of certain MUSD facilities by youth sports
leagues and the general public.
As mentioned earlier, the CIP includes major renovation, improvement, replacement,
maintenance, or rehabilitation projects with a cost of at least $10,000 useful life of at
least 10 years. It should be noted that many items listed in the CIP are reoccurring
costs due to the fact that the useful life of these facilities necessitate maintenance
and/or replacement within a ten to twenty year time frame. In FY 1985/86 the City
established an Equipment Replacement Fund (ERF) to set-aside funds to replace
various machinery and equipment as they age and/or as the asset's useful life has
exhausted. The contribution to the ERF is allocated to various sources that originally
financed the acquisition of the asset. Assets such as playground equipment, irrigation
controllers, park furnishings, vehicles and maintenance equipment are accounted for in
the ERF. For example, play equipment typically needs replacing every fifteen to
eighteen years. The City currently has twenty playgrounds in seventeen parks. If the
average life span of playground equipment is approximately eighteen years, and the
average cost to replace the play equipment is approximately $125,000, the City should
be setting aside approximately $140,000/year in a reserve fund to replace the City's
play equipment.
However, not all assets are included in the ERF at this time, and the ERF does not
account for regular maintenance activities. For instance, outdoor fitness equipment also •
35
Honorable City Council
November 15, 2017
Page 5
has a life span of approximately fifteen to eighteen years. Many parks have been
installed with safety surface material, such as poured-in-place surfacing. This material
has a lifespan of approximately fifteen years. Basketball courts and tennis courts need
to be resurfaced approximately every ten years, as do parking lots and park roads. In
addition, many of the City's buildings are aging and are in need of improvements.
Heating, ventilation and air conditioning (HVAC) systems need to be replaced on
average every thirty years. Flat roofs, such as those above the Community Center,
Police Services Center, and Ruben Castro Human Services Facility, need to be
replaced every thirty years on average. As mentioned later in this report, many of the
lighting systems in the City's parks and facilities have been replaced with new light
emitting diode (LED) lighting. Although the energy cost savings and maintenance cost
savings are substantial, these lighting systems will most likely need to be replaced in
approximately fifteen years.
Also of concern is the fact that many of the City's landscape areas are aging and in
need of replacement. Irrigation systems and certain plant types have a life span, and
many plants are directly impacted by their immediate environment. For instance, in a
new planting design, the designer will typically include sun loving plant types into the
overall design, as the trees are small and will take many years to mature. However, as
the trees mature they will provide shade, which may negatively impact the health of the
existing plant material. Many of the plantings in the parks have suffered due to this
issue. The opposite situation may also impact the plant material. For instance, along
Tierra Rejada Road, many of the Sequoia Trees have been removed from a fungal
disease (Sequoia Canker). As the trees are removed, the now exposed groundcover
has suffered from sun exposure. In some instances, supplemental irrigation water has
helped alleviate this issue, but at a high cost to the City.
Staff believes that in addition to the ERF, or as part of the ERF, a plan should be
developed, and a funding source identified to fund future rehabilitation and replacement
for those items, such as HVAC replacement and pavement management. The goal
would be to set aside sufficient funds so that when an item needs to be replaced or
receive major maintenance, the funding would come from the set aside funds, not the
annual operating budget or General Fund Reserve.
FISCAL IMPACT
Projects are prioritized based upon the funding year shown for each project. The PRCS
draft CIP presents a total of 131 active or proposed projects with an aggregate total cost
estimate of $86,325,095. It should be noted that detailed preliminary engineering has
not been conducted for the majority of the proposed projects listed. Therefore, the cost
estimates are preliminary and will be subject to change as the full scope and
requirements of each project are developed. Additionally, projected future budget
allocations for PRCS projects are currently under development, so recommended
funding sources for a number of projects are undetermined at this time.
36
Honorable City Council
November 15, 2017
Page 6
The FY 2017/18 budget for park maintenance operations approved by the City Council
is approximately $2,866,041. This represents an increase of approximately 12.9%, as
compared to the FY 2016/17 adopted budget. Revenue generated from the Special
Benefit Assessment, will generate an estimated $797,100, and it is anticipated that the
General Fund will be required to supplement park maintenance operations by
approximately $2,043,941. The Special Benefit Assessment is paid by property owners
that reside within the City limits for park maintenance operations. The City fund for
these assessments is the Park Maintenance Assessment District Fund (2390). The
balance of the park maintenance budget is funded by the Park Improvement Funds in
order to fund certain one-time park improvement projects and the replacement of certain
park equipment.
Increases in the park maintenance budget are primarily due to deferred maintenance
activities. For instance, the tree budget has increased approximately 300% in order to
maintain the City's urban forest. The tree budget was reduced several years ago to
account for budgetary constraints at that time. Other maintenance activities include the
resurfacing of tennis courts and basketball courts, paving repairs at various parks to
correct both ADA and maintenance deficiencies, restroom repairs and fencing. In
addition, several maintenance items have been rolled over from prior years due to
staffing constraints. Staff anticipates that the parks maintenance operations, and
associated maintenance costs, should return to normal levels in FY 18/19, with standard
adjustments for inflation.
Currently, there is an aggregate total of approximately $2,523,289 in the Park
Improvement Funds to fund certain CIP projects. The Park Improvement Zones
(Zones) are separated into three Zones that encompass certain geographic areas within
the City's boundary, including a Community Wide Zone. The Zones were originally
established by the City Council in 1986 to account for the collection or park fees in lieu
of land dedication, consistent with the Quimby Act for residential subdivisions. The fund
also includes fees collected from commercial, industrial, and institutional buildings
(unless exempt). The City Council adopted a policy in which 60% of the fees collected
in the Park Improvement Fund would be used for neighborhood park facilities and 40%
for community park facilities. Funding from the Park Improvement Fund can only be
used for improvement projects that are located within the boundaries of the geographic
area defined by the individual Zone. However, funding from the Community Wide Zone
can be used for park facilities and improvements that benefit the City as a whole.
These typically include projects at AVCP or other projects that provide equal benefit to
all residents. An analysis of the Park Improvement Fund and recommendations for
future spending has been included in a separate report. It should be noted however,
that funding through the Park Improvement Fund is one-time money and will only be
replenished by future development projects within the City. At the City's current
projected build-out, staff estimates that there will be approximately $22,000,000 (in
current year dollars) to fund future park improvement projects through the Park
Improvement Fund.
37
Honorable City Council
November 15, 2017
Page 7
Over the years, staff has initiated many cost savings measures in an attempt to lower
maintenance costs, while still providing a wide range of services for the community. For
instance, in response to the drought in 2015, the City Council approved a Drought
Action Plan (DAP) outlining the various actions the City should take to meet the State
Water Resources Control Board mandated water conservation reduction target of 32%.
Prior to the 2015 mandate, the City already had in place a long standing goal of water
conservation that got underway in 2009 when the City accomplished overall water
savings of 16.5% in the City parks and LMD's. This was accomplished by adjusting
irrigation schedules to minimize water use. In 2010 the City installed forty-four
WeatherTrak irrigation controllers in several LMD's and City Parks. This project
reduced water use in the LMD's and parks where the controllers were installed by an
additional 9.5% overall. The total cost to install the WeatherTrak controllers was
approximately $359,292. The total impact to the General Fund was approximately
$87,653, with a return on investment (ROI) of approximately eight years at 2010 water
rates.
Overall, the actions outlined in the DAP resulted in a 52% reduction in the City's
operational water use, which includes City parks, LMD's and the various City owned
buildings and properties. The major contributor to the water savings was the removal of
approximately 19.5 acres of turf in the City parks and approximately 17.4 acres of turf in
the LMD's. The total cost to remove the turf and install drought tolerant and California
native landscaping was $527,504, which was funded through the Metropolitan Water
District's Turf Rebate Program. There were no direct costs to the City.
In addition to water savings, since 2009 the City has completed several energy savings
projects in an effort to lower the City's operational costs related to a reduction in energy
use. Due to these efforts, in April of this year, the City achieved Gold Level status in the
Energy Leader Partnership program sponsored by Southern California Edison and
Southern California Gas. To date, the City has reduced overall energy use in City
operations by 245,930 kWh, or 15.7%. This is equivalent to approximately $34,430
annually in direct cost savings at current energy rates. When considering the fact that
the majority of the lighting projects included the installation of lighting emitting diode
(LED) lighting, that have a considerably longer ,product life than traditional lighting
systems, the actual cost savings are increased substantially due to a reduction in
overall maintenance and replacement costs. The following is a summary of a few
noteworthy projects:
• In 2009, the City Council approved a project to replace the flat roofing material
above the Active Adult Center, Community Center, and Arroyo Vista Recreation
Center with a Title 24 compliant California Cool Roof. The 30-year roofing
material reflects the suns energy, ultimately reducing heat and overall energy
use.
• In 2009, the City obtained $148,000 through an Energy Efficiency and
Conservation Block Grant (EECBG) that was awarded to the City as a part of the
American Recovery and Reinvestment Act (AARA). -In 2010, the City completed
38
Honorable City Council
November 15, 2017
Page 8
Phase I of this work, which included the replacement of seven heating, ventilation
and air conditioning (HVAC) units at the civic center buildings, which included the
Active Adult Center, Community Center and the City Hall Administration Building.
The new high efficiency HVAC units resulted in a 25% reduction in energy use,
as compared to the energy used by the original HVAC system. There was no
cost to the City for this work
• Phase II of this work was completed in 2011 and included retrofitting the existing
lighting systems that serve the Active Adult Center, Community Center, City Hall
Administration Building, Development Services Building, and the Civic Center
and Library parking lots. A major part of this work included the replacement of all
interior lighting, which consisted of traditional fluorescent T12 bulbs, to lower
wattage T8 bulbs. This work resulted in a 25% reduction in energy use. The
Phase II work also included the replacement of the existing parking lot lights and
exterior building lights with LED lighting, and resulted in an estimated reduction in
energy use of approximately 50%. In total, the phase II work resulted in direct
cost savings of approximately $21,000 annually. The total cost for this work was
$107,556, with an impact to the General Fund of approximately $22,000.
$13,690 was funded from the Library Fund (1010) and the balance was funded
by the remaining balance of the EECBG funding. The ROI for the City's portion
of the funding required for this work was less than two years.
• In 2013, the City replaced the walkway and parking lot lighting at Poindexter
Park, Campus Park and the Police Services Center with new LED lighting. The
project resulted in an overall cost savings of approximately $19,367 annually
when considering the reduction in annual maintenance costs, resulting in an ROI
of approximately six years. The total cost for this work was approximately
$242,000, which was funded by the General Fund.
• In 2017, the exterior building lights and parking lot lights at Arroyo Vista
Community Park were replaced with new LED lighting. In addition, the new
recreation trail, access road and two parking lots at the east end of the park were
installed with new LED lighting to provide lighting until the park closes at 10:00
p.m. Although there is an overall increase in energy use due to the increase in
the amount of lighting that was installed as part of the recreational trail project,
the replacement of the existing lighting resulted in a direct cost savings of
approximately $2,860 annually.
Following approval by the City Council, the PRCS CIP will be combined with the PW
CIP to create one consolidated seven year Capital Improvement Program document for
use in budget planning, project prioritizing and scheduling. The PRCS CIP layout and
project coding is consistent with that of the PW CIP to facilitate the merger of the two
documents, although page numbers, appendix references and other administrative
corrections will be required. Staff will return to Council with the combined PW/PRCS
CIP by June, 2018 for final review and approval by City Council resolution. This will
complete the Objective referenced at the beginning of this report. The combined CIP
will be updated annually by staff for use as a reference to identify, define and describe
future planned improvement projects throughout the City.
39
Honorable City Council
November 15, 2017
Page 9
STAFF RECOMMENDATION
Approve the Parks, Recreation and Community Services Department's Seven Year
Capital Improvement Program for FY 2017/18 — FY 2023/24
Attachment:
Parks, Recreation and Community Services Department Seven Year Capital
Improvement Program for FY 2017/18 — FY 2023/24
40
Attachment 1
0° �i2
P
,�,cv
oras
co
AORgTED JON'
CITY OF MOORPARK
PARKS, RECREATION & COMMUNITY
SERVICES DEPARTMENT
Seven Year
Capital Improvement Program
Facilities, Landscaping, Open Space, Parks, and Trails
FY 2017/2018 — FY 2023/2024
JANICE PARVIN, MAYOR
DAVID POLLOCK, COUNCILMEMBER
ROSEANN MIKOS, COUNCILMEMBER
KEN SIMONS, COUNCILMEMBER
MARK VAN DAM, COUNCILMEMBER
STEVEN KUENY
-CITY MANAGER-
JEREMY LAURENTOWSKI
_ -PARKS AND RECREATION DIRECTOR-
November 2017
DRAFT NOV 2017 41
DRAFT NOV 2017 4 2
Table of Contents
Page
A. Introduction A-1
B. Project Descriptions
600 Facilities
Arroyo Vista Recreation Center and Gym(Summary) B-3
601 M0023: Back Up Generator . B-4
602 M0024: HVAC Replacement . B-4
603 M0025: Kitchen Remodel . B-5
604 C0042: Facility Expansion . B-5
605 Security Cameras . B-6
606 Water Conservation Improvements . . B-6
607 Flag Pole Installation . B-7
608 C0048: Gymnasium Expansion . B-7
City Hall/Civic Center Complex(Summary) . B-8
609 C0012: New Library&Civic Center Complex . B-9
610 C0014: Pedestrian Access Improvements . B-9
611 M0023: Back-Up Generator . B-10
612 M0035: Fire Sprinkler System . . B-10
613 Patio Remodel . B-11
614 Water Conservation Improvements . B-11
615 Flag Pole Installation . B-12
616 Security Cameras . B-12
617 Energy Efficiency Improvements. . B-13
High Street Arts Center(Summary) . B-14
618 Roof RenovationB-15
619 Interior Improvements . . . B-15
620 ADA/Building Code Improvements . B-16
Metrolink Parking Lot
621. 7708: Art In Public Places . B-17
Moorpark Library(Summary) . . B-18
622 Restroom ImprovementsB-19
623 Security Cameras . . B-19
624 Parking Lot Improvements . . B-20
625 HVAC Replacement . B-20
Police Services Center(Summary) . . . B-21
626 C0015: Art In Public Places Installation . B-22
627 Landscape ImprovementsB-22
628 Parapet Wall InstallationB-23
629 Additional Parking . B-23
DRAFT NOV 2017 4 3
Table of Contents (Cont.)
Page
Moorpark Public Services Facility(Summary) B-24
630 M0023: Back-Up Generator . B-25
631 Lighting Improvements . B-25
632 Roof Drain Improvements . B-26
633 Outdoor Break Area . B-26
634 Water Conservation Improvements . B-27
635 Fueling Station . B-27
Ruben Castro Human Services Center
636 Sidewalk Installation . . B-28
31 Poindexter Avenue
637 Building Modifications . . . . B-29
Citywide
638 Purchase City StreetlightsB-30
700 Landscape Maintenance Districts (LMDs) & General Landscaping
701 High Street Improvements. . B-32
702 Princeton Avenue Landscape Renovations(Campus Park Area) . B-33
703 Campus Park Median Renovations(Campus Park Area) . B-34
704 Princeton Avenue Oak Tree . . . . . B-35
705 Championship Drive Landscape Renovations(Zone 15) . B-36
706 LA Avenue Parkway and Wall Treatment Renovations . _ B-37
707 LA Avenue Parkway Renovations(Zone 7) . . B-38
708 Poindexter Avenue Landscaping . B-39
709 Spring Road Landscape Improvements(Zone 12) . . . B-40
710 Spring Road Street Trees . . . . . B-41
711 Spring Road Street Trees(Zone 22). . . B-42
712 Metrolink Station Landscape Improvements . . . B-43
713 M0031: Tierra Rejada Road Streetscape Renovation . . . B-44
714 Tierra Rejada/Moorpark Road Intersection Improvements . . B-45
715 City Welcome Sign Improvements . . . . . B-46
716 Off-Ramp Landscape Improvements . . . . B-47
717 Peach Hill Wash Channel Improvements. B-48
800 Open Space
DRAFT NOV 2017 4 4
Table of Contents (Cont.)
Page
900 Parks
Arroyo Vista Community Park(Summary) . B-51
901 Ball Field Lighting . B-52
902 Water Spray Attraction . B-52
903 Pedestrian Bridge Lighting . B-53
904 Ramp/Walkway/Bike Path from Mountain Trail Street. . B-53
905 Softball Fencing Improvements . . B-54
906 Slope Landscaping . B-54
907 C0047: Storage Improvements . . B-55
908 Lease SCE Property . B-55
909 New Pedestrian Bridge . . B-56
910 Sand Volleyball Court . . B-56
Campus Canyon Park(Summary) . B-57
911 Basketball Court Improvements . B-58
912 Replace Playground Equipment . B-58
913 Parking Lot . B-59
Campus Park(Summary) . B-60
914 Restroom Improvements . B-61
915 Pavilion Improvements . . . B-61
916 Replace Playground Equipment.. . . B-62
College View Park(Summary). . B-63
917 Sand Volleyball Court . . B-64
918 Basketball Court Improvements . B-64
919 Dog Park Lighting . B-65
920 Park Improvements . . B-65
921 New Park Sign . B-66
Community Center Park
922 Replace Playground Equipment . . . B-67
Country Trail Park(Summary) . . B-68
923 Playground Improvements&ADA Access . . B-69
924 Restroom Addition . B-69
925 Landscape ImprovementsB-70
926 Parkour Training CircuitB-70
927 Install Trail . B-71
Glenwood Park(Summary) . B-72
928 Basketball Court Lighting . . B-73
929 Sand Volleyball Court . . . . B-73
930• Install Trail . B-74
931 Replace Playground Equipment . . . B-74
932 New Park Sign . B-75
Magnolia Park
933 Replace Playground Equipment . . . B-76
DRAFT NOV 2017 4 5
Table of Contents (Cont.)
Page
Mammoth Highlands(Summary). . B-77
934 Sand Volleyball Court . B-78
935 Basketball Court Lighting ImprovementsB-78
936 Expand Trail . B-79
Miller Park(Summary) B-80
937 Lighting Addition . B-81
938 Loop Trail . B-81
939 Replace Playground Equipment . . B-82
Monte Vista Nature Park(Summary) . . B-83
940 Lighting Improvements . B-84
941 Shade Structure. . B-84
942 Landscape Improvements . B-85
943 Trail System Improvements . B-85
Mountain Meadows(Summary) . B-86
944 C0045: Handball Wall . . B-87
945 Loop Trail . B-87
946 Replace Playground Equipment . B-88
Peach Hill Park(Summary) B-89
947 Lighting Upgrades&Additions . . B-90
948 Picnic Pavilion Improvements . B-90
949 Loop Trail . B-91
950 Sand Play Area . . B-91
951 Replace Playground Equipment . . B-92
Poindexter Park(Summary) B-93
952 Security Camera Improvements . . . B-94
953 Skate Park Fencing . . B-94
954 Park Amenity Improvements . B-95
955 Pathway Improvements . . . B-95
Tierra Rejada Park(Summary) . B-96
956 Lighting Additions . B-97
957 Tennis Court Addition . . B-97
958 Parking Lot Expansion . B-98
959 Replace Playground Equipment . . B-98
Villa Campesina Park(Summary) . B-99
960 Security Improvements . . B-100
961 Replace Playground Equipment . . . . B-100
•
Virginia Colony Park(Summary) . B-101
962 Basketball Court Addition . B-102
963 Replace Playground Equipment . . B-102
DRAFT NOV 2017 46
Table of Contents (Cont.)
Page
Walnut Acres Park
964 Security Cameras . B-103
Citywide Parks (Summary) B-104
965 C0019: Central Irrigation System . B-105
966 Lighting Upgrades . B-105
967 ADA Improvements . B-106
968 Universally Accessible Playground Equipment . B-106
969 BMX/Free Style Bicycle Facility . B-107
970 Sensory Garden. . B-107
971 Disc Golf Course . . B-108
972 Electronic Marquees . . B-108
973 Permanent Game Equipment. . B-109
974 Baseball Field . B-109
975 Bocce Ball CourtB-110
976 Ball Wall . . B-110
977 Update Park Features . B-111
978 Additional Exercise Equipment . B-111
979 Community Pool . B-112
980 Parks and Recreation Master Plan Update. B-112
1000 Trails
1001 Zone 15 Trail Improvements . . B-114
C. Program Expenditure Summary C-1
• Total Program Project Costs: Spread to Funding Year
• Total Program: Spread to Funding Sources
Appendix I: List of Completed Projects I-1
Appendix II: Description of Funding Sources 11-1
Appendix III: List of Potential Projects III-1
DRAFT NOV 2017 4 7
City of Moorpark
Capital Improvement Program
A. Introduction
The Parks, Recreation and Community Services Department Capital Improvement Program (CIP) is a
long-range plan that schedules and prioritizes the department's capital projects over a seven year
period. It also describes each individual project and potential funding source(s). The listed projects
involve capital outlays or nonrecurring expenditures for specifically identified funding sources, and do
not duplicate or include routine maintenance activities or costs. Included projects must meet at least
one of the following criteria:
• It is a new construction project with a total cost of at least $10,000 over the life of the project.
Project costs can include the cost of land, engineering, architectural planning, and contract
services needed to complete the project.
• It is an expansion or addition for an existing facility or facilities with a total cost of at least
$10,000.
• It is a major renovation, improvement, replacement, maintenance, or rehabilitation project for
an existing facility or facilities with a cost of$10,000 or more and a useful life of at least 10
years.
• It is a purchase of major equipment that is needed in connection with a project described above.
The equipment must have a total cost of$10,000 or more with a useful life of at least 7 years.
The Capital Improvement Program document also includes a list of potential projects and feasibility
studies, a list of maintenance and non-capital projects, a summary of completed projects, and a
description of the funding sources.
A summary of the total estimated active program expenditures is as follows:
Section FY 17/18 FY 18/19 FY 19/20 FY 20/21
Facilities $7,447,148 $3,790,700 $38,580,000 $2,250,000
LMDs/Landscaping $2,932,000 $10,365,000 $170,000 $0
Open Space $0 $0 $0 $0
Parks $2,160,004 $14,399,500 $2,440,000 $0
Trails $85,000 $500,000 $0 $0
Total $12,624,152 $29,055,200 $41,190,000 $2,250,000
Section FY 21/22 FY 22/23 FY 23/24 Total
Facilities $0 $500,000 $0 $52,567,848
LMDs/Landscaping $0 $0 $0 $13,467,000
Open Space $0 $0 $0 $0
Parks $200,000 $175,000 $0 $19,374,504
Trails $0 $0 $0 $585,000
Total $200,000 $675,000 $0 $85,994,352
DRAFT NOV 2017 4 8
B. Project Descriptions
Individual project descriptions are set forth in this section. Each project description includes a project
cost estimate, a proposed schedule, and recommended funding sources.
It should be noted that there has been no preliminary engineering performed for most of the projects
programmed in future years. The cost estimates provided for those projects are a rough estimate only
and should not be relied upon to predict actual costs. These estimates were included in the project
descriptions in order to provide a general idea of the total estimated program costs. Individual project
cost estimates will be revised as engineering for each project is developed.
