Loading...
HomeMy WebLinkAboutAGENDA REPORT 1994 1207 CC REG ITEM 08MAGENDA REPORT C = TY O F MOORPARK TO: The Honorable City Council FROM: Kenneth C. Gilbert, Director of Public Works DATE: November 28, 1994 (Council Meeting 12 -7 -94) 17 T%, I , A$ IT—_ _? Ar I FAA SUBJECT: Consider Approval of a Project for the Construction of Repairs to Wicks Road. A. Background The development of cracks in the street on Wicks Road, was recently brought to the attention of the City. The City initiated preliminary soils investigation efforts to determine the cause of the problem and to determine what, if any, corrective measures may be warranted. That initial effort indicates the existence of potential problems requiring remedial action. Attached is a Memo from the City Engineer providing some additional background information on this matter. B. Geotechnical Investigation The City Manager will be approving a professional services contract to retain A.G.I., Inc. to perform a complete soils analysis and provide the City with a design for the construction of remedial improvements required to address the problem. That design is expected to be completed within thirty (30) days. Upon completion of that effort, plans, specifications and a construction cost estimate (PS &E) will be prepared by the City Engineer. C. Project Costs The amount of the cost incurred to date for this project is summarized as follows: • City Engineer Preliminary Effort (Including Slosson Engineering) . . . . . . . $3,600 • J &H Engineering (Excavation, . . . . . . . $1,064 • AGI ( Geotechnical Report; . . . . _ . . . . . $8,800 Sub -total . . . . . . . . . . . . . . $13,464 Contingency . . . . . . . 1,536 Total to Date . . . . . . . . $15,000 wicksi 00075 Wicks Road December 1994 Page 2 A total project cost estimate will be developed by the City Engineer upon review of the Geotechnical Report to be prepared by A.G.I.. That cost estimate, along with a request for additional funding and a request for authorization to advertise for bids for a construction project, will be presented to the City Council when the project design is completed. D. Project Funding The funding source recommended for this project at this time is the Gas Tax Fund. An alternative funding source which could be considered is the Moorpark Redevelopment Agency (MRA). This option will be considered and discussed in more detail when the design work is completed and the full extent and cost of the required remedial work is known. tilY1:��J1 1 . • • Staff recommends that the City Council approve a fund appropriation from the Gas Tax Fund Reserve and an amendment to the FY 1994/95 Budget in the amount of $15,000 [03 -142 -903] for initial costs for the subject project. wicksz 00078 AGENDA REPORT CITY OF MOORPARK TO: THE HONORABLE CITY COUNC1_L FROM: Dirk Lovett, Assistant: City Engineer DATE: November 21, 1994 SUBJECT: Consider contract for Geotechnical investigation and recommended remedial repairs for the settlement on Wicks Road. BACKGROUND On September 23,1994 the Engineering Department was made aware of some apparent new cracks along the southerly shoulder of Wicks Road. On September 24th Engineering staff, along with their consultant Geologist, investigated the cracks and pot -holed to determine if the cracks were of a superficial nature or could potentially pose a threat to the sweet: or adjacent property. It was initially suspected that perh might be contributing to the cracks. The contacted and the street was pot -holed to five feet (the depth of the water Line), to extend the full depth of the pct -holes line leak was evident. aps a leaking water line Water District was a depth of approximately The cracks were observed No evidence of a water Both the City Engineer and the Consultant Geologist, Slosson and Associates, share the same opinion that recent settlement has taken place and that further investigation is necessary to determine the cause and extent of the settlement along with the remedial measures. Settlement monuments were immediately installed so that future movement could be monitored. An earthen berm was placed along the shoulder to redirect water from the shoulder and residents below were informed of the situation and possible hazards should the settlement, continue. The settlement monuments have been monitored and -o ()bservable movement has taken place. DISCUSSION Engineering solicited proposals from three geotechnical to perform both an Engineering Geology and a Geotechnical Engineering investigation of the extent of the distress and develop a solution. We received proposals3 from Slosson and Associates, A.G.I. Geotechnical Tnc , and Geolabs. firms to 00077 The costs of each proposal are shown below: GEOTECHNICAL FIRM COST Slosson 532,017.30 AGI Geolabs >4,'750 Both the Slosson and the AGI proposals are similar in nature and propose to perform borings and tesr_ pits for the purpose of gathering both geotechnical and geological information. Along with this they would review existing geological and topographical maps and studies to determine if a landslide might be contributing to the distress. The proposal from Geolabs does not include a geological evaluation. The end product of each proposal would be a determination as to the cause of the distress and recommended courses of repair. An underlying landslide cannot be ruled out until a geological investigation has been performed. This information is important to the Geotechnical Engineer in his design and may influence the scope and limits of the repair. F'-)r this reason only AGI and Slosson should be considered for t -;is con*.ract. Engineering contacted AGI to confirm their proposal. AGI confirmed their price and indicated that they will work with the City to develop a permanent solutiDn or alternative remedial repair measures should a more costly permanent repair be prohibitive to the City. 000"78