SUBJECT: Consider Appropriation for Construction
of office Space.
Background
At the City Council meeting of March 16, 1994, staff requested an
appropriation for a temporary office building to be located north
of City Hall. Staff recommended deferral of the item to allow
review of other options. The City Council was concerned that the
investment of almost $200,000 for temporary office space could be
better utilized as part of a permanent solution for additional
office space. Staff was directed to prepare estimates for the
construction of expanded office space.
Over the last three weeks, staff has received rough estimates from
various contractors as well as, interviewed three architects
regarding potential costs for a site plan and development of a City
Hall facility. It has been the position of the City Council that
City Hall be located in the downtown area. All options have been
developed with this desire in mind.
Staff met with the Budget and Finance Committee on April 13, 1994,
to discuss the options available to the City. The recommendations
contained in this report conform to the Committee's position.
Current Office Space
The City currently has approximately 7,600 sq. ft. of office space
which includes the City Hall building, Annex (trailer), and
Conference Room which is attached to the Community Center. Other
offices are located in the Community Center and Senior Center for
the Operations and Maintenance Supervisor and Senior Coordinator
respectively. One of the Recreation Supervisor positions will be
housed at the AVCP Recreation Center.
Presently, record storage is not adequate and many records are
stored off -site. There is no electricity, environmental control,
or lights, where the records are currently stored, which makes
retrieval of documents difficult: and could compromise the condition
of the records.
The configuration of offices in City Hall and the Annex have been
laid out incrementally, as staff has been added by using movable
partitions. The use of partitions has been extensive in the City
Hall building. Originally, the building was designed for nineteen
work areas, including eight enclosed offices, a copy room, computer
room, and eleven work areas in the central floor area. Today, we
have twenty work areas in the central area, (instead of eleven) and
nine work areas (instead of eight) in the enclosed areas. There
has been similar congestion in the Annex. In addition to twelve
work areas, all of the flat plans are being stored in the Annex.
There is also a small meeting room which doubles as a work area for
visiting auditors for various periods throughout the year.
Future Office Needs
As noted, if the City's staff size did not grow at all, the current
City Hall and Annex would marginally accommodate all personnel.
There would however be a need for 1,000 sq. ft for adequate record
storage and an area for researching records. Additionally, the
City does not have a functional Emergency Operation Center (EOC)
where emergency activities can be coordinated separate from the
day -to -day activities of the City.
Consideration has been given to possibly expanding the Finance
division by another three positions by 1996, as well as providing
building and safety and engineering services at the same location
as City Hall. The provision of a police community service office
was also part of the original plan of City Hall.
These unmet needs are significant, and there may be future needs
which are unknown. Federal and state programs frequently require
local government implementation or regulation and could force the
City to add staff. For example, in the past such mandates as AB939
Solid Waste Reduction Requirements necessitated the hiring of an
additional Management Analyst.
On -site Option
It appears there are several alternatives when considering an
expansion for additional office space. First, either the expansion
should remain on the current site, or go off -site. If City Hall
remains on -site, it could either be a new stand alone City Hall or
an expansion of the existing building. If it is to be a stand
alone City Hall, the Annex could remain where it currently is and
be used as a meeting or classroom facility or moved for another
use, such as public works and parks maintenance. The current City
Hall could be used as a teen center or other use.
The stand alone City Hall could be built on the north end of the
property or on the southwest corner. All of the architects agree
that the property is very small for intense use, and irregularly
shaped in relation to existing building location and topography,
therefore, the building would have to be two or three stories high.
It would also require an additional sixty -seven (67) parking spaces
based on a 20,000 sq. ft. building with parking at one space per
300 sq. ft. A stand alone City Hall. on -site or off -site has the
advantage of not interrupting current operations during
construction unless the Annex has to be moved. It is estimated
that moving the Annex would cost $25,000..
The $25,000 would include the following:
A) $15,000 for moving the structure;
B) $5,000 for preparation of the new site and clean -up of
the old site; and,
C) $5,000 for moving office furnishings and equipment.