•
DRAFT NOV 2017 B-1 49
FACILITIES
DRAFT NOV 2017 B-2 5 0
City of Moorpark
Capital Improvement Program
Arroyo Vista Recreation Center (AVRC)
4550 Tierra Rejada Road
Location Map
1
0Arroyo
Vista
411 Community Park
re
a
PROJECT AREA
'= I --- 09.._
w m
co��iN N°od `A
irk"Q� L L
AVRC Project Summary:
Project Total Cost
Back-Up Generator $ 128,000
HVAC Replacement $ 100,000
Kitchen Remodel .. $ 150,000
Facility Expansion $2,325,000
Security Cameras $ 35,000
Water Conservation Improvements $ 55,000
Flag Pole Installation $ 12,000
Gymnasium Expansion $2,329,700
Total AVRC Project Costs: $5,134,700
DRAFT NOV 2017 B-3 51
City of Moorpark
Capital Improvement Program
PROJECT: Back-Up Generator Code No. 601
LOCATION: Arroyo Vista Recreation Center Account No. M0023
Project Description
Install a back-up generator and alarm at the Arroyo Vista Recreation Center and install portable generators
for the AVRC sewer lift station (shares project number for portable generators for Public Services Facility
and Community Center.) Objective IV.B.3
Project Funding Schedule Total Cost: $128,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 95,000 33,000
Construction Management
Total 0 95,000 33,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
1000: General Fund 95,000 33,000
Total 0 95,000 33,000 0 0 0 0 0
PROJECT: HVAC Replacement Code No. 602
LOCATION: Arroyo Vista Recreation Center Account No. M0024
Project Description
Remove and replace four HVAC units at the Arroyo Vista Recreation Center (10 ton unit, 12.5 ton unit,
15 ton unit, and 25 ton unit).
Project Funding Schedule Total Cost: $100,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 21/22 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 100,000
Construction Management
Total 0 100,000 0 0 0 0 0 0
Funding Sources .
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
1000: General Fund 100,000
Total 0 100,000 0 0 0 0 0 0
DRAFT NOV 2017 B-4 52
City of Moorpark
Capital Improvement Program
PROJECT: Kitchen Remodel Code No. 603
LOCATION: Arroyo Vista Recreation Center Account No. M0025
Project Description
Design plans and implement renovation of the AVRC kitchen, including upgrading cabinets, replacing
appliances, installing a new sink to comply with Health& Safety Code, and painting.
Project Funding Schedule Total Cost: $150,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 25,000
LandAcquisition...._....._._....._._.__... _...__..__......_.................__. _.._................................ — ........._..__..__.........__._._...._......................._.. —..__... .........._..........._...._........... —._..
Construction/Improvements 125,000
Construction Management
Total 0 0 150,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
1000: General Fund 150,000
Total 0 0 150,000 0 0 0 0 0
PROJECT: Facility Expansion Code No. 604
LOCATION: Arroyo Vista Recreation Center Account No. C0042
Project Description
' Develop design plans and implement improvements to Arroyo Vista Recreation Center, including office
space and activity room expansion. Objective IV..A.21
Project Funding Schedule Total Cost: $2,325,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering _..__._.. 75,000
Land Acquisition
Construction/Improvements _ 2,000,000 --
Construction Management 250,000
Total 0 75,100 0 2,250,000 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
2018:Endowment Fund 75,000
2,250,000
Total 0 75,000 0 2,250,000 0 0 0 0
DRAFT NOV 2017 B-5 5 3
City of Moorpark
Capital Improvement Program
PROJECT: Security Cameras Code No. 605
LOCATION: Arroyo Vista Recreation Center Account No.
Project Description
Install new security cameras. Objective V.A.14
Project Funding Schedule Total Cost: $35,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 10,000
Land Acquisition
Construction/Improvements 25,000
Construction Management
Total 0 35,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 35,000
Total 0 35,000 0 0 0 0 0 0
PROJECT: Water Conservation Improvements Code No. 606
LOCATION: Arroyo Vista Recreation Center Account No.
Project Description
Install hands-free fixtures and low flow or waterless urinals.
Project Funding Schedule Total Cost: $55,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering —
Land Acuisition
Construction/Lnprovements 55,000
Construction Management
Total 0 55,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 55,000
Total 0 55,000 0 0 0 0 0 0
DRAFT NOV 2017 B-6 54
City of Moorpark
Capital Improvement Program
PROJECT: Flag Pole Installation Code No. 607
LOCATION: Arroyo Vista Recreation Center Account No.
Project Description
Install three flag poles (U.S. flag, California flag, and City flag) to replace the single flag pole currently at
the recreation center building entrance.
Project Funding Schedule Total Cost: $12,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 12,000
Construction Management
Total 0 12,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 12,000
Total 0 12,000 0 0 0 0 0 0
PROJECT: Gymnasium Expansion Code No. 608
LOCATION: Arroyo Vista Recreation Center Account No. C0048
Project Description
Expand AVRC gymnasium to include a second basketball court,restrooms, and locker room.
Objective IV.B.9
Project Funding Schedule Total Cost: $2,329,700
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 79,700 ---
Land Acquisition
Construction/Improvements 2,000,000
Construction Management 250,000
Total 0 0 79,700 0 2,250,000 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
2010:Park Development 79,700 - --
Undetermined 2,250,000
Total 0 0 79,700 0 2,250,000 0 0 0
DRAFT NOV 2017 B-7 5 5
City of Moorpark
Capital Improvement Program
Moorpark City Hall / Civic Center Complex
799 Moorpark Avenue
Location Map
1 --I
I
4tC i I , -.
d
r;.
� ,� Everett St ___�
I i T; {
\V\. �
i I i I .
Charles St
PROJECT AREA 11
—1 r
11
I1- � , I
I ' High St
II `
City Hall/Civic Center Complex Project Summary:
Project Total Cost
New City Hall/Civic Center Complex $43,246,008
Pedestrian Access Improvements $ 613,604
Back-Up Generator . $ 105,000
Fire Sprinkler System .... $ 65,000
Patio Remodel $ 25,000
Water Conservation Improvements $ 60,000
Flag Pole Installation .. $ 12,000
Security Cameras $ 40,000
Energy Efficiency Improvements $ 35,000
Total City Hall/Civic Center Complex Project Costs: $44,201,612
DRAFT NOV 2017 B-8 5 6
City of Moorpark
Capital Improvement Program
PROJECT: New Library and Civic Center Complex Code No. 609
LOCATION: City Hall/Civic Center Account No. C0012
Project Description
The project includes the acquisition of property, design, and construction of a city hall and civic center
complex, including the library, on the northwest corner of Moorpark Avenue and High Street. Project
activities for FY 17/18 will focus on design and construction of the library only. **Library component to
be separated out under a separate CIP number for FY 18/19. Objective 1V.A.24
Project Funding Schedule Total Cost:$43,246,008
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 834,462 93,515
Land Acquisition 451,483 500,000
Construction/Improvements 2,866,548 35,000 000
Construction Management 3,500,000
Total 1,285,945 3,460,063 0 38,500,000 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 21/22 FY 23/24
3001:City Hall Improvement 1,036288 3,366,548 38,500,000
2018:Endowment Fund 249,657 93,515 —
Total 1,285,945 3,460,063 0 38,500,000 0 0 0 0
PROJECT: Pedestrian Access Improvements Code No. 610
LOCATION: City Hall/Civic Center Account No. C0014
Project Description
Create an ADA accessible pedestrian access from Moorpark Avenue through the Civic Center complex
and create an improved bus turnout. Objective W A.19
Project Funding Schedule Total Cost: $613,604
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 37,058 23,518 _
Land Acquisition
Construction/Improvements _ 511,131
Construction Management 41,897
Total 37,058 576,546 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
2001:Traffic System Mgmt 20,621 485,523
2411:TDA Article 3 11,727 71,023
2414:TDA Article 8C 4,710 20,000
Total 37,058 576,546 0 0 0 0 0 0
DRAFT NOV 2017 B-9 5 7
City of Moorpark
Capital Improvement Program
PROJECT: Back-Up Generator Code No. 611
LOCATION: City Hall/Civic Center Account No. M0023
Project Description
Install a portable generator to serve the Active Adult Center and Community Center (shares project
number for portable generators for AVRC and Public Services Facility.) Objective IV.B.3
Project Funding Schedule Total Cost: $105,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acuq on ---- — -
Construction/Improvements 105,000
Construction Management
Total 0 105,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
1000: General Fund 105,000
Total 0 105,000 0 0 0 0 0 0
PROJECT: Fire Sprinkler System Code No. 612
LOCATION: City Hall/Civic Center Account No. M0035
Project Description
Install a fire sprinkler system at the Active Adult Center and Community Center building.
Project Funding Schedule Total Cost: $65,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements - 65,000
Construction Management
Total 0 65,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
1000: General Fund 65,000
Total 0 65,000' 0 0 0 0 0
DRAFT NOV 2017 B-10 5 8
City of Moorpark
Capital Improvement Program
PROJECT: Patio Remodel Code No. 613
LOCATION: City Hall/Civic Center Account No.
Project Description
Renovate the patio at the Development Services Building and replace the plywood decking with
permanent material, such as recycled plastic.
Project Funding Schedule Total Cost: $25,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/2.2_ FY 22/23 FY 23/24
Design/Engineering _--
Land Acquisition
Construction/Improvements 25,000
Construction Management
Total 25,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/1.9 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 25,000
Total 25,000 0 0 0 0 0 0
PROJECT: Water Conservation Improvements Code No. 614
LOCATION: City Hall/Civic Center Account No.
Project Description
Replace all restroom fixtures throughout the Civic Center complex with hands-free fixtures and install
waterless urinals at the Active Adult Center and Community Center.
Project Funding Schedule Total Cost: $60,000
Prior Yrs s FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
• Land Acquisition
Construction/Improvements 60,000 — -
Construction Management
Total 0 60,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 60,000
Total 0 60,000 0 0 0 0 0 0-
DRAFT NOV 2017 B-11 5 9
City of Moorpark
Capital Improvement Program
PROJECT: Flag Pole Installation Code No. 615
LOCATION: City Hall/Civic Center Account No.
Project Description
Install three flag poles (U.S. flag, California flag, and City flag) to replace the single pole located near the
Active Adult Center.
Project Funding Schedule Total Cost: $12,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering -- —
Land Acquisition
Construction/Improvements 12,000
Construction Management
Total 12,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 12,000
Total 12,000 0 0 0 0 0 0
PROJECT: Security Cameras Code No. 616
LOCATION: City Hall/Civic Center Account No.
Project Description
Determine appropriate locations and install security cameras throughout the Civic Center complex.
Objective V.A.14
Project Funding Schedule Total Cost: $40,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 10,000
Land Acquisition
Construction/Improvements 30,000
Construction Management
Total 40,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 40,000
Total 40,000 0 0 0 0 -0 0
DRAFT NOV 2017 B-12 6 0
City of Moorpark
Capital Improvement Program
PROJECT: Energy Efficiency Improvements Code No. 617
LOCATION: City Hall/Civic Center Account No.
Project Description
Install energy efficiency improvements including a drop-down ceiling with insulation at the Active Adult
Center and in the Citrus Room, and replace windows at the Active Adult Center, Community Center, and
the Administration building with energy efficient dual-pane windows.
Project Funding Schedule Total Cost: $35,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering....
Land Acquisition
Construction/Improvements 35,000
Construction Management
Total 0 35,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 35,000
Total 0 35,000 0 0 0 0 0
DRAFT NOV 2017 B-13 61
City of Moorpark
Capital Improvement Program
High Street Arts Center (HSAC)
33/45/61 East High Street
Location Map
i
- A
Charles St 1
- PROJECT AREA ' i—
' ` _.5 I N
y I
��` fl I— t
1
1 High St
-,a r
`o
IV j1
r 1 ; r
I 1-7-7I-1 h i
High Street Arts Center Project Summary:
Project Total Cost
Roof Renovation $ 80,000
Interior Improvements $ 65,000
ADA Compliance $ 40,000
Total High Street Arts Center Project Costs: $185,000
DRAFT NOV 2017 B-14 6 2
City of Moorpark
Capital Improvement Program
PROJECT: Roof Renovation Code No. 618
LOCATION: High Street Arts Center Account No.
Project Description
Replace the theater roof.
Project Funding Schedule Total Cost: $80,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition _
Construction/I provements _._80,000 — _.__...._._....._._..............___..................._...---...._..__.....__........_._...--•-.--......._........_.._...
Construction Management
Total 0 0 80,000 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 80,000
Total 0 0 80,000 0 0 0 0
PROJECT: Interior Improvements Code No. 619
LOCATION: High Street Arts Center Account No.
Project Description
Replace carpet throughout the theater.
Project Funding Schedule Total Cost: $65,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
—
Land Acquisition
Construction/Improvements 65,000
Construction Management
Total 0 65,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 65,000
Total 0 65,000 0 0 0 0 0
DRAFT NOV 2017 B-15 6 3
City of Moorpark
Capital Improvement Program
PROJECT: ADA & Building Code Compliance Code No. 620
LOCATION: High Street Arts Center Account No.
Project Description
Renovate stage and install guardrail at the rear balcony to meet ADA requirements.
Project Funding Schedule Total Cost: $40,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering._....._.....,._................._.................._.
�_ -- Land Acquisition
Construction/Improvements _.._.._._..._....._.._..._._....__...._.._..__40,000
Construction Management
Total 40,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 40,000
Total 40,000 0 0 0 0 0 0
DRAFT NOV 2017 B-16 6 4
City of Moorpark
Capital Improvement Program
LOCATION: Metrolink Parking Lot (North) Code No. 621
PROJECT: Art In Public Places Account No.
Location Map
Charles St
L It-
CO
1 i
High St = -—
PROJECT AREA
1st St _! j �,'��1 Dorothy Ave L._ , r 1
' , '
7 -- - - - ---, '
1 _
ii j I f ' _ _�-_
Project Description
Install public art at Metrolink North Parking Lot.
Project Funding Schedule Total Cost: $225,000 j
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 225,000
Construction Management
Total 0 225,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
2007:Art in Public Places 225,000
Total 0 225,000 0 0 0 0 0
DRAFT NOV 2017 B-17 6 5
City of Moorpark
Capital Improvement Program
Moorpark City Library
699 Moorpark Avenue
Location Map
Everett St
I PROJECT AREA --� I ! , j
7 1 1 I TIT , i 1 I I
F:,,,,,,,..,,,,,\.. ... .,sits` Charles St
1 v t 1
;L- r —! _' , i4_,
oo High St
, i —
—.
Moorpark City Library Project Summary:
Proiect Total Cost
Restroom Improvements $ 25,000
Security Cameras $ 35,000
Parking Lot Expansion $155,000
HVAC Replacement $ 85,000
Total Moorpark City Library Project Costs: $300,000
DRAFT NOV 2017 B-18 6 6
City of Moorpark
Capital Improvement Program
PROJECT: Restroom Improvements Code No. 622
LOCATION: Moorpark City Library Account No.
Project Description
Install floor drains and hands-free fixtures in the library restrooms.
Project Funding Schedule Total Cost: $25,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
----....__...__..__.._.._.__...._...__...------..__.._._._.__._.................._..............._............._..._..----- _..------......_._._........._.._........----..._....---....---.._....._...._._.._..._.........--------......._..._....._._..— ......._._...__....__....--
Land Acquisition
Construction/Improvements 25,000
Construction Management
Total 0 25,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 25,000
Total 0 25,000 0 0 0 0 0 0
PROJECT: Security Cameras Code No. 623
LOCATION: Moorpark City Library Account No.
Project Description
Determine appropriate locations and install security cameras at the library. Objective V.A.14
Project Funding Schedule Total Cost: $35,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 10,000 —
Land Acquisition ——
Construction/Improvements 25,000
Construction Management
Total 35,000 0 0 0 0 0 0
Funding Sources -
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 35,000
Total 35,000 0 0 0 0 0 0
DRAFT NOV 2017 B-19 6 7
City of Moorpark
Capital Improvement Program
PROJECT: Parking Lot Expansion Code No. 624
LOCATION: Moorpark City Library Account No.
Project Description
Expand the library parking lot.
Project Funding Schedule Total Cost: $155,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 15,000
Land Acquisition
Construction/Improvements 140,000
Construction Management
Total 155,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY Y 22/23 FY 23/24
Undetermined 155,000
Total 155,000 0 0 0 0 0 0
PROJECT: HVAC Replacement Code No. 625
LOCATION: Moorpark City Library Account No.
Project Description
Replace the HVAC units at the library.
Project Funding Schedule Total Cost: $85,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition _--_—
Construction/Improvements 85,000
Construction Management
Total 0 85,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 85,000
Total 0 85,000 0 0 0 0 0
DRAFT NOV 2017 B-20 6 8
City of Moorpark
Capital Improvement Program
Moorpark Police Services Center
610 Spring Road
Location Map
1�
—Pli nceton Ave
E High St — �—�r_. _______=Is,j
� i 11 ..
- RCIJEC AREA
j
N
I i tr
—tet S i 1
\ XI(71' ? 41
i _ - -
fr
I t`
End S _ �r'
A cc l °` rr
N' i i- t
I
1
11111/
/ 1
Moorpark Police Services Center Project Summary:
Proiect Total Cost
Art In Public Places Installation $167,500
Landscape Improvements $ 75,000
Parapet Wall Installation $165,000
Additional Parking $217,000
Total Moorpark Police Services Center Project Costs: $624,500
DRAFT NOV 2017 B-21 6 9
City of Moorpark
Capital Improvement Program
PROJECT: Art In Public Places Installation Code No. 626
LOCATION: Moorpark Police Services Center Account No. C0015
Project Description
Install artwork at the Police Services Center titled "Thin Blue Line". The art piece features an abstract
figure of a police officer made from mirror polished stainless steel set on a pedestal located in the front
entry plaza. The abstract figure is split down the middle and at night the artwork will be illuminated
through the middle by a blue light to create a"thin blue line"through the piece.
Project Funding Schedule Total Cost: $167,500
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 10,961 4,914
Land Acquisition
Construction/Improvements 151,625
Construction Management
Total 10,961 156,539 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
2007:Art in Public Places 10,961 156,539
Total 10,961 156,539 0 0 0 0 0 0
PROJECT: Landscape Improvements Code No. 627
LOCATION: Moorpark Police Services Center Account No.
Project Description
•Renovate landscaping at the Police Services Center. Renovation will include installing alternatives to the
current landscape material adjacent to the vehicular parking stalls, and renovating the landscaping around
the outside perimeter of the building.
Project Funding Schedule Total Cost: $75,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
------- -
Land Acquisition — -_ _---------- -------- -----
Construction/Improvements 75,000
Construction Management
Total 0 75,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 75,000
Total 0 75,000 0 0 0 0 0
DRAFT NOV 2017 B-22 7 0
City of Moorpark
Capital Improvement Program
PROJECT: Parapet Wall Installation Code No. 628
LOCATION: Moorpark Police Services Center Account No.
Project Description
Install parapet walls above the PSC building structure to screen roof top equipment from view.
Project Funding Schedule Total Cost: $165,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering- -- _._._. .............._.........__._.._25,000
Land Acquisition
Construction/Improvements 125,000
Construction Management 15,000
Total 0 0 165,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 165,000
Total 0 0 165,000 0 0 0 0 0
PROJECT: Additional Parking Code No. 629
LOCATION: Moorpark Police Services Center Account No.
Project Description
Evaluate the feasibility of converting a portion of the gated parking at the Police Services Center to public
parking.
Project Funding Schedule Total Cost: $217,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/_22 FY 22/23 FY 23/24
Design/Engineering 30,000
Land Acquisition
Construction/Improvements ---- 175,000 ___—
Construction Management 12,000
Total 0 0 217,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 217,000
Total 0 0 217,000 0 0 0 0 0
DRAFT NOV 2017 B-23 71
City of Moorpark
Capital Improvement Program
Moorpark Public Services Facility
Y
627 Fitch Road
Location Map
Princeton Ave r -
E High St �` PROJECT AREA
Jr
(itch Ave
11.0 ;
H II
to •
r
c
VI
;:
>; 1 Flinn ! ;r
,iLI f
1 / i1/,,
i l l i 1 I ;_ ' - 1 f
Moorpark Public Services Facility Project Summary:
Project Total Cost
Back-Up Generator $106,000
Lighting Improvements $ 75,000
Roof Drain Improvements .. $ 50,000
Outdoor Break Area $ 50,000
Water Conservation Improvements .. $ 25,000
Fueling Station $500,000
Total Moorpark Public Services Facility Project Costs: $806,000
DRAFT NOV 2017 B-24 7 2
City of Moorpark
Capital Improvement Program
PROJECT: Back-Up Generator Code No. 630
LOCATION: Moorpark Public Services Facility Account No. M0023
Project Description
Install a portable generator at the Public Services Facility (shares project number for portable generators
for AVRC and Community Center.) Objective IV.B.3
Project Funding Schedule Total Cost: $106,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 106,000
Construction Management
Total 0 0 106,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/2.2 FY 22/23 FY 23/24
1000:General Fund - 106,000
Total 0 0 106,000 0 0 0 0 0
PROJECT: Lighting Improvements Code No. 631
LOCATION: Moorpark Public Services Facility Account No.
Project Description
Replace parking lot lighting at the Public Services Facility with LED lighting or other energy efficient
alternative.
Project Funding Schedule Total Cost: $75,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering10,000 —— — —— — ---
Land Acquisition
Construction/Improvements 65,000Construction Management
Total 0 75,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 75,000
Total 0 75,000 0 0 0 0 0 0
DRAFT NOV 2017 B-25 7 3
City of Moorpark
Capital Improvement Program
PROJECT: Roof Drain Improvements Code No. 632
LOCATION: Moorpark Public Services Facility Account No.
Project Description
Improve the roof top drainage system at the Public Services Facility to minimize runoff onto the parking
lot and adjacent hardscape surfaces.
Project Funding Schedule Total Cost: $50,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 50,000
Construction Management
Total 0 50,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 50,000
Total 0 50,000 0 0 0 0 0
PROJECT: Outdoor Break Area Code No. 633
LOCATION: Moorpark Public Services Facility Account No.
Project Description
Install an outdoor break area with shade for employees assigned to the Public Services Facility.
Project Funding Schedule Total Cost: $50,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 50,000
Construction Management
Total 0 0 50,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 50,000
Total 0 0 50,000 0 0 0 0 0
DRAFT NOV 2017 B-26 7 4
City of Moorpark
Capital Improvement Program
PROJECT: Water Conservation Improvements Code No. 634
LOCATION: Moorpark Public Services Facility Account No.
Project Description
Install hands-free fixtures and waterless urinals in the Public Services Facility restrooms.
Project Funding Schedule Total Cost: $25,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 25,000
Construction Management
Total 0 25,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY Y_ 21/22 FY 22/23 FY 23/24
Undetermined 25,000
Total 0 25,000 0 0 0 0 0 0
PROJECT: Fueling Station Code No. 635
LOCATION: Moorpark Public Services Facility Account No.
Project Description
Install an alternative fuel fueling station or electric vehicle charging station at the Public Services Facility.
Project Funding Schedule Total Cost: $500,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering —
Land Acquisition
Construction/Improvements _ 500,000
Construction Management
—
Total 0 0 0 0 0 500,000 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined -- 500,000 -_
Total 0 0 0 0 0 500,000 0
DRAFT NOV 2017 B-27 7 5
City of Moorpark
Capital Improvement Program
LOCATION: Ruben Castro Human Services Center Code No. 636
(612 A-B Spring Road)
PROJECT: Sidewalk Installation Account No.
Location Map
Princeton Ave
E High St - —
r
PROJECT AREA
FitchAve
cc
vai H
Project Description
Install Sidewalk on west side of Minor Street between Flynn Avenue and Fitch Avenue.
