MOORPARK CITY COUNCIL aoo
AGENDA REPORT
B`: -zti
TO: The Honorable City Council
FROM: Mary K. Lindley, Director of Community Services *
DATE: July 18, 2001 (CC Meeting of July 18, 2001)
SUBJECT: Consider Award Contract for Design of the Community
Aquatics Facility to Martinez & Amador Architects,.
Inc. and Adopt Resolution No. 2001-
SUMMARY
The current goal to meet the aquatic needs of the City is to
have a fully operational Community Aquatics Facility open to the
public by June, 2003. To that end, the City Council is being
asked to award a contract to Martinez & Amador Architects, Inc.
(M & A) for the design of the Community Aquatics Facility. It is
proposed that the contract be awarded at a cost not to exceed
$162,000. The design work to be performed by M & A includes
competitive and recreation pools, locker room facility, and an
adjacent parking lot.
Additionally, the Council is being asked to adopt a budget
amendment resolution (Attachment A), allocating $200,000 from
the Park Improvement Fund, Community Zone, to proceed with the
design phase of the Aquatics Facility. This allocation includes
the following costs: the architect ($164,000); PICON, the City's
project manager ($10,000); plan check fees ($11,000), and an
eight percent contingency ($15,000) for any additional design,
or soils and survey work that may be necessary.
DISCUSSION
Aquatic Facility Architect
At the City Council's direction, staff solicited proposals for
the design of the Community Aquatics Facility to be located at
Arroyo Vista Community Park (AVCP) . The City received proposals
M: \MLindley \Pool \architect contract award ccagd.doc
-,b,:l•
Aquatics Design Award
Page 2
from four qualified architectural firms. The firms included
Martinez & Amador Architects, HMC Group, RJM Design Group, and
Arch Pac.
Each of the four firms had an opportunity to make a presentation
to an oral review panel consisting of: Hugh Riley, Assistant
City Manager; Phil Vein, the City's contract project
coordinator; and Mary Lindley, Director of Community Services.
In evaluating the firms and their proposals, the panel
considered a number of factors, including, but not limited to:
the firm's understanding of the project; approach and
methodology; relevant experiences; creativity and sensitivity to
the City's needs and constraints; exceptions to the City's
contract; and price proposal.
Each panel member ranked Martinez & Amador as the top candidate
firm. A reference check was performed on the firm and it was
subsequently invited back to discuss the proposed contract
price. Prior to price negotiation, M & A's proposal was for
$180,000 broken down as follows: $152,000 for the Aquatic
Facility; $22,000 for the parking lot; and $6,000 for a model of
the selected design. Upon completion of price negotiations and a
full discussion of the scope of work and the City's
expectations, M & A was willing to reduce their initial price
proposal. M & A will perform all work identified in the City's
scope of work including the Aquatics Facility, parking lot, and
provide a model of the approved design for $164,000. This price
is competitive with the other proposals received by the City.
M & A is a well qualified firm and the staff to be assigned to
the City's project have very relevant experience. M & A recently
completed the design of a $12 million, 53,500 square foot,
Aquatic Center and Teen Center for the City of El Monte. Their
work to date has included a number of public workshops (design
charettes) and community meetings to engage input from the
residents. A construction contract was just awarded on the
project and construction is underway. M & A will continue to
work with El Monte through the construction and close -out phase.
The firm also performed design and engineering services for the
City of Costa Mesa's downtown Recreation Facility and Aquatic
Center. The design included a gymnasium, a pool, lockers and
showers, meeting rooms, a library addition, parking lot and
landscaping. Locally, M & A designed the newly constructed El
C00:106
Aquatics Design Award
Page 3
Rio Community Center and Gymnasium for the Rio School District
in E1 Rio.
M & A has an office in Thousand Oaks, from which the staff
assigned to the City's aquatics facility are located. This
should make site visits and the transfer of documents easier and
more convenient.