The construction cost of a new City Hall could be from $120 to $175
per sq. ft., exclusive of land costs, and depending upon site
preparation, construction material, and electrical wiring. The
parking solution on this site could also add a great deal to the
costs. For budget purposes, it is estimated that the total cost of
the project could be as high as 3,15 to 4 million dollars.
On -site Expansion of City Hall
If this option is selected, the current building can be expanded to
the east or the northeast, without requiring the relocation of the
Annex. If the building is expanded to the north, the $25,000 cost
of relocating the Annex would apply. The construction costs would
be reduced by 33 percent if the current City Hall is expanded to be
between 2.3 to 2.5 million dollars.
The Budget and Finance committee favored the development of a new
City Hall building in the southwest corner of the Civic Center
property, if the decision is made to stay on -site. The use of the
current City Hall as a teen or recreation center of some kind and
use of the Annex as an additional classroom or meeting room was
viewed as a desirable alternative
Remaining on -site may not be the best option because of the space
limitation for construction and parking. There is also a conflict
in the southwest corner with additional space required for library
expansion and library parking, which uses all of the remaining site
except the northwest section of the property north of City Hall.
City Hall Off -site
Building a City Hall off -site would also allow the use of the
current City Hall and the Annex as a teen center and meeting rooms
and /or other uses. It would however add land costs. A 20,000 sq.
ft. facility could be constructed on a one acre parcel providing an
appropriate landscaping buffer, parking in excess of the base
requirements, and space for building expansion in case additional
services or functions are added over the next decade. Land costs
are estimated between $8 to $14 per sq. ft., thereby increasing the
costs of a new City Hall by $610,000.
Off -site Leasing or Purchase of Additional Office Space
All of the local commercial centers have been contacted. Full -
service leases run between $1.00 to $1.86 per sq. ft. per month.
Only one office building has been identified at this time with
14,000 sq. ft. available. The rest have less than 5,000 sq. ft.
available.
The Redevelopment Agency has two 1,800 sq. ft. locations, but each
would require between $20,000 to $25,000 in renovation costs to be
useable (VCMC building /Santa Barbara Savings building). Use of
these sites would allow a delay in the construction of a new or
expanded facility. However, it has the disadvantage of not having
all City offices at one location. This use should only be on an
interim basis for this reason. Use could also be coordinated with
an expanded service such as the proposed store front police
operation and provide access throughout the normal business day for
the public.
The Budget and Finance Committee viewed the lease of these
properties as temporary solutions
The purchase of a facility was however considered a viable option,
if the purchase price presents a more cost effective solution and
Redevelopment /Economic Development, and other City goals can be met
as well.
Architects' Proposals
Staff interviewed several architectural firms to receive their
input regarding a project of this size. The estimated costs for
their services range from $5,000 to $30,000 depending upon the
scope. Essentially, they recommend preparation of a site master
plan, programming future office requirements of the City,
preparation of alternatives, and finally, development of the master
plan.
4
Interim Solution for an Emergency OReration Center (EOC)
In order to meet the immediate need for an EOC, staff and the
Budget and Finance Committee recommend modification of the Citrus
Room. We have already ordered a storage bin for emergency supplies
which can be placed behind the Community Center. The main phone
panel is also located near the Citrus Room in the Community Center,
which will reduce the cost of installing dedicated phone lines.
Cabinets for storage of additional supplies can be added to the
room to make it more functional. The cabinets can be used for
general storage when the EOC is relocated.
summary
The expansion of City Hall or construction of a new facility either
on -site or off -site requires immediate steps to meet the current
needs of the City. The steps include:
A) The modification of the Citrus Room for use as an EOC;
and,
B) Further investigation of on -site and off -site options and
costs.
Recommendation
Staff and the Budget and Finance Committee recommend that the City
Council take the following actions:
1) Authorize modification to the Citrus Room for use as an
EOC using the funds currently available in Administrative
Services (01.4.117.629);
2) Assign the Budget and Finance Committee to investigate
the financial and budget impacts of constructing, leasing
or buying required office space; and,
3) Appropriate $2,500 from the General Fund to
Administrative Services for professional services
(01.4.117.641) related to the investigation of the
alternatives noted above