Project Funding Schedule Total Cost: $75,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/En ig neering 8,000
Land Acquisition
Construction/Improvements 67,000
Construction Management
Total 0 75,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 75,000
Total 0 0 75,000 0 0 0 0 0
DRAFT NOV 2017 B-28 76
•
City of Moorpark
Capital Improvement Program
LOCATION: 31 Poindexter Avenue Code No. 637
PROJECT: Building Modifications Account No.
Location Map
t- H
i
1
High St ,
PROJECT AREA
\ i
Poindexter Ave ___ , '3)__L
1st St —
Qi ! j I
I i
—_CO H I I I _
G_
L
is I - I I 1 -
Project Description
Modify building to accommodate widening of Moorpark Road.
Project Funding Schedule Total Cost: $150,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
— — Design/Engineering _.._.._..._....25,000
— Land Acquisition
—
Construction/Improvements 125,000 • _ _
Construction Management
Total 0 0 150,000 0 ' 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22. FY 22/23 FY 23/24
Undecided 150,000
Total 0 0 150,000 0 0 0 0 0
DRAFT NOV 2017 B-29 7 7
1
City of Moorpark
Capital Improvement Program
LOCATION: Citywide Code No. 638
PROJECT: Purchase City Streetlights Account No.
Location Map
Mooipr k i0
c:ourvtry Club d
c Mao mark
61
o` Campus Park Dr
c
Moor ark /.°'tAve Park
47.0.
O
o :1
e _
.. .. .. r♦-=__-=tosAngelesAve---- �'_
/
ti
i pow,.
n Celt(I
INN
r
k
Citywide Locations
Project Description
Purchase existing City streetlights and convert them to a more energy efficient lighting source. Objective
VI. A .7
Project Funding Schedule Total Cost: $2,200,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements _ 2,200,000
Construction Management
Total 2,200,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
2018:Endowment 2,200,000
Total 2,200,000 0 0 0 0 0 0
DRAFT NOV 2017 B-30 7 8
Landscape Maintenance Districts (LMDs)
General Landscaping
DRAFT NOV 2017 B-31 7 9
City of Moorpark
Capital Improvement Program
LOCATION: High Street Code No. 701
PROJECT: High Street Improvements Account No.
Location Map
_
Ili f
—: I Charles St I
r N ii
f > N ! 1!
c
—Q m i t_
co I To
1.
PROJECT AREA
ilit
i
Project Description
Improve sidewalks on High Street at Pepper Tree locations. Install new site furnishings on High Street.
Project Funding Schedule Total Cost: $2,875,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 125,000
Land Acquisition
Construction/Improvements 2,500,000
Construction Management 250,000
Total 0 0 2,875,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
2300:84-2 Citywide LLMD -_ 2,875,000
Total 0 0 2,875,000 0 0 0 0 0
DRAFT NOV 2017 B-32 8 0
City of Moorpark
Capital Improvement Program
LOCATION: Campus Park Area Code No. 702
PROJECT: Princeton Avenue Landscape Renovations Account No.
Location Map
1 S! -l a• .ra=i ' r
1 T'-. 1-i} �' -� r 1 _ _. � -7 is
PROJECT AREA
onaldaReagan■ viYr^'�'�'�
1
Project Description
Renovate median and parkway landscaping on Princeton Avenue, removing the gazania in the medians
south of Highway 118 and planting drought tolerant plants both north and south of Highway 118.
Objective V.A.17
Project Funding Schedule Total Cost: $285,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering..._................................._.._ 35,000
Land Acquisition
Construction/Improvements 250,000
Construction Management
Total 0 0 285,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
2300: 84-2 Citywide LLMD 285,000
Total 0 0 285,000 0 0 0 0 0
DRAFT NOV 2017 B-33 81
City of Moorpark
Capital Improvement Program
LOCATION: Campus Park Area Code No. 703
PROJECT: Campus Park Median Renovations Account No.
Location Map
�. •
i L I�111 LC
J1 _ I i 1—, '"i
:r 1 - lit I
1 1 ,to, - i C f ii L}
1 ,� 7 h rif 1 r •,LL 117 11:11,_--1. II i
1. , :i-rl ~ GI I_LJ_I`I I ' i [�-t _ 1 I -rm4
Q r-1 .1—I -T-3.1- =T1— i -..m--r t- - L j
'�sr -�- 1-- -":7'
7 i.1 u-ri l IJ 7':L F -1 -__1
'� -T-54-11s..-
J,r1 j5.
x 1:-, �r rr1 -1 F u i -
4-_' `pROI,t�CTAt ►, 4— 1 •IF Ow g, `1n -
1 r 1- 14 C I P61- i s — a
� -1-1 1 1 ' R1 a Il t -,
" rnr h - �--�% ',Tr i -
I I I1 f 1 111111 I i - — — - -
r...........•"..."""=' Ronald•Reagan•Fwy
~
?t'
— ifJu'i —
1
Project Description
Renovate the landscaped medians and parkways on Campus Park Drive utilizing drought tolerant plant
material. Objective V.A.17
Project Funding Schedule Total Cost: $400,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Desi/Engineering- 40,000
Land Acquisition
Construction/Improvements 360,000 ___
Construction Management
Total 0 0 400,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
2300: 84-2 Citywide LLMD — 400,000
Total 0 0 400,000 0 0 0 0 0
DRAFT NOV 2017 B-34 8 2
City of Moorpark
Capital Improvement Program
LOCATION: Campus Park Area Code No. 704
PROJECT: Princeton Avenue Oak Tree Account No.
Location Map
(7,
‹L-
0
4-4
(..)
PROJECT AREA .c
ndor
Princeton Ave
Dr
1p, e CD161"3
„-i _
-N
_
Project Description
Relocate the large oak tree on Princeton Avenue. Possible locations include the 80 acre open space parcel, or
the existing location of the Chamber of Commerce building on High Street (to provide a focal feature for the
downtown area).
Project Funding Schedule Total Cost: $65,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 65,000
Construction Management
Total 0 0 65,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 65,000
Total 0 0 65,000 0 0 0 0 0
DRAFT NOV 2017 B-35 83
City of Moorpark
Capital Improvement Program
LOCATION: Championship Drive (Zone 15) Code No. 705
PROJECT: Championship Drive Landscape Renovations Account No.
Location Map
c
tf 0,am41°t'Sh�4 - `m
2
PROJECT AREA
Project Description
Renovate landscaping on Championship Drive. Improvements to include adding street trees adjacent to down
slopes to screen lower homes, replacing the metal rail fence adjacent to Walnut Canyon Road with a three-
rail fence to match other train fencing, and installing plant material and/or bollards a the equestrian staging
area to prevent vehicular access into the drainage channel (approx.. 165,000 sq. ft.).
Project Funding Schedule Total Cost: $2,085,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
—._._._._........_Design/Engineering __....._._.._.._.. — ........_._._85,000..._.. —...__...__...._.__._......_ -- —..
Land Ac uisition
Construction/Improvements _ 2,000,000 —
Construction Management
Total 0 2,085,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY Y 22/23 FY 23/24
2315:Country Club Estates 2,085,000
Total 0 2,085,000 0 0 0 0 0 0
DRAFT NOV 2017 B-36 8 4
City of Moorpark
Capital Improvement Program
LOCATION: Los Angeles Avenue (Citywide) Code No. 706
PROJECT: LA Avenue Parkway and Wall Treatment Renovations Account No.
Location Map
Li IL I ' -0
, cc
—
Los Angeles Ave
711 ____
-PROJECT AREA
IJ
71-, 11 1 -1
Project Description
Renovate the landscaped parkways and enhance the wall treatments on the north side of LA Avenue, from
Spring Road to Millard. Wall enhancements will include removal and replacement of the existing vine, stone
pilasters, and a wall with a stucco finish. Objective V.B.6
Project Funding Schedule Total Cost: $180,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Eugineering 55,000
Land Acquisition
Construction/Improvements 125,000
Construction Mimagement
Total 0 0 180,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
2300: 84-2 Citywide LLMD 180,000
Total 0 0 180,000 0 0 0 0 0
DRAFT NOV 2017 B-37 85
City of Moorpark
Capital Improvement Program
LOCATION: Los Angeles Avenue (Zone 7) Code No. 707
PROJECT: LA Avenue Parkway Renovations Account No.
Location Map
I 1
c a—'
a
2 IFa_ -I , 1 (n- N
r-- gJ; Ili;l --
-=- r =ROJ CTAREA
L I -i� 1,11,,_L _i -
-
--i Nisi Nu
mm m
p IN ' ' / _!am is _. ,lit .
Project Description
Renovate the landscaped parkway on the north side of LA Avenue between Shasta Avenue and Gabbert 1
Road to include drought tolerant plant material. Replace the existing pear trees with Crepe Myrtle trees.
Project Funding Schedule Total Cost: $155,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 25,000
Land Acquisition
Construction/Improvements 130,000
Construction Management
Total 0 0 155,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
2307:84-2 LA Ave 155,000
Total 0 0 155,000 0 0 0 0 0
DRAFT NOV 2017 B-38 8 6
City of Moorpark
Capital Improvement Program
LOCATION: Poindexter Avenue Code No. 708
PROJECT: Poindexter Avenue Landscaping Account No.
Location Map
M �
li
IliI
1
4_,„„uLL1 ii p 11.' Poinclgai
X1.1 11
r-�' f ►ilnll Chaparal
1 1 4/111111 Middk
111
& > ME ��ou�1 School
A 'ROTECFA'i VIII
������. I 1 I. ■fflu'
7 A1/4 _ iii■ _
IY � —I � amEN 1 ��
1Y mid
C ■■ ■
_e_____,) MIL u rc\ L
r -- - iii - F I I ----,
Project Description
Landscape north side of Poindexter Avenue from Gabbert Road east to vicinity of Chaparral School.
Objective V.C.2
Project Funding Schedule Total Cost: $170,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering _ _......_...._-45,000
Land Acquisition
Construction/Improvements 125,000
Construction Management
Total 0 0 0 170,000 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 170,000
Total 0 0 0 170,000 0 0 0 0
DRAFT NOV 2017 B-39 8 7
City of Moorpark
Capital Improvement Program
LOCATION: Spring Road (Zone 12) Code No. 709
PROJECT: Spring Road Parkway Renovation Account No.
Location Map
II _ -
I
fy
1 71, ; _
1� r =t -PROJECTA RHEA:
11
r. I .'1 J — - -
I
�I
, - I
.– may _ \ ;
rm. ,. %+' '"ti' ory , , Il.I1 I -=--1.
1 1 ,V\�,e` �\t." ,�-+�- _I � r+efo Relada Road -
J , 1111 r 1 171,.;.. ,j" ---1
t 1
-TY .S .0. -.>v",--.-.a'YY-tt-- I'-) .-
Project Description
Renovate landscaped medians and parkways on Spring Road.
Project Funding Schedule Total Cost: $545,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Desi/Engineering—__ 55,000
Land Acquisition... -- �_._.._._..._. - – ___
Construction/Improvements —_ - 490,000 -
Construction Management
Total 0 545,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
2312: 84-2 Carlsberg_ 408,750
2300: 84-2 Citywide LLMD 136,250
Total 0 545,000 0 0 0 0 0 0
DRAFT NOV 2017 B-40 8 8
City of Moorpark
Capital Improvement Program
LOCATION: Spring Road Code No. 710
PROJECT: Install Street Trees Account No.
Location Map
1111
J �r '° oras r 1/isar, war LIER-iwo
4.mum
weft
4111.111 ► s •�
&MIMMMEi.=al— RI =
r■ ��i
(jjjJ� . 1111 101/4
1NO
.11MAW MEM*
\11 I I I I I I I 1 I I I I)1 I l I I I I I I 1 I h 1 II-11111111111 .1 1. I.1 Ic I /\
Project Description
Install street trees on west side of Spring Road between Arroyo Simi and Peach Hill Road .
Project Funding Schedule Total Cost: $65,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering —
Land Acquisition
Construction/Improvements 65,000
Construction Management
Total 0 0 65,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 65,000
Total '0 0 65,000 0 0 0 0 0
DRAFT NOV 2017 B-41 89
City of Moorpark
Capital Improvement Program
LOCATION: Spring 22) Code No. 711
P g Road (Zone
PROJECT: Spring Road Trees Account No.
Location Map
I --. es,% ' `+t
M•, b+�
' „ .- 1I , ° `;2714.0Q,
it`�i
r i-.Y 1i':_.'--,'::'
a i- `4'%.; -;.-
' °- .._; is nlV 44,;c
Jwl ' 1tiIv • 1
i 7; i 1a I t� u'+i - .Lr 1 A
41
/ ` is
/
F �■ — es
r ,
I11,
Iltnllnll1;711llu •U�hi:'i`e,I ` wiliZip t oU,U�
Project Description
Plant additional trees on the slopes the length of Spring Road on the west side of the street.
Project Funding Schedule Total Cost: $25,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 25,000
Construction Management
Total 0 25,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
2322:Moorpark Highlands 25,000
Total 0 25,000 0 0 0 0 0 0
9 0
DRAFT NOV 2017 B-42
City of Moorpark
Capital Improvement Program
LOCATION: Metrolink Station Code No. 712
PROJECT: Metrolink Station Landscape Improvements Account No.
Location Map
I
Charles St
SI vi 1.
gm
High St
f0
Poindexter Ave � _ Dorothy Ave
— - 1st St PIiOJECTA_RE�4 — I___
1 I f -
ril ____ __ ____ 1 1 , _ h _ 1 F----,____
Project Description
Renovate the landscaping at the Metrolink train station. Remove non-native landscaping along the pedestrian
access walkway from Moorpark Avenue to the station and replace with native plant material.
Project Funding Schedule Total Cost: $25,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering_......_..
Land Acquisition.. --— -
Construction/Im_provements - 25,000
Construction Management
Total 0 0 25,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
2300: 84-2 Citywide LLMD 25,000 —_........__......_....._......._....
Total 0 0 25,000 0 0 0 0 0
DRAFT NOV 2017 B-43 91
City of Moorpark
Capital Improvement Program
LOCATION: Tierra Rejada Road Code No. 713
PROJECT: Tierra Rejada Road Streetscape Renovation Account No. M0031
Location Map
m- TrI 1 ^ ! r J
I —1,--1 I___—— - :773 1 arige
ti �y , l
L �J
� 111171 1 II I�' II II 1I
* J . r £
A " I r'.1-1.:I, 1-
' FL
''L' ` � 141
II µ� 1I r} --,J ; J / t',4.',:'-- S -"II
,,,, r.
TY 6. t& E- .11 11 7 1 ti --;±:
-4:!:......,--,--
'�C� , 1. +1'L� �� -Y' �iiw i u�ne� X1',1 1� ^
,'..:a' �ry a ",:".7r.-1 -'-\.,..—'' II-Il 11 yJ� i1 ' 1 - {.�T: 4 "+'
•
d 1! 1 nrit": �' , � �4 11 --i- '_-'311110---c -: 'c7'k4j��t�a0�-4-%'..V,,
. __
1 5 ��ulwvi r, Aft% `�Ltkpe,-�i f -rn�+ . ° `CJy�`� K
>'`�S,� MlllkNil Qpb i . « r t.: l -� mtit�i�n .` "�
` � 2Iffin nen \f'v 0I�.► ,f�' 7 L'I`,
Project Description
Renovate parkway and median landscaping using native and/or drought tolerant trees, plants, and materials.
Project Funding Schedule Total Cost: $2,800,351
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 56,878 65,000
Land Acquisition
Construction/Improvements 348,473 80,000 2,250,000
Construction Management
Total 405,351 145,000 2,250,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
1000:General Fund 381 201 145,000 2,250,000
2302: 84-2 Steeple Hill 24,150
Total 405,351 145,000 2,250,000 0 0 0 0 0
9 2
DRAFT NOV 2017 B-44
City of Moorpark
Capital Improvement Program
LOCATION: Intersection of Tierra Rejada Road and Moorpark Road Code No. 714
PROJECT: Tierra Rejada/Moorpark Road Intersection Improvements Account No.
Location Map
' ` - 1
. .
•
itttw
\
41000
gergilAno?4V
iimmv so
Tierra Rejada Rd
� y
� f
Project Description
Landscape excess right-of-way on southeast corner of Tierra Rejada Road and Moorpark Road and install
standard curb and gutter. Objective V.B.7
Project Funding Schedule Total Cost: $95,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 20,000
Land Acquisition
Construction/Improvements 75,000
Construction Management
Total 9 0 95,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 95,000
Total 0 0 95,000 0 0 0 0 0
DRAFT NOV 2017 B-45 9 3
1
City of Moorpark
Capital Improvement Program
LOCATION: Multiple Locations Code No. 715
PROJECT: City Welcome Signs Account No.
Location Map
Sr
pilau Ea AREA
•
5, 0 0
Sh Tvn�t Qt \ ,
"c A� \%.. `
0 e1a`'
'Tierra Relada Rd - iII.r
ngr.
Colony
i .
tvrvY Cdd'
Project Description
Install new City welcome signs on Tierra Rejada Road and Princeton Avenue, including lighting.
Project Funding Schedule Total Cost: $132,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering_— 12,000
Land Acquisition
Construction/Improvements 120,000
Construction Management — —
Total 0 132,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 132,000
Total 0 132,000 0 0 0 0 0 0
DRAFT NOV 2017 B-46 9 4
City of Moorpark
Capital Improvement Program
LOCATION: Tierra Rejada Road & LA Avenue On/Off-Ramp Areas Code No. 716
PROJECT: Off-Ramp Landscape Improvements Account No.
Location Map
iiiiiiiiiiii it \
hIII,!,ti
itV ._�iA .�
,
amo _ rl:demily
1:31.ulciiiiie i f ,e, .are
°II'I""°I'!"".TSL �sPa�+�` _. V-i
IIHII13"..
�: r ,, = . , VOA. P AREAS
INIMPAIN
Loll •.=.....!... '44m..,..*„..:22-qt.....w.., ;,.
„I, i f1�1i111111t.�. ` 1S.�. ,�
Ii I1,17„1:.....„l Iu lnnrna.�' �♦n
nal, ;
lr i 11 Indo
nen —.v..,.
`w nliw ulln.m II III tI11111n1, �: \
.7 MI lin=_- ;7;E;2,,11 rpm,s a,y ` •`:
moi_-' _--- g au1 an. [.�`': Jam G
n:...=,117.„,,,,,0, :,...iii i WunPj %��'.. , ate
�r_nl�,.'�r o'a s� _!:."%`: flTr-7a7F.:F7:o
'Illltll�� F � orrry�� ��,tnN`P�i V
� Pi -ii ftg; Paan,Ilsi i -n„o`
. � ;$,111,` .�. � Ultll►u :,.,.
....1.:;1" lel f:",••:4 ♦,4i as 1 s �.
V0'0.4VwV., 1.
J„`I i�nY.G� /piiA�•,�a 11111`���� I ,��.,� _��`.
at Un nyi��:70:9„ I 'alas +rtt�ri_ .crinin•••�A \'
n1 ano , � o o ,gyp �� Pv mrlC .�:♦4 ons • n111H45
Project Description
Install native landscape material and boulders within the freeway off ramp areas at Tierra Rejada Road and
Highway 23/118. Install a City welcome sign with lighting at the northbound freeway off ramp at Tierra
Rejada Road and install native landscaping. Install river cobble within the two triangular traffic delineators at
the northbound and southbound Highway 23/118 off ramps at Tierra Rejada Road. Renovate the landscaping
at the LA Avenue northbound on ramp and off ramp. Objective V.C.5
Project Funding Schedule Total Cost: $3,450,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 150,000
Land Acquisition — — _.................. ...._..._.
Construction/Improvements 3,300,000
Construction Management
Total 0 0 3,450,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 3,450,000
Total 0 0 3,450,000 0 0 0 0 0
DRAFT NOV 2017 B_47 9 5
City of Moorpark
Capital Improvement Program
LOCATION: Peach Hill Wash Channel (Zone 10) Code No. 717
PROJECT: Peach Hill Wash Slope Improvement Account No.
Location Map
TK
PROJECT AREA
rAo
\\
oo -
4
4,
1Country
1 Trail
Park - - _ .
Project Description
Improve slopes adjacent to Peach Hill Wash Channel.
Project Funding Schedule Total Cost: $650,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
_._. Design/Engineering_ — — —
Land Acquisition_
Construction/Improvements 650,000
Construction Management
Total 0 0 650,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
2310: 84-2 Mtn Meadows 650,000
Total 0 0 650,000 0 0 0 0 0
DRAFT NOV 2017 B-48 9 6
Open Space
9
DRAFT NOV 2017 B-49
Parks
DRAFT NOV 2017 B-50 9 8
City of Moorpark
Capital Improvement Program
Arroyo Vista Community Park
4550 Tierra Rejada Road
Location Map
- -—L -..! F.— _. _. _ - -' -
i
,,,-: \.., \ A,�l \A�\ ,��\V' VA
`fD \ \ \ \\`, •1 \•\\\\,\.„
-mac -. . L--'-
7-;-t.,, 0,<,,,eti lir'"` ^_:5/.? 1-±1
' Moorpark j .,,.....5Mj Td%-u1%.I 1 h, �/i,,,,.l j J i� ''�'t•{,--1
School High i ,\I-A.:• "„,--,qy. ♦' �* \�• .. '.` 1}, 0 K• EN-`i__,,
- \ + I �\ s•
,,4 ,,,r,,,,)T---,.., 7- 17..._______Eiasi, ,-,-,=-,.._-',--4 '', qk' 4,(,„\-----,-1--iii 1 7 's
Arroyo Vista Community Park Project Summary:
Project Total Cost
Ball Field Lighting $2,500,000
Water Spray Attraction $ 665,000
Pedestrian Bridge Lighting $ 170,000
Walkway/Bike Path from Mountain Trail Street $ 573,000
Softball Fencing Improvements ... $ 20,000
Slope Landscaping ..$ 55,000
Storage Improvements $ 80,000
Lease SCE Property .. $2,500,000
New Pedestrian Bridge .. $ 375,000
Sand Volleyball Court $ 60,000
Total Arroyo Vista Community Park Project Costs: $6,998,000
DRAFT NOV 2017 B-51 9 9
City of Moorpark
Capital Improvement Program
PROJECT: Ball Field Lighting Code No. 901
LOCATION: Arroyo Vista Community Park Account No.
Project Description
Upgrade and add additional lighting at ball fields. Objective IV.B.7
Project Funding Schedule Total Cost: $2,500,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 2,500,000
Construction Management
Total 0 0 2,500,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 2,500,000
Total 0 0 2,500,000 0 0 0 0 0
PROJECT: Water Spray Attraction Code No. 902
LOCATION: Arroyo Vista Community Park Account No.
Project Description
Design and install a water spray attraction at AVCP. Objective V..A.12
Project Funding Schedule Total Cost: $665,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY Y 22/23 FY 23/24
Design/Engineering 65,000
Land Acquisition
Construction/Improvements -_— 600,000_—_
Construction Management
Total 0 0 665,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 ' FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 665,000
Total 0 0 665,000 0 0 0 0 0
DRAFT NOV 2017 B-52 10 0
City of Moorpark
Capital Improvement Program
PROJECT: Pedestrian Bridge Lighting Code No. 903
LOCATION: Arroyo Vista Community Park Account No.
Project Description
Install walkway lighting on pedestrian bridge at south terminus of Leta Yancy Road.
Project Funding Schedule Total Cost: $170,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY Y 21/22 FY 22/23 FY 23/24
Design/Engineering 45,000
Land Acquisition
Construction/Improvements _..__....._..--...._._.._.........._...._......._. ..._..........._....-125,000 – —..........._.