M & A has secured the consulting and design services of Rowley
International, a full - service aquatic design and engineering
firm. Rowley International has been in business for
approximately 27 years and has built aquatic facilities world-
wide and under a variety of conditions. M & A and Rowley worked
together on the aforementioned E1 Monte and Costa Mesa projects.
Rowley International's expertise will be important, not only in
providing a pool that meets the communities diverse needs, but
for designing a pool that is as economical as possible to
maintain. The City has yet to identify an on -going funding
source for pool maintenance and both M & A and Rowley will play
an important role in estimating maintenance costs associated
with the desired aquatics facility design and amenities. The
maintenance cost and the ability to find a on -going funding
source may impact the final design, facility amenities, and
whether or not the project will need to be built in phases.
Design Phase Budget
It is recommended that the City Council approve a budget for the
design phase of the Community Aquatics Facility project by
adopting the attached resolution amending the FY 2001/02 Budget.
The budget amendment would allocate $200,000 from the Park
Improvement Fund, Community Zone, to a project budget consisting
of: $164,000 for architectural and engineering; $10,000 for the
City's project manager (PICON) ; $11,000 for plan check fees
(this includes County Health Department plan check fees for the
pools); and an eight percent contingency ($15,000) for any
additional design work, such as the analysis and design of a
larger sewer pump station to accommodate the locker room.
Very preliminary estimates place the total cost to design and
construct the Community Aquatics Facility at approximately $2.4
million. To date, the City has allocated $10,000 toward initial
site work, including a soils test and topographical survey. In
addition to the design costs ($200,000) identified above,
estimated future costs to complete the project include: between
00 :10`
Aquatics Design Award
Page 4
$1.4 and $1.6 million for construction; $320,000 for design and
construction work for water and sewer to the pool site (this
assumes a larger sewer pump and grinder will be required and
includes water connection fees); approximately $100,000 for
design and installation of an electrical transformer and
electrical connection; $65,000 to PICON for project management
fees to coordinate construction; $21,000 for inspection fees
(City and County Public Health); and $285,000 as a modest 12
percent contingency. During the design process, the cost figures
will be better refined.
The current fund balance in the Community Zone Park Improvement
Fund is approximately $1,058,000. The Zone owes $486,000 of
which $176,000 is owed to the General Fund for the AVCP tennis
courts, and the remaining $310,000 is owed to other Improvement
Zones. The Community Zone is also owed $30,400 from another
Zone. This leaves a positive balance of approximately $602,400
if all loans were repaid today. The City can delay the repayment
of any or all of these loans until such time as new revenue is
generated. From the current positive balance, the City has the
funds to budget for the Aquatics Facility design work.
The City's ability to proceed with the construction of the
aquatics facility, and other park improvements, is dependent on
future revenues. Based on future development projections, it is
estimated that the Community Zone will receive approximately $11
million in new revenues over the next seven to ten years.
Included in that figure, the City expects to receive no less
than $2,592,000 in the Community Zone from Toll Brothers for
Tract 4928. Of the $11 million in new revenues, it is
anticipated that the City will have received $2.7 million by the
time the Aquatics Facility is completed in May 2003. However,
this estimate is based on residential construction in the City.
If certain residential projects are delayed or never
materialize, the estimated future revenue in the Park
Improvement Fund will be less.
Attachment A to this Agenda Report identifies the estimated fund
balance in the Park Improvement Fund - Community Zone based on
projected revenue (park improvement fees) and expenditures
(future park improvements) . As you can see, if the City proceeds
with all of the major improvements identified for AVCP, the
Community Zone is expected to experience a negative fund balance
Aquatics Design Award
Page 5
in FY 2002/03. This projection assumes that MUSD will not
participate in funding the aquatics facility.