Construction Management
Total 0 0 170,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 170,000
Total 0 0 170,000 0 0 0 0 0
PROJECT: Walkway/Bike Path from Mountain Trail Street Code No. 904
LOCATION: Arroyo Vista Community Park Account No.
Project Description
Work with Moorpark Unified School District to construct a ramp/walkway and bike path from Mountain
Trail Street,through a portion of Moorpark High School, to AVCP. Objective V.A.18
Project Funding Schedule Total Cost: $573,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 40,000
Land Acquisition
Construction/Improvements 525,000
Construction Management 8,000
Total 0 573,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 573,000
Total 0 573,000 0 0 0 0 0 0
DRAFT NOV 2017 B-53 101
City of Moorpark
Capital Improvement Program
PROJECT: Softball Fencing Improvements Code No. 905
LOCATION: Arroyo Vista Community Park Account No.
Project Description
Add permanent or removable outfield fencing at the AVCP softball fields as deemed appropriate.
Project Funding Schedule Total Cost: $20,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
——....__Design/Engineering ........_.._....._....._...._....... — ——
— Land Acquisition
Construction/Improvements 20,000
Construction Management
Total 0 0 20,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 20,000
Total 0 0 20,000 0 0 0 0 0
PROJECT: Slope Landscaping Code No. 906
LOCATION: Arroyo Vista Community Park Account No.
Project Description
Prepare and implement a landscaping plan to improve the landscaping on the slopes adjacent to Arroyo
Vista Community Park and Moorpark High School.
Project Funding Schedule Total Cost: $55,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 55,000 _
Construction Management — —
Total 0 55,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 55,000
Total 0 55,000 0 0 0 0 0 0
DRAFT NOV 2017 B-54 10 2
City of Moorpark
Capital Improvement Program
PROJECT: Storage Improvements Code No. 907
LOCATION: Arroyo Vista Community Park Account No. C0047
Project Description
Determine storage needs for Arroyo Vista Community Park and expand or add storage areas as needed.
Project Funding Schedule Total Cost: $80,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/_22 FY 22/23 FY 23/24
Design/Engineering 20,000
Land Acquisition ..._.. ......_.....__._.....................
Construction/Improvements 60,000
Construction Management
Total 0 80,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
2010: Community Wide Dev 80,000
Total 0 80,000 0 0 0 0 0 0
PROJECT: Lease SCE Property Code No. 908
LOCATION: Arroyo Vista Community Park Account No.
Project Description
Lease adjacent SCE property and improve area for recreational purposes and expand parking. Objective
IV.A.22
Project Funding Schedule Total Cost: $2,500,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 65,000
Land Acquisition
Construction/Improvements 2,435,000
Construction Management
Total 0 0 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 2,500,000
Total 0 0 2,500,000 0 0 0 0 0
DRAFT NOV 2017 B-55 10 3
City of Moorpark
Capital Improvement Program
PROJECT: New Pedestrian Bridge Code No. 909
LOCATION: Arroyo Vista Community Park Account No.
Project Description
Evaluate feasibility of constructing a new pedestrian bridge to AVCP from southern terminus of Leta
Yancy Road to allow vehicular traffic to exit AVCP from the current pedestrian bridge during special
events. Objective IV.B.10
Project Funding Schedule Total Cost: $375,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 75,000
Land Acquisition _._...._
Construction/Improvements —_......._..___._...__.._.._....__.___._..—_300,000
Construction Management
Total 0 0 375,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/2.4
Undetermined 375,000
Total 0 0 375,000 0 0 0 0 0
PROJECT: Sand Volleyball Court Code No. 910
LOCATION: Arroyo Vista Community Park Account No.
Project Description
Install a sand volleyball court.
Project Funding Schedule Total Cost: $60,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 60,000
Construction Management
Total 0 0 60,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 60,000
Total 0 0 60,000 0 0 0 0 0
DRAFT NOV 2017 B-56 10 4
City of Moorpark
Capital Improvement Program
Campus Canyon Park
6970 Campus Canyon Drive
Location Map
12.1
1 L
�w Campus
—t ponroe Ave � nyon al
-' N, PROJECT AREA
'U1
Campus Canyon Park Project Summary:
Project Total Cost
Basketball Court Improvements $ 12,000
Replace Playground Equipment $175,000
Parking Lot $206,000
Total Campus Canyon Park Project Costs: $393,000
10 5
DRAFT NOV 2017 B-57
City of Moorpark
Capital Improvement Program
PROJECT: Basketball Court Improvements Code No. 911
LOCATION: Campus Canyon Park Account No.
Project Description
Renovate the basketball court at Campus Canyon Park.
Project Funding Schedule Total Cost: $12,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
-..._Design/Engineering - -.._.. — -........__._.
Land Acquisition
Construction/Improvements 12,000
Construction Management
Total 0 12,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 12,000
Total 0 12,000 0 0 0 0 0 0
PROJECT: Replace Playground Equipment Code No. 912
LOCATION: Campus Canyon Park Account No.
Project Description
Replace children's play structures and equipment and replace sand with wood fiber. Install sand play area.
Project Funding Schedule Total Cost: $175,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 175,000
Construction Management
Total 0 0 175,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 175,000
Total 0 0 175,000 0 0 0 0 0
DRAFT NOV 2017 B-58 10 6
City of Moorpark
Capital Improvement Program
PROJECT: Parking Lot Code No. 913
LOCATION: Campus Canyon Park Account No.
Project Description
Add parking lot at Campus Canyon Park.
Project Funding Schedule Total Cost: $206,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 25,000
Land Acquisition
Construction/Improvements 175,000
Construction Management 6,000
Total 0 0 0 206,000 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 206,000
Total 0 0 0 206,000 0 0 0 0
DRAFT NOV 2017 B-59 10 7
City of Moorpark
Capital Improvement Program
Campus Park
6400 Harvard Street
Location Map
- Campus Park Dr l
1 I w
—_ ._1.._ I— Stanford St L1 I( ---
-
—- — r 1 — 1 _'Ll I
I , -
.I r
N 1
�-o W t t_ L� 1 = -.
- N •
- - . _ c2 t PROJECT AREA
1 , z, -
- -I —� —i 1-- Diu p
{ --- --,
r-- sm I u
1 -1- I -i—
41
Hartford St ' �� j� r,__i
A
I
Ronald Re:an F ED
Campus Park Project Summary:
Project Total Cost
Restroom Improvements .. $203,000
Pavillion Improvements $ 10,000
Replace Playground Equipment $175,000
Total Campus Park Project Costs: $388,000
108
DRAFT NOV 2017 B-60
City of Moorpark
Capital Improvement Program
PROJECT: Restroom Improvements Code No. 914
LOCATION: Campus Park Account No.
Project Description
Remove and replace restroom building with prefabricated restroom building or renovate current restroom
building at Campus Park to comply with ADA requirements and correct maintenance issues.
Project Funding Schedule Total Cost: $203,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
- -....._ Design/Engineering ....__....—— 25,000._....._....
Land Acquisition
Construction/Improvements 170,000
Construction Management 8,000
Total 0 203,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 203,000
Total 0 203,000 0 0 0 0 0 0
PROJECT: Pavilion Improvements Code No. 915
LOCATION: Campus Park Account No.
Project Description
Replace concrete flatwork in the Campus Park picnic pavilion.
Project Funding Schedule Total Cost: $10,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 10,000
Construction Management
Total 0 10,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 10,000
Total 0 10,000 0 0 0 0 0 0
10 9
DRAFT NOV 2017 B-61
City of Moorpark
Capital Improvement Program
PROJECT: Replace Playground Equipment Code No. 916
LOCATION: Campus Park Account No.
Project Description
Replace children's play structures and equipment, including swing set, and replace sand with wood fiber.
Install separate sand play area.
Project Funding Schedule Total Cost: $175,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering .................._..__._._......_._.........
Land Acquisition
Construction/Improvements 175,000
Construction Management
Total 0 0 175,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 175,000
Total 0 0 175,000 0 0 0 0 0
110
DRAFT NOV 2017 B-62
City of Moorpark
Capital Improvement Program
College View Park
15400 Campus Park Drive
Location Map
'
Elan L ,1
�l /Campus—Park Di
z 11
�`
PROJECT AREA
�MERonaldtRaagan7F.wy�i
College View Park Project Summary:
Project Total Cost
Sand Volleyball Courts .$ 45,000
Basketball Court Improvements $ 87,000
Dog Park Lighting $ 83,000
Park Improvements .... $ 27,000
New Park Sign $ 35,000
Total College View Park Project Costs: $277,000
DRAFT NOV 2017 B-63 111
City of Moorpark
Capital Improvement Program
PROJECT: Sand Volleyball Court Code No. 917
LOCATION: College View Park Account No.
Project Description
Install a sand volleyball court at College View Park.
Project Funding Schedule Total Cost: $45,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
— —Design/Engineering._.__..—...........__..._....._..............................................
Land Acquisition
Construction/Improvements 45,000
Construction Management
Total 0 45,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 45,000
Total 0 45,000 0 0 0 0 0 0
PROJECT: Basketball Court Improvements Code No. 918
LOCATION: College View Park Account No.
Project Description
Install a second basketball court with lighting at College View Park.
Project Funding Schedule Total Cost: $87,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
— — Design/Engineering _...._._—.._...........__........._-- ._-. _. 12,000
Land Acquisition
Construction/Improvements 75,000
Construction Management
Total 0 0 0 87,000 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 87,000
Total 0 0 0 87,000 0 0 0 0
112
DRAFT NOV 2017 B-64
City of Moorpark
Capital Improvement Program
PROJECT: Dog Park Lighting Code No. 919
LOCATION: College View Park Account No.
Project Description
Install lighting at the dog park.
Project Funding Schedule Total Cost: $83,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY23/24
Design/Engineering 8,000
Land Acquisition
Construction/Improvements 75,000
Construction Management
Total 0 0 83,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 83,000
Total 0 0 83,000 0 0 0 0 0
PROJECT: Park Improvements Code No. 920
LOCATION: College View Park Account No.
Project Description
Install fencing along Campus Park Drive and Collins Drive, including corner. Install a park sign on
Collins Drive frontage.
Project Funding Schedule Total Cost: $27,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements ___._.__......._..---....._.._.__._.27,000 ---- — —
Construction Management
Total 0 0 27,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18- FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined , 27,000
Total 0 0 0 27,000 0 0 0 0
DRAFT NOV 2017 B-65 113
City of Moorpark
Capital Improvement Program
PROJECT: New Park Sign Code No. 921
LOCATION: College View Park Account No.
Project Description
Remove marquee base and install new park sign.
Project Funding Schedule Total Cost: $35,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
—
Land Acquisition
Construction/Improvements 35,000
Construction Management
Total 0 0 35,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 35,000
Total 0 0 35,000 0 0 0 0 0
114
DRAFT NOV 2017 B-66
City of Moorpark
Capital Improvement Program
LOCATION: Community Center Park (799 Moorpark Avenue) Code No. 922
PROJECT: Replace Playground Equipment Account No.
Location Map
1
H
Everett
1 t i
PROJE .1',EA, i I —
' I ' I i ' '' H
g iHH , i11H ,
. , i ,
" ,
,..„..., „ ._, I , , .
Charles St
1 1
if I
i it
1
2
i
i] ! 4)1 1
i
1
I
I
c • I 1 .., i
, v) .
12
• a 1
1 1 1 1 i 1 1
I
E High St
‘1 1
Project Description
Replace children's play structures and equipment, and replace sand with wood fiber.
Project Funding Schedule Total Cost: $125,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering .
Land Acquisition _
Construction/Improvements 125,000
Construction Management
Total 0 0 125,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 125,000
Total 0 0 125,000 0 0 0 0 0
115
DRAFT NOV 2017 B-67
City of Moorpark
Capital Improvement Program
Country Trail Park
11701 1/2 Mountain Trail Street
Location Map
• o
o �� L PROJECT AREA P,sre
_ \
ilii v �.
Sfie" r TDr �� \�
L ,,� j r - •'t
i� _4 I 4
-�� i { •
Country Trail Park Project Summary:
Project Total Cost
Playground Improvements and ADA Access.... $422,000
Restroom Addition $285,000
Landscaping Improvements $ 25,000
Parkour Training Circuit $175,000
Install Trail $ 45,000
Total Country Trail Park Project Costs: $952,000
DRAFT NOV 2017 B-68 116
City of Moorpark
Capital Improvement Program
PROJECT: Playground Improvements and ADA Access Code No. 923
LOCATION: Country Trail Park Account No.
Project Description
Remove and replace playground equipment and sand at Country Trail Park with a reduced size playground
and sand play area. Install an ADA compliant ramp and walkway from the parking lot to the playground.
Project Funding Schedule Total Cost: $422,000
Prior Yrs FY Y 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY Y 23/24
Design/Engineering 35,000
_.—Land Acquisition__...__......_...__.....__._.............._.
Construction/Im rovements 375,000
Construction Management 12,000
Total 0 0 422,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 422,000
Total 0 0 422,000 0 0 0 0 0
PROJECT: Restroom Addition Code No. 924
LOCATION: Country Trail Park Account No.
Project Description
Install a prefabricated restroom facility at Country Trail Park.
Project Funding Schedule Total Cost: $285,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 45,000
Land Acquisition
Construction/Improvements 210,000
Construction Management 30,000
Total 0 0 0 285,000 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 285,000
Total 0 0 0 285,000 0 0 0 0
DRAFT NOV 2017 B-69 117
City of Moorpark
Capital Improvement Program
PROJECT: Landscaping Improvements Code No. 925
LOCATION: Country Trail Park Account No.
Project Description
Improve natural area at Country Trail Park. Improve landscaping along the slope.
Project Funding Schedule Total Cost: $25,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering— —._—.._—.__...._...__..... -- ........_._._._.
Land Acquisition
Construction/Improvements 25,000
Construction Management
Total 0 25,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 25,000
Total 0 25,000 0 0 0 0 0 0
PROJECT: Parkour Training Circuit Code No. 926
LOCATION: Country Trail Park Account No.
Project Description
Install fitness circuit specific to Parkour training.
Project Funding Schedule Total Cost: $175,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 175,000
Construction Management
Total 0 0 175,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 175,000
Total 0 0 175,000 0 0 0 0 0
DRAFT NOV 2017 B-70 118
City of Moorpark
Capital Improvement Program
PROJECT: Install Trail Code No. 927
LOCATION: Country Trail Park Account No.
Project Description
Install decomposed granite trail.
Project Funding Schedule Total Cost: $45,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
—_ — Land Acquisition -- --
Construction/Improvements 45,000
Construction Management
Total 0 45,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 45,000
Total 0 45,000 , 0 0 0 0 0 0
DRAFT NOV 2017 B-71 119
City of Moorpark
Capital Improvement Program
Glenwood Park
11800 Harvester Street
Location Map
Los Angeles Ave
'----s)--,—..I Lei` 1 ' ‘..,..\ 1111 --
1 _
-- C...- ..�-
_ •� . _ —11 *-' oI
IBM I
LIT Milmum ;4 111111 I
-° a.- PROJECT AREA ,;
: r;- rr,
' arveste A . 'I ~1 r1
-.---,--1—p—i-A., \\F\i's'*,:x.4`.\\4,3\i-1
r
„.,--,,.--t ......----;---
Glenwood Park Project Summary:
Project Total Cost
Basketball Court Lighting $ 71,000
Sand Volleyball Court $ 45,000
Install Trail .. $ 12,000
Replace Playground Equpment $250,000
New Park Sign $ 35,000
Total Glenwood Park Project Costs: $413,000
DRAFT NOV 2017 B-72 12 0
City of Moorpark
Capital Improvement Program
PROJECT: Basketball Court Lighting Code No. 928
LOCATION: Glenwood Park Account No.
Project Description
Install coin operated lights at the Glenwood Park basketball court.
Project Funding Schedule Total Cost: $71,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
-- - Design/Engeering.._......._......._..__..._....._.._... 6,000.............._._._. _._.—.
Land Acquisition
Construction/Improvements —._.._......................_.__............_..._____.....___...__._65,000
Construction Management
Total 0 0 71,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 71,000
Total 0 0 71,000 0 0 0 0 0
PROJECT: Sand Volleyball Court Code No. 929
LOCATION: Glenwood Park Account No.
Project Description
Install a sand volleyball court at Glenwood Park.
Project Funding Schedule Total Cost: $45,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering _
Land Acquisition
Construction/Improvements 45,000
Construction Management
Total i 0 0 45,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 45,000
Total 0 0 45,000 0 0 0 0 0
DRAFT NOV 2017 B_73 121
City of Moorpark
Capital Improvement Program
PROJECT: Install Trail Code No. 930
LOCATION: Glenwood Park Account No.
Project Description
Install a trail from Tierra Rejada Road to playground.
Project Funding Schedule Total Cost: $12,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 12,000
Construction Management
Total 0 12,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 12,000
Total 0 12,000 0 0 0 0 0 0
PROJECT: Replace Playground Equipment Code No. 931
LOCATION: Glenwood Park Account No.
Project Description
Replace children's play structures and equipment, and replace sand with wood fiber. Install sand play
area.
Project Funding Schedule Total Cost: $250,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 250,000
Construction Management
Total 0 0 250,000 0 0 0 0 0
Funding Sources -
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 250,000
Total 0 0 250,000 0 0 0. 0 0
12 2
DRAFT NOV 2017 B-74
City of Moorpark
Capital Improvement Program
PROJECT: New Park Sign Code No. 932
LOCATION: Glenwood Park Account No.
Project Description
Remove marquee base and install new park sign.
Project Funding Schedule Total Cost: $35,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
---..._.._Land Acquisition........._....._..__.._.........
Construction/Improvements 35,000
Construction Management
Total 0 0 35,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 35,000
Total 0 0 35,000 0 0 0 0 0
DRAFT NOV 2017 B-75 12 3
City of Moorpark
Capital Improvement Program
LOCATION: Magnolia Park(296 Charles Street) Code No. 933
PROJECT: Replace Playground Equipment Account No.
Location Map
Everett St
PROJECT AREA
z
Charles St
ksMagnolia
Park-1
I
N
0 I p .
E High St
' I
I
Project Description
Replace children's play structures and equipment, and replace sand with wood fiber.
Project Funding Schedule Total.Cost: $175,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering_
Land Acquisition
Construction/Improvements _ -- 175,000
Construction Management -------- ------------� - - - --Total 0 0 0 0 0 0 175,000 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined --- 175,000
Total 0 0 0 0 0 0 175,000 0
DRAFT NOV 2017 B-76 124
City of Moorpark
Capital Improvement Program
Mammoth Highlands Park
7000 Elk Run Loop
Location Map
5‘,0
te �4h
��dG� % Mammoth
Highlands
Park
ki I PROJECT AREA '
b 1 �,r1
un 1 °P =-i d
- Elk R = _ � ,
Mammoth Highlands Park Project Summary:
Project Total Cost
Sand Volleyball Court $ 45,000
Basketball Court Light Improvements $ 39,500
Expand Trail '$ 25,000
Total Mammoth Highlands Park Project Costs: $109,500
DRAFT NOV 2017 B-77 12 5
City of Moorpark
Capital Improvement Program
PROJECT: Sand Volleyball Court Code No. 934
LOCATION: Mammoth Highlands Park Account No.
Project Description
Install a sand volleyball court at Mammoth Highlands Park.
Project Funding Schedule Total Cost: $45,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY Y 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 45,000 -- — — _
Construction Management
Total 0 45,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 45,000
Total 0 45,000 0 0 0 0 0 0
PROJECT: Basketball Court Light Improvements Code No. 935
LOCATION: Mammoth Highlands Park Account No.
Project Description
Reposition or add lights as needed at the Mammoth Highlands basketball court.
Project Funding Schedule Total Cost: $39,500
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 4,500
Land Acquisition
Construction/Improvements 35,000
Construction Management
Total 0 0 39,500 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 39,500
Total 0 0 39,500 0 0 0 0 0
DRAFT NOV 2017 B-78 12 6
City of Moorpark
Capital Improvement Program
PROJECT: Expand Trail Code No. 936
LOCATION: Mammoth Highlands Park Account No.
Project Description
Expand trail around perimeter of Mammoth Highlands Park.
Project Funding Schedule Total Cost: $25,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 25,000
Construction Management
Total 0 25,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 25,000
Total 0 25,000 0 0 0 0 0 0
12 7
DRAFT NOV 2017 B-79
City of Moorpark
Capital Improvement Program
Miller Park
4530 Miller Parkway
Location Map
stae
05 Tr/
Miller.
Park•
PROJECT AREA
O4ve$t
1J
oo
44.
o
Miller Park Project Summary:
Project Total Cost
Lighting Addition $ 25,000
Loop Trail Addition $ 45,000
Replace Playground Equipment $250,000
Total Miller Park Project Costs: $320,000
DRAFT NOV 2017 B-80 12 8
City of Moorpark
Capital Improvement Program
PROJECT: Lighting Addition Code No. 937
LOCATION: Miller Park Account No.
Project Description
Install security lights behind the tennis courts at Miller Park.
Project Funding Schedule Total Cost: $25,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 25,000
Construction Management
Total 0 25,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 25,000
Total 0 25,000 0 0 0 0 0 0
PROJECT: Loop Trail Addition Code No. 938
LOCATION: Miller Park Account No.
Project Description
Install loop trail at Miller Park with a connection to the adjacent nature trails.
Project Funding Schedule Total Cost: $45,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering__.-_.__.---.--........__. --.--.......___...._._
-- Land Acquisition
Construction/Improvements 45,000
Construction Management
Total 0 45,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 45,000
Total 0 45,000 0 0 0 0 0 0
DRAFT NOV 2017 B-81 12 9
City of Moorpark
Capital Improvement Program
PROJECT: Replace Playground Equipment Code No. 939
LOCATION: Miller Park Account No.
Project Description
Replace children's play structures and equipment, and replace sand and poured-in-place surfacing with
wood fiber.
Project Funding Schedule Total Cost: $250,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering _.. — ......__.._.__........
Land Acquisition
Construction/Improvements 250,000
Construction Management
Total 0 0 0 250,000 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 250,000
Total 0 0 0 250,000 0 0 0 0
DRAFT NOV 2017 B-82 130
City of Moorpark
Capital Improvement Program
Monte Vista Nature Park
4201 Spring Road
Location Map
Gurnmoke Rd PROJECT AREA
--- - Monte Vista.
Nature Park
oo�� 4
Ao ett
Monte Vista Nature Park Project Summary:
Project Total Cost
Lighting Improvements $ 25,000
Shade Structure $ 30,000
Landscape Improvements $300,000
Trail System Improvements $150,000
Total Monte Vista Nature Park Project Costs: $505,000
131
DRAFT NOV 2017 B_83
City of Moorpark
Capital Improvement Program .
PROJECT: Lighting Improvements Code No. 940
LOCATION: Monte Vista Nature Park Account No.
Project Description
Install additional lighting at Monte Vista Nature Park.
Project Funding Schedule Total Cost: $25,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 25,000
Construction Management
Total 0 25,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 25,000
Total 0 25,000 0 0 0 0 0 0
•
PROJECT: Shade Structure Code No. 941
LOCATION: Monte Vista Nature Park Account No.
Project Description
Identify an appropriate location and install a shade structure at Monte Vista Nature Park.
Project Funding Schedule Total Cost: $30,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Accinisition
Construction/Improvements 30,000
Construction Management
Total 0 30,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 30,000
--
Total 0 30,000 0 0 0 0 0 0
13 2
DRAFT NOV 2017 B-84
City of Moorpark
Capital Improvement Program
PROJECT: Landscape Improvements Code No. 942
LOCATION: Monte Vista Nature Park Account No.
Project Description
Develop an overall site plan for Monte Vista Nature Park, to include removal of all non-native plant
species. Removed plants will be replaced with native landscaping, demonstration gardens, interpretive
signage, walkways, and seating areas.
Project Funding Schedule Total Cost: $300,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 50,000
Land Acquisition
Construction/Imjrovements 250,000
Construction Management
Total 0 0 0 300,000 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 300,000
Total 0 0 0 300,000 0 0 0 0
PROJECT: Trail System Improvements Code No. 943
LOCATION: Monte Vista Nature Park Account No.
Project Description
Improve trail system including drainage and installation of slough walls.
Project Funding Schedule Total Cost: $150,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Desi/Engineering 25,000
Land Acquisition
Construction/Improvements —_— 125,000
Construction Management
Total 0 0 150,000 0 0 0 0 0
Funding Sources .
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 150,000
Total 0 0 150,000 0 0 0 0 0
DRAFT NOV 2017 B-85 13 3
City of Moorpark
Capital Improvement Program
Mountain Meadows Park
4350 Mountain Meadow Drive
Location Map
i _ PROJECT AREA
a• foou�ta�o
- _ - 1 o `Meadows i
C e Park
is -.Z._ r
---i i --4;' Tt
T.
P'
Y 1
— l ,, t-_-*�r, ,po r-----1 ._-_,.=
v;� Jit r 1 --, - 4 i -1_ 1 �, '
�._Ti ref-i \ 1 .1 . 1 f
Mountain Meadows Park Project Summary:
Project Total Cost
Handball Wall $ 41,924
Loop Trail $ 35,000
Replace Playground Equipment $225,000
Total Mountain Meadows Park Project Costs: $301,924
13 4
DRAFT NOV 2017 B_86
City of Moorpark
Capital Improvement Program
PROJECT: Handball Wall Code No. 944
LOCATION: Mountain Meadows Park Account No. C0045
Project Description
Install a handball wall at Mountain Meadows park. Objective IV.A.25
Project Funding Schedule Total Cost: $41,924
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 7,324 9,600
_...__ Land Acquisition_........_........_._. _._____._._.
Construction/Improvements._....__._._. 25,000 — ._............— .._..... — —
Construction Management
Total 7,324 34,600 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY Y 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
2013:Park Devt Zone 3 7,324
2010: Community Wide Dev 34,600
Total 7,324 34,600 0 0 0 0 0 0
PROJECT: Loop Trail Code No. 945
LOCATION: Mountain Meadows Park Account No.
Project Description
Install a loop trail around the perimeter of Mountain Meadows park.
Project Funding Schedule Total Cost: $35,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 35,000
Construction Management
Total 0 0 35,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 35,000
Total 0 0 35,000 0 0 0 0 0
DRAFT NOV 2017 B_87 135
City of Moorpark
Capital Improvement Program
PROJECT: Replace Playground Equipment Code No. 946
LOCATION: Mountain Meadows Park Account No.
Project Description
Replace children's play structures and equipment, and replace sand and paved-in-place surfacing with
wood fiber.
Project Funding Schedule Total Cost: $225,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering..........._.._..._.................................._......__...._..._.... - — - -
Land Acquisition_ _..._._._......._..._..........................._. _.
Construction/Improvements 225,000
Construction Management
Total 0 0 225,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 225,000
Total 0 0 225,000 0 0 0 0 0
•
DRAFT NOV 2017 B-88 13 6
City of Moorpark
Capital Improvement Program
Peach Hill Park
13200 Peach Hill Road
Location Map
11 i I
PROJECT AREA
CI I Peach Hill'. I I I -I
I—f,,'E oondna.SE ,Park .
T 1I
i
WI[iams Randa Rd
_i1
1 I 1 i
TM!I A 1 I ' rl_ _ 1 Y
FTTP Re1ada d �
_ r1, aJ { 1 � L
terra �
1 . , I , I!!1 I! t_t!_ - I L ;
Peach Hill Park Project Summary:
Project Total Cost
Lighting Upgrades and Additions $300,000
Picnic Pavilion Improvements $ 75,000
Loop Trail $ 45,000
Sand Play Area $ 20,000
Replace Playground Equipment $135,000
Total Peach Hill Park Project Costs: $575,000
13 7
DRAFT NOV 2017 B-89
City of Moorpark
Capital Improvement Program
PROJECT: Lighting Upgrades and Additions Code No. 947
LOCATION: Peach Hill Park Account No.
Project Description
Replace the softball field lighting and add lighting to the soccer field at Peach Hill Park.
Project Funding Schedule Total Cost: $300,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering...........__.._..........._....._..........._. -.
Land Acquisition
Construction/Improvements 300,000
Construction Management
Total 0 0 0 300,000 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/1.8 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 300,000
Total 0 0 0 300,000 0 0 0 0
PROJECT: Picnic Pavilion Improvements Code No. 948
LOCATION: Peach Hill Park Account No.
Project Description
Renovate the Peach Hill Park picnic pavilion, including enclosing the roof, or remove the pavilion and
replace it with new pavilion with a solid roof, comparable to pavilions at other City parks.
Project Funding Schedule Total Cost: $75,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering -__.._.._._._...._._._....._.........- _-.
---.._.._. Land Acquisition
Construction/Improvements 75,000
Construction Management
Total 0 75,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 75,000
Total 0 75,000 0 0 0 0 0 0
13 8
DRAFT NOV 2017 B-90
City of Moorpark
Capital Improvement Program
PROJECT: Loop Trail Code No. 949
LOCATION: Peach Hill Park Account No.
Project Description
Install a loop trail around the perimeter of Peach Hill Park.
Project Funding Schedule Total Cost: $45,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering —_..---.-.---.._........_._._._._._. __.
.............._._......_Land Acquisition- -._.....—._..........._.
Construction/Imp ovements 45,000
Construction Management
Total 0 0 45,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 45,000
Total 0 0 45,000 0 0 0 0 0
PROJECT: Sand Play Area Code No. 950
LOCATION: Peach Hill Park Account No.
Project Description
Install sand play area
Project Funding Schedule Total Cost: $20,000
Prior Yrs FY 17/18 . FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements — 20,000 _ - —_--- --- —
Construction Management
Total 0 0 20,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 20,000
Total 0 0 20,000 0 0 0 0 0
DRAFT NOV 2017 B-91 139
City of Moorpark
Capital Improvement Program
PROJECT: Replace Playground Equipment Code No. 951
LOCATION: Peach Hill Park Account No.
Project Description
Replace children's play structures and equipment.
Project Funding Schedule Total Cost: $135,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
--- -Design/Engineering ._.... ...._....... -...._.... - ...- ..............- - - - -- - -
Land Acquisition
Construction/Improvements __-_...._._.-._...._.-._._...__._..._____._._......._.___....._..._135,000
Construction Management
Total 0 0 0 135,000 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 135,000
Total 0 0 0 135,000 0 0 0 0
ti
DRAFT NOV 2017 B-92 14 0
City of Moorpark
Capital Improvement Program
Poindexter Park
500 Poindexter Avenue
Location Map
Poindexter -
I r
_ PROJECT AREA
— .7 I �\% I a
1 \•
� -
1
Poindexter Park Project Summary:
Project Total Cost
Security Camera Upgrades $ 35,000
Skate Park Fencing $ 30,000
Park Amenity Improvements $ 30,000
Pathway Improvements $ 65,000
Total Poindexter Park Project Costs: $160,000
DRAFT NOV 2017 B-93 141
City of Moorpark
Capital Improvement Program
PROJECT: Security Camera Upgrades Code No. 952
LOCATION: Poindexter Park Account No.
Project Description
Upgrade security cameras at Poindexter Park, and install additional cameras as needed. Objective V.A.14
Project Funding Schedule Total Cost: $35,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 10,000
Land Acquisition
Construction/jp.imEsnents 25,000 _
Construction Management
Total 0 35,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 35,000
Total 0 35,000 0 0 0 0 0 0
PROJECT: Skate Park Fencing Code No. 953
LOCATION: Poindexter Park Account No.
Project Description
Improve security fencing around the perimeter of the skate park.
Project Funding Schedule Total Cost: $30,000
' Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 30,000
Construction Management
Total 0 30,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 30,000
Total 0 30,000 0 0 0 0 0 0
DRAFT NOV 2017 B-94 14 2
City of Moorpark
Capital Improvement Program
PROJECT: Park Amenity Improvements Code No. 954
LOCATION: Poindexter Park Account No.
Project Description
Replace metal and wood amenities throughout Poindexter Park with concrete, including the picnic tables
in the picnic pavilion.
Project Funding Schedule Total Cost: $30,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Impvements 30,000
Construction Management
Total 0 30,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 2.3/24
Undetermined 30,000
Total 0 30,000 0 0 0 0 0 0
PROJECT: Pathway Improvements Code No. 955
LOCATION: Poindexter Park Account No.
Project Description
Install concrete mow curbs, improve the decomposed granite paths at Poindexter Park, and install outdoor
exercise equipment along the path.
Project Funding Schedule Total Cost: $65,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY Y 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
— —_-- Land Acquisition
Construction/Improvements 65,000
Construction Management
Total 0 65,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 65,000
Total 0 65,000 0 0 0 0 0 0
14 3
DRAFT NOV 2017 B-95
City of Moorpark
Capital Improvement Program
Tierra Rejada Park
11900 Mountain Trail Street
Location Map
*aRP�d�aRn PROJECT AREA
Tierra Rejada
Park '
'� `
Tierra Rejada Park Project Summary:
Project Total Cost
Lighting Additions $ 85,000
Tennis Court Addition .$ 70,000
Parking Lot Expansion $106,000
Replace Playground Equipment $400,000
Total Tierra Rejada Park Project Costs: $661,000
DRAFT NOV 2017 B-96 14 4
City of Moorpark
Capital Improvement Program
PROJECT: Lighting Additions Code No. 956
LOCATION: Tierra Rejada Park Account No.
Project Description
Install coin operated lights at the basketball and tennis courts at Tierra Rejada Park.
Project Funding Schedule Total Cost: $85,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 10,000
Land Acquisition
Construction/Improvements 75,000
Construction Management
Total 0 0 85,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 85,000
Total 0 0 85,000 0 0 0 0 0
PROJECT: Tennis Court Addition Code No. 957
LOCATION: Tierra Rejada Park Account No.
Project Description
Construct additional court at Tierra Rejada Park.
Project Funding Schedule Total Cost: $70,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 10,000
Land Acquisition
Construction/Improvements 60,000
Construction Management
Total 0 0 70,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 70,000
Total 0 0 70,000 0 0 0 0 0
DRAFT NOV 2017 B-97 14 5
•
City of Moorpark
Capital Improvement Program
PROJECT: Parking Lot Expansion Code No. 958
LOCATION: Tierra Rejada Park Account No.
Project Description
Expand parking lot on Mountain Meadow Drive by approximately 14 spaces.
Project Funding Schedule Total Cost: $106,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering ....._...._.._...._......._..__._._...__......_.._._..._._... 25,000 ................._.
Land Acquisition
Construction/Improvements _.._—._._._....___....._._._—...._..._......__._......._._75,000
Construction Management 6000
Total 0 0 106,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 106,000
Total 0 0 106,000 0 0 0 0 0
PROJECT: Replace Playground Equipment Code No. 959
LOCATION: Tierra Rejada Park Account No.
Project Description
Replace children's play structures and equipment, and replace sand with wood fiber. Create sand play
area.
Project Funding Schedule Total Cost: $400,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 400,000
Construction Management
Total 0 0 400,000 0 0 0 0 0
Funding Sources •
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 400,000
Total 0 0 400,000 0 0 0 0 0
14 6
DRAFT NOV 2017 B-98
City of Moorpark
Capital Improvement Program
Villa Campesina Park
4704 Leta Yancy Road
Location Map
Los Angeles Ave
1
T
,1-_ I
r__ PROJECT AREA
Villa Lampe sviaAve 3'
Ir I I
C
ii \ "to
lk:\...
I
1
Villa Campesina Park Project Summary:
Project Total Cost
Security Improvements $ 55,000
Replace Playground Equipment $250,000
Total Villa Campesina Park Project Costs: $305,000
DRAFT NOV 2017 B-99 14 7
City of Moorpark
Capital Improvement Program
PROJECT: Security Improvements Code No. 960
LOCATION: Villa Campesina Park Account No.
Project Description
Install security cameras and add additional security lighting as needed at Villa Campesina Park. Objective
V.A.14
Project Funding Schedule Total Cost: $55,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineexing 10,000
Land Acquisition
Construction/Improvements 45,000
Construction Management
Total 0 55,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 55,000
Total 0 55,000 0 0 0 0 0 0
PROJECT: Replace Playground Equipment Code No. 961
LOCATION: Villa Campesina Park Account No.
Project Description
Replace children's play structures and equipment, and replace sand with wood fiber.
Project Funding Schedule Total Cost: $250,000,
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Erigineering
Land Acquisition
Construction/Improvements 250,000
Construction Management
Total 0 0 250,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 250,000
Total 0 0 250,000 0 0 0 0 0
148
DRAFT NOV 2017 B-I00
City of Moorpark
Capital Improvement Program
Virginia Colony Park
14507 Condor Drive
Location Map
a
PROJECT AREA
rinceton Av
Pe
la
77, �a td `
Virginia Colony Park Project Summary:
Project Total Cost
Basketball Court Addition $ 55,000
Replace Playground Equipment $200,000
Total Villa Campesina Park Project Costs: $255,000
DRAFT NOV 2017 B-101 149
City of Moorpark
Capital Improvement Program
PROJECT: Basketball Court Addition Code No. 962
LOCATION: Virginia Colony Park Account No.
Project Description
Install a full or half-court basketball court at Virginia Colony Park.
Project Funding Schedule Total Cost: $55,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 55,000
Construction Management
Total 0 0 55,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY Y 20/21 FY 21/22 FY 22/23 FY 2. 3/24
Undetermined 55,000
Total 0 0 55,000 0 0 0 I 0 0
PROJECT: Replace Playground Equipment Code No. 963
LOCATION: Virginia Colony Park Account No.
Project Description
Replace children's play structures and equipment, and replace sand with wood fiber. Add sand play area.
Project Funding Schedule Total Cost: $200,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 2. 0/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 200,000
Construction Management
Total 0 0 0 0 0 200,000 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 200,000
Total 0 0 0 0 0 200,000 0 0
15 0
DRAFT NOV 2017 B-102
City of Moorpark
Capital Improvement Program
LOCATION: Walnut Acres Park (161 Second Street) Code No. 964
PROJECT: Security Cameras Account No.
Location Map
PROJECT AREA
Poindexter Ave
1st St
y
W Acres. W I
m
o_ Park; --
2nd St
J
Project Description
Install security cameras as needed at Walnut Acres Park. Objective V..A.14
Project Funding Schedule Total Cost: $10,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 10,000
Construction Management
Total 0 10,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 10,000
Total 0 10,000 0 0 0 0 0 0
DRAFT NOV 2017 B-103 151
City of Moorpark
Capital Improvement Program
Citywide Parks
Various Locations / Locations To Be Determined
Citywide Parks Project Summary:
Project Total Cost
Central Irrigation System $ 481,923
Lighting Upgrades $ 555,000
ADA Improvements $ 60,000
Universally Accessible Playground $ 350,000
BMX/Bicycle Facility $ 850,000
Sensory Garden $ 295,000
Disc Golf Course $ 150,000
Electronic Marquees $ 275,000
Permanent Game Equipment . $ 30,000
Baseball Field $ 260,000
Bocce Ball Court $ 10,000
Ball Wall $ 35,000
Update Park Features $ 175,000
Additional Exercise Equipment $ 150,000
Community Pool $3,000,000
Total Citywide Parks Project Costs: $6,676,923
DRAFT NOV 2017 B-104 15 2
City of Moorpark
Capital Improvement Program
PROJECT: Central Irrigation System Code No. 965
LOCATION: Citywide Parks Account No. C0019
Project Description
Replace existing irrigation controllers with WeatherTRAK ET Pro2 controllers at various City parks and
Landscape Maintenance Districts. Project largely complete, with only work at AVCP and Miller Park
remaining. The central control system at AVCP will include an inline fertilization system to manage
fertilization of sports turf.
Project Funding Schedule Total Cost: $481,923
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 293,519 188,404
Construction Management
Total 293,519 188,404 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
1000: General Fund 71,599 188,404
2302:District 84-2 Zone 2 33,111
2312:District 82-2 Zone 12 34,466
2315:District 84-2 Zone 15 61,937
2322:District 84-2 Zone 22 92,406
Total 293,519 188,404 0 0 0 0 0 0
PROJECT: Lighting Upgrades Code No. 966
LOCATION: Citywide Parks Account No.
Project Description
Replace site lighting with LED lighting or other energy efficient alternatives at Campus Canyon, College
View, Mammoth Highlands, Miller, Mountain Meadows, Peach Hill, Tierra Rejada, and Villa Campesina
Parks.
Project Funding Schedule Total Cost: $555,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 55,000
Land Acquisition —
— ----
—
Construction/Improvements 500,000
Construction Management
Total 0 555,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 555,000
Total 0 555,000 0 0 0 0 0 0
DRAFT NOV 2017 B-105 153
City of Moorpark
Capital Improvement Program
PROJECT: ADA Improvements Code No. 967
LOCATION: Citywide Parks Account No.
Project Description
Install ADA compliant walkways connecting public sidewalks to park walkways and amenities at Peach
Hill, Monte Vista, Mountain Meadows, and Tierra Rejada Parks. Install upgrades at Villa Campesina
Park, including parking and signage.
Project Funding Schedule Total Cost: $60,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
_——Design/Engineering —— —
Land Acquisition — --..—......-.........._._. _.
Construction/Improvements 60,000 _......_...__ _.—_...._._._..___..___..__...._......_.._....—...._.._._.....—._..._.
Construction Management
Total 0 60,000 ' 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 60,000
Total 0 60,000 0 0 0 0 0 0
PROJECT: Universally Accessible Playground Code No. 968
LOCATION: Citywide Parks Account No.
Project Description
Design and install universally accessible playground equipment at one City park. Objective IV.A.16
Project Funding Schedule Total Cost: $350,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 350,000
Construction Management
Total 0 0 350,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 350,000
Total 0 0 350,000 0 0 0 0 0
15 4,
DRAFT NOV 2017 B-106
City of Moorpark
Capital Improvement Program
PROJECT: BMX/ Bicycle Facility Code No. 969
LOCATION: Citywide Parks Account No.
Project Description
Select a site and design and construct a facility to accommodate either bicycle free-style or BMX riding.
Objective IV..B.8
Project Funding Schedule Total Cost: $850,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 100,000
Land Acquisition _
Construction/Im rovements 750,000
Construction Management
Total 0 0 0 850,000 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 850,000
Total 0 0 0 850,000 0 0 0 0
PROJECT: Sensory Garden Code No. 970
LOCATION: Citywide Parks Account No.
Project Description
Select a site and design and install a therapeutic or sensory garden.
Project Funding Schedule Total Cost: $295,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Desi /Engineering 45,000
Land Acquisition
Construction/Improvements 250,000 _
Construction Management
Total 0 0 295,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 295,000
Total 0 0 295,000 0 0 0 0 0
DRAFT NOV 2017 B-107 15 5
City of Moorpark
Capital Improvement Program
PROJECT: Disc Golf Course Code No. 971
LOCATION: Citywide Parks Account No.
Project Description
Determine an appropriate location for and install a disc golf course, including walkways and amenities.
Objective IV.A.20
Project Funding Schedule Total Cost: $150,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 25,000
Land Acquisition
Construction/Improvements 125,000
Construction Management
Total 0 0 150,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 150,000
Total 0 0 150,000 0 0 0 0 0
PROJECT: Electronic Marquees Code No. 972
LOCATION: Citywide Parks Account No.
Project Description
Determine appropriate locations for and install electronic messaging marquees. Replace the magnetic
marquee at AVCP with an electronic marquee.
Project Funding Schedule Total Cost: $275,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition —
Construction/Improvements 27.5,000
Construction Management
Total 0 275,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 275,000
Total 0 275,000 0 0 0 0 0 0
156
DRAFT NOV 2017 B-108
City of Moorpark
Capital Improvement Program
PROJECT: Permanent Game Equipment Code No. 973
LOCATION: Citywide Parks Account No.
Project Description
Select sites and install various permanent game equipment including a shuffleball court, horseshoe pit, and
cornhole pit.
Project Funding Schedule Total Cost: $30,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/2.2 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 30,000
Construction Management
Total 0 30,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY Y 18/19 FY 19/20 FY 20/2.1 FY 21/22 FY Y 22/23 FY 23/24
Undetermined 30,000
Total 0 30,000 0 0 0 0 0 0
PROJECT: Baseball Field Code No. 974
LOCATION: Citywide Parks Account No.
Project Description
Identify site and install a baseball field.
•
Project Funding Schedule Total Cost: $260,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 35,000
Land Acquisition —
Construction/Improvements - 225,000
Construction Management
Total 0 0 260,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 260,000
Total 0 0 260,000 0 0 0 0 0
DRAFT NOV 2017 B-109 15 7
City of Moorpark
Capital Improvement Program
PROJECT: Bocce Ball Court Code No. 975
LOCATION: Citywide Parks Account No.
Project Description
Select site and install an additional bocce ball court.
Project Funding Schedule Total Cost: $10,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 10,000
Construction Management
Total 0 0 10,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 10,000
Total 0 0 10,000 0 0 0 0 0
PROJECT: Ball Wall Code No. 976
LOCATION: Citywide Parks Account No.
Project Description
Identify location and install a ball wall.
Project Funding Schedule Total Cost: $35,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements 35,000
Construction Management
Total 0 35,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 35,000
Total 0 35,000 0 0 0 0 0 0
DRAFT NOV 2017 B-110 158,
City of Moorpark
Capital Improvement Program
PROJECT: Update Park Features Code No. 977
LOCATION: Citywide Parks Account No.
Project Description
Improve drinking fountains, identify locations and install electronic play systems, tandem swings, and
other upgraded features.
Project Funding Schedule Total Cost: $175,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering
Land Acquisition
Construction/Improvements _.___..._—_.....__.... 175,000
Construction Management
Total 0 0 175,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/2.3 FY 23/24
Undetermined 175,000
Total 0 0 175,000 0 0 0 0 0
PROJECT: Additional Exercise Equipment Code No. 978
LOCATION: Citywide Parks Account No.
Project Description
Identify locations and install additional exercise equipment.
Project Funding Schedule Total Cost: $150,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering — — —Land Acquisition
Construction/Improvements 150,000
Construction Management
Total 0 0 150,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 150,000
Total 0 0 150,000 0 0 0 0 0
DRAFT NOV 2017 B-111 159
City of Moorpark
Capital Improvement Program
PROJECT: Community Pool Code No. 979
LOCATION: Citywide Parks Account No.
Project Description
Coordinate construction of community pool with the High School or identify location and construct a
community pool facility at a City park. Objective IV.B.2
Project Funding Schedule Total Cost: $3,000,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering __......._............_
- -- Land Acquisition.- — .._._...—
Construction/Im rovements 3,000,000 __._.............-.-.-.-.--.-.--.