In considering the budget for the aquatics facility, the City
must also think about future maintenance costs, which have yet
to be identified. Such consideration may determine whether the
entire envisioned aquatics facility is built at once or whether
certain components are delayed to a later date. Without MUSD's
financial participation, the City may need to proceed cautiously
with the construction of facility and work with the architect to
explore the feasibility of phasing the completion of the
project,
The City Council may wish to postpone future park projects, such
as AVCP Phase II improvements, and /or borrow from other Park
Improvement Zones, the General Fund, or Endowment Fund.
Borrowing would allow the City to proceed with the Aquatics
Facility, the restroom /concession /storage facility currently
under design, and preliminary improvements included in AVCP
Phase II (grading, irrigation, hydroseeding). This matter will
be discussed at a future meeting when more information in
available about construction and maintenance costs for the
facility.
STAFF RECOMMENDATION (Roll Call Vote)
Award a contract to Martinez and Amador Architects, Inc. in the
amount of $164,000 and authorize the City Manager to execute
said contract, and approve Resolution No. 2001 -_, amending the
FY 2001/02 Budget, allocating $200,000 for the design of the
Community Aquatics Facility.
Attachments:
C'00:'
Aquatics Design Award
Page 7
Attachment A
Resolution No. 2001-
EXHIBIT A
Budget Revision
A. Fund Allocation:
Fund No.
Fund Name
Amount
2100
Park Improvement Fund, Community Zone
$200,000.00
$200,000.00
$210,000.00
B. Budget Appropriation:
BUDGET NUMBER
BUDGETED
REVISION
NEW BUDGET
2153.7800.7017.9630
$10,000.00
$200,000.00
$210,000.00
Approved to Form:
Aquatics Design Award
Page 6
RESOLUTION NO. 2001-
RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF MOORPARK, CALIFORNIA, AMENDING THE FY
2001/02 BUDGET FOR THE DESIGN OF THE
COMMUNITY AQUATICS FACILITY AT AVCP BY
APPROPRIATING $200,000 FROM THE PARK
IMPROVEMENT FUND, COMMUNITY ZONE (2100), TO
THE AQUATICS FACILITY PROJECT BUDGET
(2153.7017) .
WHEREAS, on June 20, 2001, the City Council adopted the FY
2001/02 Budget; and
WHEREAS, on July 18, 2001, staff presented the Council with
a report which requests the appropriation of $200,000 from the
Park Improvement Fund, Community Zone, for the design of the
Community Aquatics Facility at Arroyo Vista Community Park; and
WHEREAS, Exhibit "A" hereof describes said budget amendment
and its resultant impacts to the budget line items.
NOW THEREFORE, THE CITY COUNCIL OF THE CITY OF MOORPARK
DOES RESOLVE AS FOLLOWS:
SECTION 1. A budget amendment to allocate $200,000 from the
Park Improvement Fund, Community Zone, and appropriate the same
for the design of the Community Aquatics Facility, as more
particularly described in Exhibit "A" attached hereto is hereby
approved.
SECTION 2. The City Clerk shall certify to the adoption of
the resolution and shall cause a certified resolution to be
filed in the book of original Resolutions.
PASSED AND ADOPTED this 18th day of July, 2001.
Patrick Hunter, Mayor
ATTEST:
Deborah S. Traffenstedt, City Clerk
ATTACHMENT B
Community Zone
Estimate Fund Balance Activity
Fiscal Year Expenditures /Projects Estimated Cost Revenue Fund Balance
2001 -2002
$1,376,000
$1,000,000
Aquatics Facility
$250,000
Restroom Facility
$460,000
AVCP Phase II
$500,000
$1,166,000
2002 -2003
$1,408,000
Aquatics Facility
$2,350,000
AVCP Phase II Completion
$1,000,000
($776,000)
2003 -2004
$1,828,000
Aquatics Facility
$50,000
$1,002,000
2004 -2005
$1,292,000
$2,294,000
2005 -2006
$992,000
$3,286,000
Beyond
$4,250,000
$7,536,000
These are estimates for discussion purposes only. Actual expenditure and revenue figures may
change