Construction Management
Total 0 0 3,000,000 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY Y 21/22 FY 22/23 FY 23/24
Undetermined 3,000,000
Total 0 0 3,000,000 0 0 0 0
PROJECT: Parks and Recreation Master Plan Update Code No. 980
LOCATION: Citywide Parks Account No.
Project Description
Update Parks and Recreation Master Plan to ensure goals and policies remain current and are based on
recreational needs of the community.
Project Funding Schedule Total Cost: $75,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering 75,000
Land As uisition
Construction/Improvements
Construction Management
Total 0 0 75,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 75,000
Total 0 0 75,000 0 0 0 0 0
DRAFT NOV 2017 B-112 16 0
Trails
DRAFT NOV 2017 B-113 161
City of Moorpark
Capital Improvement Program
LOCATION: Zone 15 Code No. 1001
PROJECT: Trail Improvements Account No.
Location Map
chasPP�°�Sh P _
PROJECT AREA
Project Description
Renovate trails to improve drainage and minimize runoff. Remove horse crossing bars at the entrance to all
multi-use trails, and replace with more effective alternative device or system where feasible.
Project Funding Schedule Total Cost: $585,000
Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Design/Engineering_..—...---.....-----.__.._...._......_85,000
Land Acquisition ---
Construction/Improvements 500,000
Construction Management
Total 0 85,000 500,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24
Undetermined 85,000
500,000
Total 0 85,000 500,000 0 0 0 0 0
16 2
DRAFT NOV 2017 B-114
City of Moorpark
Capital Improvement Program
C. Program Expenditure Summaries
• Total Program Project Costs (Listed by Fiscal Year) C-2
• Total Program (Seven Years) — Spread to Funding Source C-3
DRAFT NOV 2017 C-1 16 3
Total Program Project Costs
By Fiscal Year
16 4
DRAFT NOV 2017 C-2
Program Expenditure Summary
Program Summary: Fiscal Years 2017/18- 2023/24
Project
Code Project Name Number Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24 Total
FACILITIES (600)
Arroyo Vista Recreation Center and Gym
601 Back-Up Generator M0023 $95,000 $33,000 $128,000
602 HVAC Replacement M0024 $100,000 $100,000
603 Kitchen Remodel M0025 $150,000 $150,000
604 Facility Expansion C0042 $75,000 $2,250,000 $2,325,000
605 Security Cameras $35,000 $35,000
606 Water Conservation Improvements $55,000 $55,000
607 Flag Pole Installation _ $12,000 $12,000
608 Gymnasium Expansion C0048 $79,700 $2,250,000 $2,329,700
Arroyo Vista Recreation Center and Gym Total: $0 $372,000 $2,512,700 $0 $2,250,000 $0 $0 $0 $5,134,700
City Hall/Civic Center Complex
609 New Library&Civic Center Complex C0012 $1,285,945 $3,460,063 $38,500,000 $43,246,008
610 Pedestrian Access Improvements C0014 $37,058 $576,546 $613,604
611 Back-Up Generator M0023 $105,000 $105,000
612 Fire Sprinkler System M0035 $65,000 $65,000
613 Patio Remodel $25,000 $25,000
614 Water Conservation Improvements _ $60,000 _ $60,000
615 Flag Pole Installation $12,000 $12,000
616 Security Cameras $40,000 $40,000
617 Energy Efficiency Improvements $35,000 $35,000
City Hall/Civic Center Complex Total: $1,323,003 $4,278,609 $100,000 $38,500,000 $0 $0 $0 $0 $44,201,612
High Street Arts Center
618 Roof Renovation $80,000 $80,000
619 Interior Improvements $65,000 $65,000
620 ADA/Building Code Improvements $40,000 $40,000
High Street Arts Center Total: $0 $40,000 $65,000 . $80,000 $0 $0 $0 $0 $185,000
Metrolink Parking Lot
621 Art In Public Places 7708 $225,000 $225,000
Moorpark Library
622 Restroom Improvements $25,000 _ $25,000
623 Security Cameras $35,000 $35,000
624 Parking Lot Improvements _ $155,000 _ $155,000
625 HVAC Replacement $85,000 $85,000
Moorpark Library Total: $0 $300,000 $0 $0 $0 $0 $0 $0 $300,000
165
Program Expenditure Summary
Program Summary: Fiscal Years 2017/18- 2023/24
Project
Code Project Name Number I Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24 Total
Police Services Center
626 Art In Public Places Installation _ _ _ C0015 $10,961 $156,539 $167,500
627 Landscape Improvements _ $75,000 $75,000
628 Parapet Wall Installation $165,000 $165,000
629 Additional Parking $217,000 $217,000
Police Services Center Total: I $10,961 $156,539 $457,000 $0 $0 $0 $0 $0 $624,500
Moorpark Public Services Facility
630 Back-Up Generator M0023 $106,000 $106,000
631 Lighting Improvements $75,000 $75,000
632 Roof Drain Improvements $50,000 $50,000
633 Outdoor Break Area $50,000 -$50,000
634 Water Conservation Improvements $25,000 $25,000
635 Fueling Station $500,000 $500,000
Moorpark Public Services Facility Total: $0 $100,000 $206,000 $0 $0 $0 $500,000 $0, $806,000
Ruben Castro Human Services Center
636 Sidewalk Installation $75,000 I $75,000
31 Poindexter Avenue
637 Building Modifications $150,000 $150,000
Citywide
638 Purchase City Streetlights $2,200,000
$2,200,000
FACILITIES TOTAL $1,333,964 $7,447,148 $3,790,700 $38,580,000 $2,250,000 $0 $500,000 $0 $53,901,812
166
Program Expenditure Summary -
Program Summary: Fiscal Years 2017/18 - 2023/24
Project
Code Project Name Number I Prior Yrs FY 17/18 FY 18/19 I FY 19/20 FY 20/21 ( FY 21/22 FY 22/23 FY 23/24 Total
LANDSCAPE MAINTENANCE DISTRICTS (LMDS) & GENERAL LANDSCAPING (700)
701 High Street Improvements $2,875,000 I $2,875,000
702 Princeton Avenue Landscape Renovations(Campus Park Area) $285,000 $285,000
703 Campus Park Median Renovations(Campus Park Area) $400,000 $400,000
704 Princeton Avenue Oak Tree $65,000 $65,000
705 Championship Drive Landscape Renovations(Zone 15) $2,085,000 $2,085,000
706 LA Avenue Parkway and Wall Treatment Renovations $180,000 $180,000
707 LA Avenue Parkway Renovations (Zone 7) $155,000 $155,000
708 Poindexter Avenue Landscaping $170,000 $170,000
709 Spring Road Landscape Improvements(Zone 12) $545,000 $545,000
710 Spring Road Street Trees $65,000 $65,000
711 Spring Road Street Trees(Zone 22) $25,000 $25,000
712 Metrolink Station Landscape Improvements $25,000 $25,000
713 Tierra Rejada Road Streetscape Renovation M0031 $405,351 $145,000 $2,250,000 $2,800,351
714 Tierra Rejada/Moorpark Road Intersection Improvements $95,000 $95,000
715 City Welcome Sign Improvements $132,000 $132,000
716 Off-Ramp Landscape Improvements $3,450,000 $3,450,000
717 Peach Hill Wash Channel Improvements $650,000
$650,000
LANDSCAPE MAINTENANCE DISTRICTS &GENERAL LANDSCAPING TOTAL: $405,351 $2,932,000 $10,495,0001 $170,000 $0, $0, $0 $0 $14,002,351
OPEN SPACE (800)
(No Current Projects)
PARKS (900)
Arroyo Vista Community Park
901 Ball Field Lighting $2,500,000 $2,500,000
902 Water Spray Attraction _ $665,000 $665,000
903 Pedestrian Bridge Lighting $170,000 $170,000
904 Ramp/Walkway/Bike Path from Mountain Trail St. $573,000 $573,000
905 Softball Fencing Improvements _ $20,000 $20,000
906 Slope Landscaping $55,000 $55,000
907 Storage Improvements C0047 $80,000 $80,000
908 Lease SCE Property _ $2,500,000 $2,500,000
909 New Pedestrian Bridge $375,000 $375,000
910 Sand Volleyball Court $60,000 $60,000
Arroyo Vista Community Park Total: $0 $135,0001 $6,863,000 $0 $0 $0 $0 $0 $6,998,000
167
a
Program Expenditure Summary .
-
Program Summary: Fiscal Years 2017/18- 2023/24
Project
Code Project Name Number Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22 FY 22/23 FY 23/24 Total
Campus Canyon Park
911 Basketball Court Improvements $12,000 $12,000
912 Replace Playground Equipment $175,000 $175,000
913 Parking Lot $206,000 $206,000
Campus Canyon Park Total: $0 $12,000 $175,000 $206,000 $0 $0 $0 $0 $393,000
Campus Park
914 Restroom Improvements $203,000 $203,000
915 Pavilion Improvements $10,000 $10,000
916 Replace Playground Equipment $175,000 $175,000
Campus Park Total: $0 $213,000 $175,000 $0 $0 $0 $0 $0 $388,000
College View Park
917 Sand Volleyball Court $45,000 $45,000
918 Basketball Court Improvements $87,000 $87,000
919 Dog Park Lighting $83,000 $83,000
920 Park Improvements $27,000 $27,000
921 New Park Sign $35,000 $35,000
College View Park Total: $0 $45,000 $118,000 $114,000 $0 $0 $0 $0 $277,000
Community Center Park
922 Replace Playground Equipment $125,000 $125,000
Country Trail Park
923 Playground Improvements&ADA Access $422,000 $422,000
924 Restroom Addition $285,000 $285,000
925 Landscape Improvements $25,000 $25,000
926 Parkour Training Circuit $175,000 $175,000
927 Install Trail $45,000 $45,000
Country Trail Park Total: $0 $70,000 $597,000 $285,000 $0 $0 $0 $0 $952,000
Glenwood Park
928 Basketball Court Lighting $71,000 $71,000
929 Sand Volleyball Court $45,000 $45,000
930 Install Trail $12,000 $12,000
931 Replace Playground Equipment - $250,000 $250,000
932 New Park Sign $35,000 $35,000
Glenwood Park Total: $0 $12,000 $401,000 $0 $0 $0 $0 $0 $413,000
168
Program Expenditure Summary
Program Summary: Fiscal Years 2017/18-2023/24
Project
Code Project Name Number I Prior Yrs I FY 17/18 FY 18/19 I FY 19/20 FY 20/21 FY 21/22 FY 22/23 I FY 23/24 Total
Magnolia Park
933 Replace Playground Equipment $175,000 $175,000
Mammoth Highlands
934 Sand Volleyball Court $45,000 $45,000
935 Basketball Court Lighting Improvements $39,500 $39,500
936 Expand Trail $25,000 $25,000
Mammoth Highlands Total: $0 $70,000 $39,500 $0 $0 $0 $0; $0 $109,500
Miller Park
937 Lighting Addition $25,000 $25,000
938 Loop Trail $45,000 $45,000
939 Replace Playground Equipment $250,000 $250,000
Miller Park Total: $0 $70,000 $0 $250,000 $0 $0 $0 $0 $320,000
Monte Vista Nature Park
940 Lighting Improvements $25,000 $25,000
.
941 Shade Structure $30,000 $30,000
942 Landscape Improvements $300,000 $300,000
943 Trail System Improvements $150,000 $150,000
Monte Vista Nature Park Total: $0 $55,000 $150,000 $300,000 $0 $0 $0 $0 $505,000
Mountain Meadows
944 Handball Wall C0045 $7,324 $34,600 $41,924
1 945 Loop Trail $35,000 $35,000
946 Replace Playground Equipment $225,000 $225,000
Mountain Meadows Total: $7,324 $34,600 $260,000 $0 $0 $0 $0 $0 $301,924
Peach Hill Park
947 Lighting Upgrades &Additions $300,000 $300,000
948 Picnic Pavilion Improvements $75,000 $75,000
949 Loop Trail $45,000 $45,000
950 Sand Play Area $20,000 $20,000
951 Replace Playground Equipment $135,000_ $135,000
Peach Hill Park Total: $0 $75,000 $65,000 $435,000, $0 $0 $0 $0 $575,000
Poindexter Park
952 Security Camera Improvements $35,000 $35,000
953 Skate Park Fencing $30,000 $30,000
954 Park Amenity Improvements $30,000 -$30,000
955 Pathway Improvements $65,000 $65,000
Poindexter Park Total: $0 $160,000 $0 $0 $0 $0 $0 $0 $160,000
169
Program Expenditure Summary
Program Summary: Fiscal Years 2017/18- 2023/24
Project
Code Project Name Number Prior Yrs FY 17/18 FY 18/19 FY 19/20 FY 20/21 I FY 21/22 FY 22/23 FY 23/24 Total
Tierra Rejada Park
956 Lighting Additions $85,000 $85,000
957 Tennis Court Addition _ $70,000 $70,000
958 Parking Lot Expansion $106,000 $106,000
959 Replace Playground Equipment $400,000 $400,000
Tierra Rejada Park Total: $0 $0 $661,000 $0 $0 $0 $0 $0 $661,000
Villa Campesina Park
960 Security Improvements _ $55,000 $55,000
961 Replace Playground Equipment $250,000 - $250,000
Villa Campesina Park Total: $0 $55,000 $250,000 $0 $0 $0 $0 $0 $305,000
Virginia Colony Park
962 Basketball Court Addition $55,000 $55,000
963 Replace Playground Equipment $200,000 $200,000
Virginia Colony Park Total: $0 $0 $55,000 $0 $0 $200,000 $0 $0 $255,000
Walnut Acres Park _
964 Security Cameras 7 $10,000 _ I $10,000
Citywide Parks
965 Central Irrigation System C0019 $293,519 $188,404 - $481,923
966 Lighting Upgrades $555,000 1 $555,000
967 ADA Improvements $60,000 I $60,000
968 Universally Accessible Playground Equipment $350,000 I $350,000
969 BMX/Free Style Bicycle Facility $850,000 $850,000
970 Sensory Garden $295,000 $295,000
971 Disc Golf Course $150,000 $150,000
972 Electronic Marquees $275,000 $275,000
973 Permanent Game Equipment $30,000 $30,000
974 Baseball Field $260,000 $260,000
975 Bocce Ball Court $10,000 $10,000
976 Ball Wall $35,000 $35,000
977 Update Park Features $175,000 $175,000
978 Additional Exercise Equipment $150,000 $150,000
979 Community Pool _ $3,000,000 _ $3,000,000
980 Parks and Recreation Master Plan Update $75,000 $75,000
Citywide Parks Total: $293,519 $1,143,404! $4,465,000 $850,000 $0 $0 $0' $0 $6,751,923
PARKS TOTAL: $300,843 $2,160,004 $14,399,500 $2,440,000 $0 $200,000 $175,000 $0 $19,675,347
170
Program Expenditure Summary
Program Summary: Fiscal Years 2017/18-2023/24
Project
Code Project Name Number Prior Yrs FY 17/18 I FY 18/19 FY 19/20 I FY 20/21 I FY 21/22 FY 22/23 FY 23/24 Total
TRAILS (1000)
1001 Zone 15 Trail Improvements $85,000 $500,000
$585,000
TRAILS TOTAL: $0 $85,000 $500,000 $0 $0 $0 $0 $0 $585,000
TOTAL PROGRAM EXPENDITURE: $2,040,158 $12,624,152 $29,185,200 $41,190,000' $2,250,000 $200,000 $675,000 $0! $88,164,510
171
Total Program
(FY 2017/18 — FY 23/24)
By Funding Source
172
DRAFT NOV 2017 C-3
Program Funding Summary
Program Funding Source:Fiscal Year 2017/18-2023/24
1000: 2007: 2010: 2013: 2018: 2300: 2302: 2307: 2310: 1 2312: 2315: 2322: 3001: 1 2001: 2411: 2414:
Project General Art In Public Park Park Imp. Endowment 84-2 84-2 84-2 84-2 Mtn 84-2 Country Moorpark City Hall Traffic Sys TDA TDA
Code Project Name Number Fund Places Improvement Zone 3 Fund Citywide LLMD Steeple Hill LA Ave Meadows Carlsberg Club Estates Highlands I Improvement j Management Article 3 Article 8C Undetermined Total
Facilities(600)
Arroyo Vista Recreation Center and Gym
601 Back-Up Generator M0023 $128,000 _ _ $128,000
602 HVAC Replacement M0024 $100,000 $100,000
603 Kitchen Remodel M0025 $150,000 _ $150,000
604 Facility Expansion C0042 $75,000 $2,250,000 $2,325,000
605 Security Cameras $35,000 $35,000
606 Water Conservation Improvements $55,000 $55,000
607 Flag Pole Installation $12,000 $12,000
608 Gymnasium Expansion C0048 $79,700 $2,250,000 $2,329,700
Arroyo Vista Recreation Center and Gym Total: $378,000 $0 $79,700 $0 $75,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $4,602,000 $5,134,700
City Hall/Civic Center Complex -
609 New Library&Civic Center Complex C0012 $343,172 $42,902,836 $43,246,008
610 Pedestrian Access Improvements C0014 $506,144 $82,750 $24,710 $613,604
611 Back-Up Generator M0023 $105,000 $105,000
612 Fire Sprinkler System M0035 $65,000 $65,000
613 Patio Remodel $25,000 $25,000
614 Water Conservation Improvements $60,000 $60,000
615 Flag Pole Installation _ ' $12,000 $12,000
616 Security Cameras $40,000 $40,000
•
617 Energy Efficiency Improvements $35,000 $35,000
City Hall/Civic Center Complex Total $170,000 $0 $0 $0 $343,172 $0 $0 $0 $0 $0 $0 $0 $42,902,836 $506,144 $82,750 $24,710 $172,000 $44,201,612
High Street Arts Center
618 Roof Renovation - $80,000 $80,000
619 Interior Improvements $65,000 $65,000
620 ADA/Building Code Improvements $40,000 $40,000
High Street Arts Center Total: $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $185,000 $185,000
Metrolink Parking Lot
621 Art In Public Places 7708 $225,000 $225,000
Moorpark Library
622 Restroom Improvements $25,000 $25,000
623 Security Cameras $35,000 $35,000
624 Parking Lot Improvements $155,000 $155,000
625 HVAC Replacement $85,000 $85,000
Moorpark Library Total: $0 $0 $0 $0 $0 $0 $0 $0 $0 $0, $0 $0 $0 $0 $0 $0 $300,000 $300,000
Police Services Center
626 Art In Public Places Installation C0015 $167,500 $167,500
•
627 Landscape Improvements $75,000 $75,000
628 Parapet Wall Installation $165,000 $165,000
629 Additional Parking $217,000 $217,000
Police Services Center Total: $0 $167,500 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $457,000 $624,500
173
Program Funding Summary
Program Funding Source:Fiscal Year 2017/18-2023/24
1000: 2007: 2010: 2013: 2018: 2300: 2302: 2307: 2310: 2312: 2315: 2322: 3001: 2001: 2411: 2414:
Project General Art In Public Park Park Imp. Endowment 84-2 84-2 84-2 84-2 Mtn 84-2 Country Moorpark City Hall Traffic Sys ! TDA TDA
Code Project Name Number Fund Places Improvement Zone 3 Fund Citywide LLMD Steeple Hill I LA Ave Meadows Carlsberg Club Estates Highlands Improvement Management Article 3 Article 8C Undetermined Total
Moorpark Public Services Facility
630 Back-Up Generator M0023 $106,000 $106,000
631 Lighting Improvements _ _ _ $75,000 $75,000
632 Roof Drain Improvements _ _ $50,000 $50,000
633 Outdoor Break Area $50,000 $50,000
634 Water Conservation Improvements $25,000 $25,000
635 Fueling Station $500,000 $500,000
Moorpark Public Services Facility Total: $106,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $700,000 $806,000
Ruben Castro Human Services Center
636 Sidewalk Installation $75,000 $75,000
31 Poindexter Avenue
637 Building Modifications $150,000 $150,000
Citywide
638 Purchase City Streetlights $2,200,000
$2,200,000
Facilities Total: $654,000 $392,500 $79,700 $0 $2,618,172 $0 $0 $0 $0 $0 $0 $0 $42,902,836 $506,144 $82,750 $24,710 $6,641,000 $53,901,812
LANDSCAPE MAINTENANCE DISTRICTS(LMDs)&GENERAL LANDSCAPING(700)
701 High Street Improvements $2,875,000 • $2,875,000
Princeton Avenue Landscape
702 Renovations(Campus Park Area) $285,000 $285,000
Campus Park Median Renovations
703 (Campus Park Area) $400,000 $400,000
704 Princeton Avenue Oak Tree $65,000 $65,000
Championship Drive Landscape
705 Renovations(Zone 15) $2,085,000 $2,085,000
LA Avenue Parkway and Wall
706 Treatment Renovations $180,000 $180,000
LA Avenue Parkway Renovations
707 (Zone 7) $155,000 $155,000
708 Poindexter Avenue Landscaping $170,000 $170,000
Spring Road Landscape
709 Improvements(Zone 12) - $136,250 $408,750 $545,000
710 Spring Road Street Trees $65,000 $65,000
711 Spring Road Street Trees(Zone 22) $25,000 $25,000
Metrolink Station Landscape
712 Improvements $25,000 $25,000
Tierra Rejada Road Streetscape
713 Renovation M0031 $2,776,201 $24,150 $2,800,351
Tierra Rejada/Moorpark Road
714 Intersection Improvements $95,000 $95,000
715 City Welcome Sign Improvements $132,000 $132,000
716 Off-Ramp Landscape Improvements $3,450,000 $3,450,000
Peach Hill Wash Channel
717 Improvements $650,000 $650,000
Landscape Maintenance Districts(LMDs)& 1 7 4
General Landscaping Total: $2,776,201 $0 $0 $0 $0 $3,901,250 $24,150 $155,000 $650,000 $408,750 $2,085,000, $25,000, $0 $0 $0 $0 $3,977,000 $14,002,351
Program Funding Summary
Program Funding Source:Fiscal Year 2017/18-2023/24
1000: 2007: 2010: 2013: 2018: 2300: 2302: 2307: 2310: 2312: 2315: 2322: 3001: 2001: 2411: 2414:
Project General Art In Public Park Park Imp. Endowment I 84-2 84-2 84-2 84-2 Mtn 84-2 Country Moorpark City Hall Traffic Sys TDA TDA
Code Project Name Number Fund Places Improvement Zone 3 Fund Citywide LLMD Steeple Hill LA Ave Meadows Carlsberg Club Estates Highlands Improvement Management Article 3 Article 8C Undetermined Total
OPEN SPACE(800)
(No Current Projects) I
PARKS(900)
Arroyo Vista Community Park •
901 Ball Field Lighting $2,500,000 $2,500,000
•
902 Water Spray Attraction $665,000 $665,000
903 Pedestrian Bridge Lighting $170,000 $170,000
Ramp/Walkway/Bike Path from
904 Mountain Trail Street $573,000 $573,000
905 Softball Fencing Improvements $20,000 $20,000
906 Slope Landscaping $55,000 $55,000
907 Storage Improvements C0047 $80,000 $80,000
908 Lease SCE Property $2,500,000 $2,500,000
909 New Pedestrian Bridge $375,000 $375,000
910 Sand Volleyball Court $60,000 $60,000
Arroyo Vista Community Park Total: $0 $0 $80,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $6,918,000 $6,998,000
Campus Canyon Park
911 Basketball Court Improvements $12,000 $12,000
912 Replace Playground Equipment $175,000 $175,000
913 Parking Lot , $206,000 $206,000
Campus Canyon Park Total: I $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $393,000 $393,000
•
Campus Park
914 Restroom Improvements $203,000 $203,000
915 Pavilion Improvements $10,000 $10,000
916 Replace Playground Equipment $175,000 $175,000
Campus Park Total: $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $388,000 $388,000
College View Park
917 Sand Volleyball Court $45,000 $45,000
918 Basketball Court Improvements $87,000 $87,000
919 Dog Park Lighting
$83,000 $83,000
920 Park Improvements $27,000 $27,000
921 New Park Sign $35,000 $35,000
College View Park Total: $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0, $0 $0 $0 $277,000 $277,000
Community Center Park
922 Replace Playground Equipment $125,000 $125,000
Country Trail Park
Playground Improvements&ADA
923 Access $422,000 $422,000
924 Restroom Addition $285,000 $285,000
925 Landscape Improvements $25,000 $25,000
926 Parkour Training Circuit $175,000 $175,000
927 Install Trail $45,000 $45,000
Country Trail Park Total: $0 $0 $0, $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $952,000 $952,000
175
I
Program Funding Summary
Program Funding Source:Fiscal Year 2017/18-2023/24
1000: I 2007: 2010: 2013: 2018: 2300: 2302: 2307: I 2310: I 2312: 2315: 2322: 3001: 2001: 2411: 2414:
Project ' General I Art In Public Park Park Imp. Endowment 84-2 84-2 84-2 84-2 Mtn 84-2 Country Moorpark City Hall Traffic Sys TDA TDA
Code Project Name Number Fund Places Improvement Zone 3 Fund Citywide LLMD Steeple Hill I LA Ave Meadows Carlsberg Club Estates 1 Highlands Improvement Management Article 3 Article 8C Undetermined Total
Glenwood Park
928 Basketball Court Lighting $71,000 $71,000
929 Sand Volleyball Court _ $45,000 $45,000
930 Install Trail $12,000 $12,000
931 Replace Playground Equipment $250,000 $250,000
932 New Park Sign $35,000 $35,000
Glenwood Park Total: $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $413,000 $413,000
Magnolia Park
933 Replace Playground Equipment
$175,000 $175,000
Mammoth Highlands
934 Sand Volleyball Court - $45,000 $45,000
Basketball Court Lighting
935 Improvements $39,500 $39,500
936 Expand Trail $25,000 $25,000
Mammoth Highlands Total: $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $109,500 $109,500
Miller Park
937 Ughting Addition $25,000 $25,000
938 Loop Trail $45,000 $45,000
939 Replace Playground Equipment $250,000 $250,000
Miller Park Total: $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $320,000 $320,000
Monte Vista Nature Park
940 Ughting Improvements $25,000 $25,000
941 Shade Structure $30,000 $30,000
942 Landscape Improvements $300,000 $300,000
943 Trail System Improvements $150,000 $150,000
Monte Vista Nature Park Total: $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0, $0 $505,000 $505,000
Mountain Meadows
944 Handball Wall C0045 $34,600, $7,324 $41,924
945 Loop Trail $35,000 $35,000
946 Replace Playground Equipment $225,000 $225,000
Mountain Meadows Total: $0 $0 $34,600 $7,324 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $260,000 $301,924
Peach Hill Park
947 Lighting Upgrades&Additions $300,000 $300,000
948 Picnic Pavilion Improvements $75,000 $75,000
949 Loop Trail $45,000 $45,000
950 Sand Play Area $20,000 $20,000
951 Replace Playground Equipment $135,000 $135,000
Peach Hill Park Total: $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $575,000 $575,000
Poindexter Park
952 Security Camera Improvements $35,000, $35,000
953 Skate Park Fencing - $30,000 $30,000
954 Park Amenity Improvements $30,000 $30,000
955 Pathway Improvements $65,000 $65,000
Poindexter Park Total: $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $160,000 $160,000
176
Program Funding Summary
Program Funding Source:Fiscal Year 2017/18-2023/24
1000: 2007: 2010: 2013: 2018: 2300: 2302: 2307: 2310: 2312: 2315: 2322: 3001: 2001: 2411: 2414:
Project General Art In Public Park Park Imp. Endowment 84-2 84-2 84-2 84-2 Mtn 84-2 Country Moorpark City Hall Traffic Sys TDA TDA
Code Project Name Number Fund Places Improvement Zone 3 Fund Citywide LLMD Steeple Hill , LA Ave Meadows Carlsberg Club Estates Highlands Improvement Management Article 3 Article 8C Undetermined Total
Tierra Rejada Park
956 Lighting Additions I _ $85,000 $85,000
957 Tennis Court Addition
_- $70,000 $70,000
958 Parking Lot Expansion L - I $106,000 $106,000
959 Replace Playground Equipment I $400,000 $400,000
Tierra Rejada Park Total: $0 $0 $0 $0 $0 $01 $0 $0 $0 $0 $0 $0 $0 $0 $0, $0 $661,000 $661,000
Villa Campesina Park
960 Security Improvements $55,000 $55,000
961 Replace Playground Equipment 5250,000 $250,000
Villa Campesina Park Total: $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $305,000 $305,000
Virginia Colony Park
962 Basketball Court Addition $55,000 $55,000
963 Replace Playground Equipment $200,000 $200,000
Virginia Colony Park Total: $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $255,000 $255,000
Walnut Acres Park
964 Security Cameras $10,000 $10,000
Citywide Parks
965 Central Irrigation System C0019 $260,003 $33,111 $34,466 $61,937 $92,406 $481,923
966 Ughting Upgrades $555,000 $555,000
967 ADA Improvements $60,000 $60,000
Universally Accessible Playground
968 Equipment • $350,000 $350,000
969 BMX/Free Style Bicycle Facility $850,000 $850,000
970 Sensory Garden $295,000 $295,000
971 Disc Golf Course $150,000 $150,000
972 Electronic Marquees $275,000 $275,000
973 Permanent Game Equipment $30,000 $30,000
974 Baseball Field $260,000 $260,000
975 Bocce Ball Court $10,000 $10,000
976 Ball Wall $35,000 $35,000
977 Update Park Features $175,000 $175,000
978 Additional Exercise Equipment $150,000 $150,000
979 Community Pool $3,000,000 $3,000,000
Parks and Recreation Master Plan
980 Update $75,000 $75,000
Citywide Parks Total: $260,003 $0 $0 $0 $0 $0 $33,111 $0 $0 $34,466 $61,937 $92,406 $0 $0 $0 $01 $6,270,000 $6,751,923
Parks Total: $260,003 $0 $114,600 $7,324L $0 $0 $33,111 $0 $0 $34,466 $61,937 $92,406 $0 $0 $0 $0' $19,071,500 $19,675,347
TRAILS(1000)
1001 Zone 15 Trail Improvements
$585,000 $585,000
Trails Total: ( $0 $01 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $- $0 $0 $0 $585,000 $585,000
Total Program Expenditure: $3,690,2041 $392,500 $194,300 $7,3241 52,618,1721 $3,901,250 $57,261_ $155,000 $650,000 $443,216, $2,146,937 $117,406! $42,902,836 $506,144 $82,7501 $24,710 $30,274,500, $88,164,510
177
Appendix I: Summary of Completed Projects
Facilities
ACTIVE ADULT CENTER
ITEM/DESCRIPTION DATE COST
CENTER EXPANSION 03/2000 $ 424,055.80
KITCHEN AIR CONDITIONING 09/2000 $ 8,693.00
AUTOMATIC SLIDING DOOR 09/2000 $ 7,135.20
KITCHEN RENOVATION (SINKS/OVEN) 06/2015 $ 10,358.81
ARROYO VISTA RECREATION CENTER
ITEM/DESCRIPTION DATE COST
GYMNASIUM CONSTRUCTION 01/1993 $1,180,357.02
RECREATION CENTER BUILDING CONSTRUCTION 01/1993 $1,150,192.14
RETAINING WALL, RECREATION CENTER 01/1993 $ 3,674.81
SCOREBOARD(2) FOR GYM 01/1993 $ 6,553.44
LIGHTS, 13 STEEL OUTDOOR 01/1999 $ 40,600.00
LED SCOREBOARD (2) FOR GYM 08/2003 $ 6,682.00
VIDEO MONITORING SYSTEM 09/2004 $ 18,890.00
THEATER SYSTEM 01/2007 $ 10,760.77
RECREATION CENTER BUILDING EXPANSION 08/2008 $2,050,918.72
SOUND SYSTEM &SYNCHRONIZER 11/2011 $ 5,964.18
BASKETBALL BACKBOARDS FOR GYM 09/2014 $ 17,975.23
SCOREBOARD(2), SHOT TIMER, RECEIVERS FOR GYM 09/2014 $ 12,100.98
TELESCOPIC BLEACHERS FOR GYM 01/2015 $ 50,088.00
CITY HALL
ITEM/DESCRIPTION DATE COST
CITY HALL BUILDING CONSTRUCTION 01/1988 $ 460,153.19
GENERATOR, BACKUP 01/1990 $ 61,686.83
GENERATOR, EMERGENCY 07/2000 $ 1,599.53
TELEPHONE SYSTEM, CABLE, &CONSULTANT 07/2001 $ 82,469.71
COMPUTER ROOM FIRE SYSTEM 04/2005 $ 19,337.00
CITY HALL AUDIO SYSTEM 08/2005 $ 32,128.91
HEAT PUMP CONDENSING UNIT#1, #2,  03/2011 $ 10,890.00
MODULAR BUILDING -ANNEX - 01/1992 $ 112,710.28
ANALYSER, MERCURY VAPOR ANNEX 01/2002 $ 5,790.11
DRAFT NOV 2017 I-1 1 7 8
DOSIMETER, PERSONAL ALARM ANNEX 04/2002 $ 3,736.97
ANNEX IMPROVEMENTS 01/2007 $ 483,047.82
MODULAR BUILDING - BREAKROOM/FILE ROOM 09/2010 $ 55,693.98
MODULAR BUILDING - DEVELOPMENT SERVICES 09/2010 $ 116,264.04
FIRE SPRINKLER SYSTEM DEV SVS MODULAR 06/2012 $ 50,816.00
ADA IMPROVEMENTS 2013 $ 15,500.00
COMMUNITY CENTER
ITEM/DESCRIPTION DATE COST
COMMUNITY CENTER BUILDING CONSTRUCTION 01/1981* $1,084,258.05
FLAGPOLE 01/1981* $ 2,286.18
LIGHTS, 7 STEEL OUTDOOR 01/1981* $ 11,060.18
PATIO WALL, BLOCK W/STUCCO 01/1981* $ 6,302.45
PAVING, ASPHALT 01/1981* $ 19,463.44
LAND, CIVIC CENTER 05/1984 $ 460,400.00
KITCHEN IMPROVEMENTS 01/1988 $ 7,446.68
A/V IMPROVEMENTS 01/1988 $ 11,955.32
AN IMPROVEMENTS 01/1995 $ 10,175.88
AN IMPROVEMENTS 1998-2001 $ 7,962.04
ROOF REPAIR/CONSTRUCTION 02/2000 $ 39,604.32
VIDEO MONITOR, MOTION MEDIA, CAMERA/AUDIO 04/2002 $ 64,123.35
SYSTEMS
BROADCASTING SYSTEM &VIDEO SYSTEM 06/2002 $ 46,516.65
REFURBISHMENT
PIONEER DUAL DVD RECORDERS (2) 09/2003 $ 8,784.00
WATER HEATER 02/2005 $ 2,025.00
AN IMPROVEMENTS 2005 $ 59,597.33
LIGHTING SYSTEM 01/2006 $ 47,595.57
SPEAKERS, RACK AND MOUNT 01/2006 $ 7,911.22
PROJECTOR SYSTEM & INSTALL 10/2007 $ 5,628.69
CC VIDEO CTRL RM UPGRADE 06/2008 $ 12,226.00
HEATNENT AC#1, 2, 3, 4, 8, 9, & 10 08/2010 $ 76,746.49
AN IMPROVEMENTS 2010-2015 $ 6,292.41
CAMERA, VIDEO HD (4) & REMOTE CAMERA CONTROLLER 02/2015 $ 40,504.52
PARKING LOT IMPROVEMENTS 12/2015 $ 71,821.00
17 9
DRAFT NOV 2017 I-2
HIGH STREET ARTS CENTER
ITEM/DESCRIPTION DATE COST
BUILDING & LAND PURCHASE 07/2005 $1,250,879.57
SOUND SYSTEM & PROJECTOR 04/2007 $ 84,620.96
MOVING LIGHTS (4) 07/2011 $ 3,329.48
AUDIO WIRELESS PERSONAL MONITOR 04/2012 $ 261.06
PROPERTY ACQUISITION (61 HIGH STREET) 01/2016 $ 880,000
LIBRARY
ITEM/DESCRIPTION DATE COST
LAND, ACCESS RD & PARKING LOT 05/1984 $ 313,600.00
LAND, BUILDING 12/2006 $2,559,060.00
MEDIA DROP 01/2011 $ 2,717.29
POLICE SERVICE CENTER
ITEM/DESCRIPTION DATE COST
LAND, POLICE SERVICE CENTER 04/2001 $1,011,889.19
POLICE SERVICE CENTER CONSTRUCTION 06/2006 $9,784,082.11
SECURITY, VIDEO SYSTEM 06/2002 $ 6,831.95
SURVEILLANCE, VIDEO SYSTEM 06/2002 $ 8,141.76
FIRE PROTECTION SYSTEM FM200 12/2010 $ 17,928.82
LIGHTING UPGRADES 5/2014 $ 44,556.00
PARKING LOT PAVING 02/2016 $ 24,910.00
POST OFFICE
ITEM/DESCRIPTION DATE COST
LAND PARCEL 08/1993 $ 231,500.00
LAND POST OFFICE DOWNTOWN PARKING LOT 01/2011 $ 555,982.00
POST OFFICE PARKING LOT IMPROVEMENTS 01/2011 $ 595,695.00
PUBLIC SERVICES FACILITY
ITEM/DESCRIPTION DATE COST
LAND, MPSF 02/2002 $ 790,664.00
PUBLIC SERVICES FACILITY CONSTRUCTION 04/2007 $6,576,746.15
FENCE, CHAIN LINK 07/2004 $ 8,294.00
IRON FENCE INSTALL& GATE KEYPAD 02/2008 $ 43,879.79
ICE MAKER, CUBE-STYLE 02/2013 $ 2,938.49
18 0
DRAFT NOV 2017 I-3
CARD READER ENTRY SYSTEM 11/2015 $ 6,869.00
RUBEN CASTRO HUMAN SVC CTR
ITEM/DESCRIPTION DATE COST
LAND -2 ARCE PARCEL MAP 5426 06/2003 $ 653,175.00
LAND, PARKING LOT 05/2010 $ 117,252.46
PUBLIC ART:WE ARE ONE FAMILY 04/2012 $ 113,497.99
CONCRETE FOOTING FOR ART 07/2013 $ 31,309.26
BUILDING B CONSTRUCTION 07/2013 $8,812,924.52
EMERGENCY GENERATOR, ENGINE &ALTERNATOR 07/2013 $ 83,870.00
HEATNENT AC UNITS (14 TOTAL) 07/2013 $ 70,000.00
IRRIGATION CONTROLLER 07/2013 $ 9,846.61
PRE-FAB SUNSHADE FOR BUILDING B 08/2014 $ 238,175.51
COURTYARD GATE REPLACEMENT 11/2016 $ 9,150.00
TSA REJADA ROAD I MOUNTAIN TRAIL STREET INTERSECTION
ITEM/DESCRIPTION DATE COST
911 MEMORIAL SCULPTURE/FOUNTAIN 03/2002 146,777
Parks, Landscaping, Open Space &Trails
ARROYO VISTA COMIITY PARK
ITEM/DESCRIPTION DATE COST
LAND, ACCESS ROAD 07/1/1983 $ 113,400.00
LAND, PARK SITE 05/11/1984 $5,708,300.00
LAND, PARK SITE 01/06/1988 $4,066,200.00
LAND, ACCESS ROAD 09/11/1992 $ 330,900.00
PHASE I CONSTRUCTION 01/01/1993 $ 514,543.68
LAND, ACCESS ROAD 05/06/1996 $ 290,800.00
FOOTBALL FIELD GOAL POST (2 TOTAL) 09/01/1997 $ 3,611.84
MULTI-PURPOSE COURT W/FENCE 01/01/1999 $ 100,000.00
PATIO AND PATHWAYS PAVING, CONCRETE 01/01/1999 $ 75,000.00
TENNIS COURT CONSTRUCTION 12/15/1999 $ 202,412.26
TENNIS COURT SPORTWALL 04/05/2000 $ 3,140.00
CONCEPTUAL DESIGN PHASE II 11/01/2000 $ 5,570.77
POOL CAD MAPPING, TOPO SURVEY, GEOTECHINICAL 12/20/2000 $ 5,600.00
RESTROOM BUILDING (EAST) DESIGN & 06/27/2001 $ 17,904.08
CONSTRUCTION
DRAFT NOV 2017 I-4 181
SOCCER GOALS (4 TOTAL) 08/01/2001 $ 4,815.80
DRINKING FOUNTAIN GALVANIZED 11/11/2002 $ 1,209.02
FOOTBALL FIELD FENCE 09/30/2003 $ 4,996.00
PARK ENTRY GUARDRAIL 06/18/2004 $ 8,750.00
PHASE II EXPANSION CONSTRUCTION 11/17/2004 $2,052,599.68
PUMP, SUBMERSIBLE WELL#1 10/31/2008 $ 21,835.68
PLAYGROUND STRUCTURES & SWINGS 07/02/2010 $ 165,000.43
IRRIGATION CONTROL PANEL SYSTEM WELLS#1 & 3 06/13/2014 $ 50,450.00
PUMP, SEWAGE SUBMERSIBLE#1  06/13/2014 $ 21,600.00
VFD SEWER CONTROL PANEL 06/13/2014 $ 25,600.00
PUBLIC ART: LITHOMOSAICS AND BRONZE TOAD 11/21/2014 $ 151,944.00
PARKING LOT IMPROVEMENTS 12/15/2015 $ 448,342.00
SLOPE RETAINING WALL 2/1/2017 $ 133,937.37
RECREATIONAL TRAIL 6/30/2017 $3,275,479.00
PARKING LOT IMPROVEMENTS 6/30/2017 $ 474,680.00
LIGHTING IMPROVEMENTS 6/30/2017 $ 447,000.00
MULTI-USE COURT IMPROVEMENTS 8/15/2017 $ 58,341.00
ACCESS ROAD IMPROVEMENTS 12/1/2017 $ 457,000.00
BUFFER ZONE
ITEM/DESCRIPTION DATE COST
LAND, HOME ACRES BUFFER ZONE 04/05/1994 $ 264,500.00
TURF REPLACEMENT 01/16/2016 $ 28,824.00
BUTTERCREEK PARK
ITEM/DESCRIPTION DATE COST
LAND, PARK SITE AT DAISY/PEPPERMILL 05/11/1984 $ 473,700.00
LAND, PARK SITE AT PEPPERMILL ST 05/11/1984 $ 888,000.00
CAMPUS CANYON PARK
ITEM/DESCRIPTION DATE COST
LAND, PARK SITE 10/1986 $1,110,600.00
RETAINING WALL, BLOCK 04/1990 $ 18,894.06
SOFTBALL FIELD BACKSTOP 01/1994 $ 3,061.92
DRINKING FOUNTAINS 01/1994 $ 3,674.30
FENCE, BALLFIELD 01/1994 $ 2,711.65
FENCE, STEEL BAR & BLOCK 01/1994 $ 106,279.09
DRAFT NOV 2017 I-5 18 2
LIGHTS, 5 STEEL OUTDOOR 01/1994 $ 9,272.09
PAVING, CONCRETE GROUP 01/1994 $ 42,774.05
PICNIC PAVILION 01/1994 $ 17,849.05
i
SAND PIT FOR PLAYGROUND 01/1994 $ 14,432.96
RESTROOM 01/1994 $ 26,215.79 I
RETAINING WALL, BLOCK/STUCCO 01/1994 $ 5,073.41
FENCE, REPLACE WROUGHT IRON 02/2000 $ 17,895.00
PLAYGROUND EQUIPMENT 09/2000 $ 31,082.85
SURFACE, PLAYGROUND 10/2000 $ 31,187.77
DRINKING FOUNTAIN GALVANIZED 03/2003 $ 1,273.51
5' BLACK IRON FENCE 11/2008 $ 11,355.00
CAMPUS PARK
ITEM/DESCRIPTION DATE COST
LAND, PARK SITE 05/1984 $ 249,500.00
LAND, PARK SITE 10/1987 $ 279,800.00
DRINKING FOUNTAIN 01/1988 $ 1,625.09
r
FENCE, REAR PERIMITER 01/1988 $ 5,798.66
LIGHTS, 5 STEEL OUTDOOR 01/1988 $ 12,602.41
PAVING, PAVILION AND BASKETBALL COURT 01/1988 $ 31,853.94
PICNIC PAVILION 01/1988 $ 14,491.01
SAND PIT FOR PLAYGROUND 01/1988 $ 8,504.69
RESTROOM BUILDING 01/1988 $ 17,283.55
PLAYGROUND EQUIPMENT 07/2001 $ 43,209.87
PARK MONUMENT SIGN (CONCRETE) 04/2003 $ 3,343.26
PARK TABLES& BENCHES 04/2008 $ 9,625.47
LIGHTING UPGRADES 05/2014 $ 41,808.00
COLLEGE VIEW PARK
ITEM/DESCRIPTION DATE COST
LAND, PARK SITE 05/1984 $ 643,000.00
DRINKING FOUNTAINS 01/1990 $ 3,494.82
FENCE, CHAIN LINK 01/1990 $ 8,856.28
LIGHTS, 11 STEEL OUTDOOR 01/1990 $ 32,719.04
PAVING, CONCRETE 01/1990 $ 65,602.08
PICNIC PAVILION 01/1990 $ 15,905.68
SAND AND WOODCHIP PITS FOR PLAYGROUND 01/1990 $ 14,760.48
PLAYGROUND STRUCTURE 01/1990 $ 16,988.70
DRAFT NOV 2017 I-6 18 3
RESTROOM BUILDING 01/1990 $ 41,586.73
SIGN, PARK 01/1990 $ 1,476.05
TABLE, PICNIC W/BENCHES (13 TOTAL) 01/1990 $ 13,882.18
PLAYGROUND EQUIPMENT 08/1999 $ 5,800.00
COLLEGE VIEW PARK MONUMENT 07/2003 $ 2,348.00
PARK TABLES & BENCHES 07/2007 $ 6,917.63
SECURITY LIGHTS (6) INSTALL 06/2008 $ 27,151.02
BASKETBALL COURT LIGHTS 09/2009 $ 19,702.59
PLAYGROUND EQUIPMENT& INSTALLATION 06/2010 $ 62,549.96
DOG PARK ADDITION 09/2010 $ 79,473.87
BENCH, CONCRETE 06/2015 $ 1,063.18
COMMUNITY CENTER PARK
ITEM/DESCRIPTION DATE COST
PERIMETER FENCE, STEEL 01/1981* $ 16,003.27
DRINKING FOUNTAIN 01/1988 $ 1,625.09
SAND PIT FOR PLAYGROUND 01/1998 $ 4,638.92
PLAYGROUND STRUCTURE & SWINGS 01/1998 $ 8,215.73
TABLE, PICNIC, W/BENCHES (7) 01/1998 $ 7,583.73
DRINKING FOUNTAIN GALVANIZED 11/2002 $ 1,209.02
PLAYGROUND STRUCTURE 12/2002 $ 40,843.37
PARKING LOT IMPROVEMENT 12/2015 $ 75,417.00
COUNTRY TRAIL PARK
ITEM/DESCRIPTION DATE COST
LAND, PARK SITE 11/1995 $ 900,000.00
DRINKING FOUNTAIN 01/1997 $ 1,792.83
FENCE, STEEL BAR & STONE 01/1997 $ 107,560.94
LIGHTS, 6 STEEL OUTDOOR 01/1997 $ 18,398.58
PAVING, ASPHALT 01/1997 $ 29,720.79
PAVING, CONCRETE 01/1997 $ 101,899.84
SAND PITS FOR PLAYGROUND 01/1997 $ 31,136.06
PLAYGROUND STRUCTURES (2), EQUIPMENT& 01/1997 $ 22,155.62
SWINGS
SIGN, PARK CONCRETE 01/1997 $ 943.52
TABLE, PICNIC W/BENCHES 01/1997 $ 1,095.62
PLAYGROUND FENCE, WROUGHT IRON 05/2001 $ 6,786.00
IRRIGATION CONTROLLER 08/2012 $ 3,296.17
DRAFT NOV 2017 I-7 184
PLAYGROUND STRUCTURE REPAIRS 09/2012 $ 5,823.63
CONCRETE PARK BENCHES (8) & PICNIC TABLES (8) 07/2013 $ 15,299.40 i
PARKING LOT IMPROVEMENTS 12/2015 $ 13,759.00
GLENWOOD PARK
ITEM/DESCRIPTION DATE COST
LAND, PARK SITE 05/1984 $ 659,300.00 f
BASKERBALL COURT& PATHWAYS PAVING 01/1994 $ 58,606.58
DRINKING FOUNTAIN 01/1994 $ 1,837.15
LIGHTS, 5 STEEL OUTDOOR 01/1994 $ 9,272.09
PERIMITER FENCE, CHAIN LINK 01/1994 $ 11,546.37
PICNIC PAVILION 01/1994 $ 19,522.40
SAND PITS FOR PLAYGROUND (3 TOTAL) 01/1994 $ 28,865.94
PLAYGROUND STRUCTURES (2) & SWINGS 01/1994 $ 28,475.89
SIGN, PARK CONCRETE 01/1994 $ 874.73
PICNIC TABLES WITH BENCHES (6 TOTAL) 01/1994 $ 6,736.26
PLAYGROUND STRUCTURE 06/2006 $ 15,883.27
CONCRETE PARK TABLES 01/2009 $ 6,812.52
RESTROOM BUILDING 03/2011 $ 385,332.00
SWING -4 SEAT 11/2013 $ 1,862.61
TABLE, PICNIC CONCRETE (2 TOTAL) 06/2015 $ 2,257.50
LANDSCAPED
PARKWAYS
ITEM/DESCRIPTION DATE COST
WATERSCAPE -TIERRA REJADA AT MOUNTAIN TRAIL 02/2002 $ 145,866.50
SIGNS STEEPLE HILL ENTRY 05/2003 $ 3,921.49
IRRIGATION CONTROLLERS(38 TOTAL) 08/2011 $ 273,814.18
IRRIGATION CONTROLLER 04/2014 $ 8,581.65
MAGNOLIA PARK
ITEM/DESCRIPTION DATE COST
LAND, PARK SITE 06/2003 $ 55,000.00 .
LAND, PARK SITE 10/2003 $ 67,622.00
FENCE, WROUGHT IRON 10/2007 $ 10,000.00
PARK BENCHES AND TABLES 10/2007 $ 10,000.00
PARK CONSTRUCTION 10/2007 $ 280,293.91
PLAYGROUND EQUIPMENT&SWINGS 10/2007 $ 64,541.75
DRAFT NOV 2017 I-8 18 5
J
MAMMOTH HIGHLANDS PARK
ITEM/DESCRIPTION DATE COST
LAND, PARK SITE 12/2005 $7,577,422.44
MAMMOTH ART BONE SCULPTURES 07/2009 $ 25,290.62
PARK CONSTRUCTION 07/2009 $3,044,506.00
IRRIGATION CONTROLLERS 08/2011 $ 10,871.00
MILLER PARK
ITEM/DESCRIPTION DATE COST
LAND, PARK SITE 06/2000 $ 283,400.00
LAND, PARK SITE 06/2000 $ 353,200.00
BACKSTOP 09/2000 $ 1,200.00
BALLFIELD BLEACHER, ALUMINUM 09/2000 $ 2,500.00
BALLFIELD FENCE, CHAIN LINK 09/2000 $ 12,000.00
BASKETBALL COURT PAVING 09/2000 $ 40,000.00
DRINKING FOUNTAIN 09/2000 $ 3,000.00
LIGHTS, 14 STEEL OUTDOOR 09/2000 $ 120,000.00
PAVILION/PLAYGROUND FENCE, STEEL 09/2000 $ 12,000.00
SAND PIT FOR PLAYGROUND 09/2000 $ 15,000.00
PLAYGROUND STRUCTURES (2)AND EQUIPMENT 09/2000 $ 33,000.00
SIGN, PARK W/LIGHTS 09/2000 $ 20,000.00
SOCCER GOAL 09/2000 $ 2,407.90
PICNIC TABLES (17 TOTAL) 09/2000 $ 13,600.00
TENNIS COURT FENCE, CHAIN LINK 09/2000 $ 20,000.00
TENNIS COURT WITH LIGHTS 09/2000 $ 70,000.00
TENNIS SCREEN 09/2000 $ 3,500.00
PICNIC PAVILION 10/2000 $ 63,000.00
RESTROOM BUILDING 10/2000 $ 66,924.00
SWING SETS 06/2008 $ 12,614.79
BASKETBALL COURT LIGHTS 09/2009 $ 23,869.25
INSTALL CONCRETE FIXTURES (REPLACE METAL) 04/2012 $ 11,287.00
PARKING LOT IMPROVEMENTS 12/2015 $ 25,189.00
MONTE VISTA NATURE PARK
ITEM/DESCRIPTION DATE COST
LAND, PARK SITE 02/1990 $ 800,000.00
DRINKING FOUNTAIN 01/1990 $ 1,747.41
DRAFT NOV 2017 I-9 18 6
PAVING, ASPHALT 01/1990 $ 11,070.35
PICNIC TABLE WITH BENCHES(2 TOTAL) 01/1990 $ 2,135.72
PARKING LOT IMPROVEMENTS 12/2015 $ 33,011.00
MOUNTAIN MEADOWS PARK
ITEM/DESCRIPTION DATE COST
LAND, PARK SITE 03/1987 $1,223,200.00
BACKSTOPS (2 TOTAL) 01/1992 $ 6,140.14
BALLFIELD FENCE, CHAIN LINK 01/1992 $ 1,605.89
BLEACHER, ALUMINUM 01/1992 $ 1,535.03
DRINKING FOUNTAINS (3 TOTAL) 01/1992 $ 5,526.12
LIGHTS, 6 STEEL OUTDOOR 01/1992 $ 18,425.47
PAVING, ASPHALT 01/1992 $ 40,823.80
PAVING, CONCRETE 01/1992 $ 55,699.01
PERIMITER FENCE, CHAIN LINK 01/1992 $ 5,071.23
PICNIC PAVILION 01/1992 $ 17,992.91
PLAYGROUND STRUCTURES (2) & SWINGS 01/1992 $ 15,964.35
RESTROOM BUILDING 01/1992 $ 23,764.22
SIGN, PARK 01/1992 $ 845.21
PICNIC TABLES WITH BENCHES (12 TOTAL) 01/1992 $ 13,508.28
PARK MONUMENT SIGN (CONCRETE) 03/2003 $ 5,573.13
PLAYGROUND STRUCTURE 06/2006 $ 122,845.73
PARK TABLES & BENCHES 04/2008 $ 6,921.92
BASKETBALL COURT LIGHTS 09/2009 $ 61,905.17
OPEN SPACE
ITEM/DESCRIPTION DATE COST
OPEN SPACE LAND: TIERRA REJADA ROAD 02/2011 $1,982,429.38
PEACH ISL PARK
ITEM/DESCRIPTION DATE COST
LAND, PARK SITE 05/1984 $1,375,100.00
BACKSTOP 01/1992 $ 3,070.07
BALLFIELD FENCE, CHAIN LINK 01/1992 $ 2,113.01
BALLFIELD LIGHTS, 6 STEEL OUTDOOR 01/1992 $ 63,390.38
BASKETBALL COURT& PATHWAY PAVING, CONCRETE 01/1992 $ 29,159.57
BLEACHER, ALUMINUM (2 TOTAL) 01/1992 $ 3,070.06
LIGHTS 14 STEEL OUTDOOR 01/1992 $ 29,582.18
DRAFT NOV 2017 I-10 18 7
PARKING LOT PAVING, ASPHALT 01/1992 $ 60,432.16
PICNIC PAVILION 01/1992 $ 22,406.26
SAND/WOOD CHIP PIT FOR PLAYGROUND 01/1992 $ 19,017.11
PLAYGROUND FENCE, WOOD RAIL 01/1992 $ 3,380.82
RESTROOM BUILDING 01/1992 $ 109,654.88
PICNIC TABLES WITH BENCHES (13 TOTAL) 01/1992 $ 14,633.97
DRINKING FOUNTAIN 09/2000 $ 1,214.83
PLAYGROUND STRUCTURE &SWINGS 09/2000 $ 47,000.04 I
PICNIC TABLES & BENCHES 08/2007 $ 14,988.19
PLAYGROUND EQUIPMENT& INSTALLATION 06/2010 $ 29,999.58
IRRIGATION CONTROLLERS 08/2011 $ 21,610.50
PLAYGROUND STRUCTURE 02/2013 $ 35,668.18
PARKING LOT IMPROVEMENT 12/2015 $ 47,120.00
SOFTBALL BLEACHERS 6/2017 $ 24,617.00
POINDEXTER PARK
ITEM/DESCRIPTION DATE COST
LAND, PARK SITE 12/1996 $1,172,000.00
BACKSTOPS 01/1996 $ 5,994.08
BLEACHER, ALUMINUM (4 TOTAL) 01/1996 $ 5,994.08
FENCE, BALLFIELD & PAVILION, CHAIN LINK 01/1996 $ 6,567.63
FENCE, BRICK/STEEL BAR(BTWN PARK& SHOPS) 01/1996 $ 28,120.52 I
FENCE, PERIMITER 01/1996 $ 13,320.24
DRINKING FOUNTAIN 01/1996 $ 3,596.44
FLAGPOLE 01/1996 $ 3,422.56
GAZEBOS (2) 01/1996 $ 3,330.06
LIGHTS, 32 STEEL OUTDOOR 01/1996 $ 76,868.91
PARKING LOT LIGHTS, 8 STEEL OUTDOOR 01/1996 $ 24,050.44
PAVILION PAVING, CONCRETE 01/1996 $ 23,495.43
PAVING, ASPHALT 01/1996 $ 108,226.99 1
PICNIC PAVILION 01/1996 $ 42,353.55
RESTROOM BUILDING 01/1996 $ 76,215.40
SIGN, PARK CNCRT/STONE W/LGHTS 01/1996 $ 4,162.58
GAZEBO, METAL 8' SIDES (2) 02/2002 $ 50,000.00
LAND, PARK SITE (FOR EXPANSION) 02/2004 $ 645,171.00
TABLE, PICNIC W/BENCHES 03/2006 $ 9,993.40
SKATE PARK 12/2009 $2,068,864.00
DRAFT NOV 2017 I-11 18 8
LIGHTING UPGRADES (LED) 05/2014 $ 166,000.00
PLAYGROUND EQUIPMENT& STRUCTURES 04/2015 $ 115,000.00
PARKING LOT IMPROVEMENTS 12/2015 $ 36,618.00
DRAINAGE IMPROVEMENTS 04/2017 $ 14,191.50
TIERRA REJADA PARK
ITEM/DESCRIPTION DATE COST
LAND, PARK SITE 01/1992 $ 960,000.00
BASKETBALL AND TENNIS COURT PAVING, CONCRETE 01/1995 $ 78,581.56
PAVING, ASPHALT 01/1995 $ 9,070.56
DRINKING FOUNTAINS (3 TOTAL) 01/1995 $ 5,561.52
LIGHTS, 8 STEEL OUTDOOR 01/1995 $ 26,044.18
PERMIITER FENCE, STEEL BAR &STONE 01/1995 $ 96,094.03
PICNIC PAVILION 01/1995 $ 34,179.26
SAND PITS FOR PLAYGROUND 01/1995 $ 39,515.31
RESTROOM BUILDING 01/1995 $ 44,997.89
PICNIC TABLES WITH BENCHES (9 TOTAL) 01/1995 $ 10,196.10
TENNIS COURTS 01/1995 $ 107,769.00
SIGN, PARK 01/1995 $ 898.08
SCREEN, TENNIS COURT 04/2001 $ 3,760.00
INTERIOR FENCE, WROUGHT IRON 06/2001 $ 15,990.00
PLAYGROUND FENCE(REPLACEMENT) 09/12/2001 $ 3,350.70
PARK MONUMENT SIGNS (CONCRETE) 03/2003 $ 9,866.25
BOCCE BALL COURT 03/2003 $ 6,778.79
STORAGE BOX 06/2004 $ 1,100.00
PLAYGROUND STRUCTURE AND EQUIPMENT 06/2007 $ 181,155.59
PARK TABLES & BENCHES 08/2007 $ 10,376.44
PARK BENCHES CONCRETE (11 TOTAL) 07/2013 $ 10,051.25
BENCH, CEDAR 10/2014 $ 1,536.37
PARK BENCH, CONCRETE 02/2015 $ 976.10
PICKLEBALL COURT 08/2017 $ 20,400.00
VETERANS MEMORIAL PARK
ITEM/DESCRIPTION DATE COST
LAND, PARK SITE 04/2001 $ 83,139.44
VETERANS MEMORIAL PARK CONSTRUCTION 05/2009 $ 508,249.34
DRAFT NOV 2017 I-12 18 9
VILLA CAMPESINA PARK
ITEM/DESCRIPTION DATE COST
LAND, PARK SITE 08/1998 $ 199,200.00
LIGHTS, 8 STEEL OUTDOOR 09/1996 $ 9,600.00
FENCE, CHAIN LINK 09/1998 $ 2,000.00
DRINKING FOUNTAIN 04/2002 $ 1,200.00
PARK MONUMENT SIGN (CONCRETE) 04/2003 $ 3,343.27
PLAYGROUND STRUCTURE 04/2004 $ 27,395.00
PLAYGROUND SURFACING & BASE 06/2004 $ 14,801.00
BASKETBALL COURT EQUIPMENT 06/2004 $ 1,900.00
BASKETBALL COURT PAVING 06/2004 $ 9,600.00
GRADING, TRENCHING 06/2004 $ 3,525.00
SIDEWALK, ENTRY, & STEEL BOLLARDS 06/2004 $ 4,150.00
V1RG MIA COLONY PARK
ITEM/DESCRIPTION DATE COST
LAND, PARK SITE 01/1996 $ 300,000.00
DRINKING FOUNTAIN 01/1988 $ 2,257.07
SAND/WOOD CHIP PIT FOR PLAYGROUND 01/1988 $ 2,164.83
PLAYGROUND STRUCTURE 01/1988 $ 6,771.21
SIGN, PARK 01/1988 $ 5,798.66
FENCE, CHAIN LINK 09/1993 $ 2,706.04
DRINKING FOUNTAIN GALVANIZED 11/2002 $ 1,217.12
PLAYGROUND STRUCTURE 06/2006 $ 55,135.91
WALNUT ACRES PARK
ITEM/DESCRIPTION DATE COST
LAND,161 SECOND STREET 02/2011 $ 551,235.31
PARK CONSTRUCTION 10/2015 $ 875,000.00
*Information on file for projects completed prior to City incorporation. Dates to be verified prior to
publication.
DRAFT NOV 2017 I-13 19 0
Appendix II: Description of Funding Sources
FUND TITLE DESCRIPTION
Property tax, sales tax, business license, franchise fees,
1000 General Fund fines and forfeitures, investment interest, funds from other
agencies, fees for service. Primary City fund for operational
expenditures.
Fees based on the air quality impacts of development with
the purpose of mitigating these impacts by funding programs
2001 Traffic Systems Management or projects that reduce emissions. Funds can only be used
Fund to appropriate programs including, but not limited to, low
emissions and alternative fuel vehicles for the City fleet and
transit buses.
Fees to provide art in public areas resulting from the demand
2007 Art In Public Places Fund for additional art from new development. Used to fund
projects that provide art in public areas.
2010- Quimby Act fees from developers in lieu of dedicating park
2013 Park Improvement Fund land. For use for construction of park facilities as a result of
increased demand for parks resulting from new development.
Developer fee paid by a developer as a condition of the
issuance of a building permit for each residential or
2018 Endowment Fund institutional use within the boundaries of the specific plan.
The development fee may be expended by the City in its sole
and unfettered discretion.
Citywide and special benefit assessments levied upon each
property within districboundaes and collected 2300- Assessment District Parkways& County Tax Collie tort Prov des funding for public by
streeura
2332 Medians Citywide Fund lighting and parkway/median landscape maintenance and
improvement on designated landscape districts.
Local transportation fund derived from Y.cent of general
2411- Local Transportation sales tax collected by Statewide and allocated to the City by
2414 Development Act Fund (Articles Ventura County Transportation Commission (VCTC). Used
8A, 8C, 3 &6.5) for transportation and street/road maintenance related
expenses.
Funds come from developers through various special
3001 City Hall Improvement Fund agreements. Funds are used for the purpose of building a
new Civic Center Complex.
DRAFT NOV 2017 II-1 191
Appendix Ill:
Potential Projects, Feasibility Studies, Plans, and Evaluations
Location Title Description
Active Adult Center Citrus Room Make the Citrus Room a formal part of the Active Adult
Conversion Center upon completion of the new City.Hall building.
Arroyo Vista AVCP Access Prepare a feasibility study on a second access point for
Community Park Point Arroyo Vista Community Park.
Buttercreek Park Buttercreek Park Determine disposition of Buttercreek Park site. Objective
site V.A.15
Campus Canyon Basketball Court Evaluate installing lights at the basketball court.
Park Lights
College View Park Soccer Field Select a location to potentially add a soccer field.
Addition
College View Park Fire Station Evaluate the feasibility of constructing a fire station on a
portion of the park.
Glenwood Park Restroom Privacy Explore options to increase privacy at the Glenwood Park
restroom.
Glenwood Park Park Expansion Evaluate options for potential expansion of Glenwood
Park.
Miller Park Sports Field Evaluate alternative uses for the sports field. Objective
Alternate Use V.A.21
Monte Vista Nature Security Add security features at Laurelhurst Road entrance.
Park Improvements
Park TBD Tennis Court Select a park site to locate a tennis court in the Campus
Park area.
Parks TBD Security Cameras Evaluate parks for installation of security cameras.
Objective V.A.14
Parks TBD Community Evaluate parks/open space for development of a
Garden Community Garden. Objective V1.8.5
Parks TBD Dog Park Evaluate potential locations for a second dog park.
Parks TBD Amphitheater Evaluate installation of an outdoor performance
venue/amphitheater.
Peach Hill Park Driveway Addition Evaluate adding a second driveway to the parking lot off
Christian Barrett Drive.
Poindexter Park Additional Park Determine alternative uses for turf area adjacent to the
Amenity basketball court.
DRAFT NOV 2017 III-1 192
Post Office Park Potential Park Evaluate feasibility of constructing park facilities on
Site Facility remnant property west of post office. Objective V.A.16
Ridgecrest Drive Alternative Uses Evaluate potential park and recreation uses for the
asphalt area at the terminus of Ridgecrest Drive.
Tierra Rejada Park Volleyball Court Evaluate the feasibility of installing a volleyball court
option to the basketball court at Tierra Rejada Park.
Library Generator Evaluate the feasibility of installing a generator.
Open Space: 80 Site Plan Develop a comprehensive site plan and identify
Acre Parcel appropriate uses for the site, potentially including: 1) A
small lake or wetland with interpretive center; 2) A
seating area and access trail to the hill top view point; 3)
A loop trail; 4) A bicycle/pedestrian connection to Tierra
Rejada Road and adjacent communities; and/or 5) A
restored riparian corridor. Objective VI.A.9
Open Space: Passive Evaluate potential passive recreation uses and
Crawford Canyon Recreation Uses enhancements for open space at Crawford Canyon.
Open Space: Passive Evaluate potential passive recreation uses for the SDI
SDI Property Recreation Uses property. Objective VI.A.11
Open Space: Passive Evaluate potential uses for the 200+ acre Meridian Hills
Meridian Hills Recreation Uses open space property.
Waste Management Potential Uses Evaluate potential uses for the Waste Management site.
Site
Facility Location Additional Evaluate the feasibility of constructing a teen center or
TBD recreation center second recreation center.
LA Avenue Medians Install landscaping within future medians on LA Avenue.
Arroyo Simi Bike Path Evaluate feasibility of constructing an improved bike path
on the north side of the Arroyo Simi from AVCP
pedestrian bridge to the east side of Sprint Road.
Objective VI.8.4
Arroyo Simi Trail System Evaluate the feasibility of constructing a trail along the
levee road of the Arroyo Simi, from the westerly City limit
to Madera Road in Simi Valley.
Equestrian Staging Trail Connection Evaluate feasibility of connecting Moorpark Country Club
Areas equestrian staging area and the Meridian Hills equestrian
staging area with a loop multi-use trail. Objective IV.8.6
Highlands Trails Possible Trail Evaluate possible uses for alternate State Route 23 and
Connections North Hills Parkway rights-of-way, including possible trail
connection to College Heights Drive and Happy Camp
Regional Park. Objective V.A.21
_ High Street Art Art In Public Consider future location for public art project on High
Places Street.
DRAFT NOV 2017 III-2 • 19 3
Potential Maintenance and Non-capital Projects
Location Project Title Description
Arroyo Vista Card Reader Install a card reader at the main entry doors.
Recreation Center
Glenwood Park Park Benches Install park benches adjacent to the basketball court.
Mammoth
Highlands Park Shade Trees Plant shade trees adjacent to park benches
Miller Park Tree Planters Remove tree planters around the oaks trees adjacent to
the restroom.
Plant shade trees at picnic area on the east side of park,
Miller Park Trees replace oak trees at picnic area with shade trees, and
plant additional trees throughout the park as needed.
Miller Park Native Plants Plant native plant material at the vehicular turn-around.
Miller Park Turf Removal Remove turf behind the tennis court and provide
alternative paving options.
Miller Park Park Benches Install benches adjacent to the basketball court.
Miller Park Fencing Slough wall safety fencing at the base of the slope.
Maintenance
Mountain Trees Plant trees along the south side of the park adjacent to
Meadows Park the school site.
Mountain Park Benches Install park benches adjacent to the basketball court.
Meadows Park
Peach Hill Park Turf Renovation Renovate turf and improve drainage
Peach Hill Park Trees Plant additional trees at the north end of the park.
Peach Hill Park Park Name Sign Replace the park name sign with an updated sign.
Poindexter Park Recycle Install additional recycle receptacles throughout the
Receptacles park.
Virginia Colony Sign Remove the raised monument sign and replace with a
Park Replacement park name sign.
Virginia Colony Drinking Install a drinking fountain.
Park Fountain
Zone 15 & Zone Mutt Mitt Install Mutt Mitt dog waste bag dispensers at multi-use
22 Dispensers trial entrance locations.
DRAFT NOV 2017 III-3 19 4
End Of Document
DRAFT NOV 2017 195