HomeMy WebLinkAboutAGENDA REPORT 1995 0719 CC REG ITEM 11BTO:
FROM:
DATE:
SUBJECT:
i " .A 10 LI
Ag�rida Report
City of Moorpark
The Honorable City Council
Kenneth C. Gilbert., Director of Public Works
July 7, 1995 (Council. Meeting 7- 19 -95)
Consider Approval of the Conceptual Design for the
Reconstruction of the Spring Road Bridge
On September 21, 1994, the City Council selected the firm of
Dwight French and Associates to prepare the design plans and
specifications for the replacement of the Spring Road Bridge
across the Arroyo Simi,
A. Design Phases
The contract for design services structures those services
to provide for the evolution of the design using certain
review benchmarks summarized as follows:
• Conceptual Design:
- initial hydrology analysis,
- initial geotechnical analysis,
- survey,
- right -of -way needs,
- utility relocation requirements,
- bridge length, width & other design elements,
- interface with future trail system,
- Preliminary plan / profile,
- bridge alignment,
- road closure analysis,
- preliminary construction cost estimate.
sprgbrg8 0001019
Spring Road Bridge Design
July 1995
Page 2
Preliminary Design:
- final hydrology analysis,
- final geotechnical and seismic analysis,
- bridge widening costs (grant data),
- final design for bridge alignment, length, width,
approaches & other project elements;
- final right -of -way requirements,
- final utility relocation requirements,
- draft construction staging & traffic control plan,
- estimate of probable construction cost.
Draft Final Design:
- final r -o -w needs (legal descriptions, etc.),
- final draft design plans and specifications,
- final construction staging & traffic control plan,
- final roadway approach design plans
- final striping plans,
- final bid items and estimated quantities.
Construction Documents:
- final plans and specifications
B. Conceptual Design
The engineer has completed the conceptual design. A copy
of a report summarizing that work product has been placed
in the City Council office for your review.
C. Environmental Review
Based on the above mentioned report summarizing the
conceptual design, staff will proceed with the preparation
of the Environmental Assessment and Environmental document
for this project. If necessary, the completion of the
this environmental document will be deferred until the
completion of the Preliminary design phase. It is
anticipated that the environmental document which will be
required, will be a Mitigated Negative Declaration.
D. Bridge Width
On June 21, 1995, the City Council approved a change to
the design width for the new bridge from sixty feet (601)
to fifty feet (501). This bridge width is compatible with
the design width for Spring Road south of the bridge which
has been approved for construction by the developer of the
proposed Carlsberg project.
9prgbrg8
00011-0
Spring Road
July 1995
Page 3
E. Alignment
Bridge Design
One of the matters to be determined at this point in the
design process is the alignment of the new bridge
structure. The Engineer's report identifies two alternate
summarized as follows:
Alternate #1: Placement of the centerline of the
bridge at the centerline of the street right -of -way.
Pros:
• Allows use of more of the existing paving, thus
reducing the cost for street widening and
realignment.
• Required closure of Spring Road (see below)
reduces construction time and cost.
• Street curvature (see below) should have the
effect of reducing speeds.
• Shorter construction time (approximately 6
months)..
Cons:
• Requires the complete removal of the existing
bridge and the closure of Spring Road.
• Curvature of street aliqnment north of the
bridge remains.
Alternate 12: Curb at northeast corner of the bridge
to align to the existing curb on the east side of the
street north of the bridge.
Pros:
• Allows existing bridge to be used for one lane
of traffic (signalized to allow only one
direction at a time) during construction.
• Curvature of the street. north of the bridge is
reduced.
Cons:
• Will require the relocation (possible right -of-
way acquisition) and reconstruction of the
utility access road serving the pump station
owned by the Calleguas Municipal Water District.
• Will require the developer to the southeast
(Carlsberg) to construct additional fill slope
and /or retaining walls.
• Increased cost (approximately $160,000) and
construction time due to these additional
construction requirements.
•
Longer construction time (approximately 8
months).
sprgbrge
0009.1.1
Spring Road Bridge Design
July 1995
Page 4
Four Lanes: With either alternate, the widening of
only one side of the proposed bridge will accommodate
four lanes of traffic.
Curve South of Bridge: The Engineer has evaluated the
existing curve and grade south of the bridge for the
purpose of determining if any improvements to this
curve could be undertaken at the time the bridge was
reconstructed. "Softening" this curve would require
the radius of the curve to be lengthen. This would
move the roadway to the east. Moving the roadway to
the east would require one or all of the following: a)
the relocation of the existing water pump station,
b) the import of substantial fill material, and c) the
construction of a substantial amount of retaining
walls. It is the opinion of the Engineer that the
benefits derived do not justify the substantial costs
of these additional improvements.
F. Road Closure
Absent the construction of a temporary bridge, the only
way in which traffic can be maintained during construction
will be to select the bridge alignment described in
Alternate #2 above. However, even with this Alternate it
will be necessary to remove a portion of the existing
bridge reducing the width to only one lane.
1. One -Way Only: Traffic could be restricted to one
direction only. If it is likely that construction
activities would cause periodic closures, it may be
preferable to designate the bridge for north bound
traffic only due to the fact that there is limited
vehicle storage for southbound traffic between the
bridge and Los Angeles Avenue.
2. Two -Way Traffic: Two way traffic could be maintained
on a one lane bridge through the installation of a
demand - actuated temporary traffic signal which would
allow only one direction of traffic to flow at time.
It should be noted that there has been no traffic study
performed to determine the degree of traffic congestion
which would result from this installation, nor the
amount of vehicle storage which would be required north
of the bridge.
sprgbrge ��
Spring Road Bridge Design
July 1995
Page 5
G. construction Cost Estimate
The preliminary construction cost estimate for the project
is as follows:
Alternate 11: $1,285,000
Alternate 12: $1,440,000
Note: These costs are based on the preliminary
recommended design which calls for a three -span
bridge. Should the seismic analysis indicate
the construction of a single span bridge, the
cost estimate will be revised upward.
H. Trails
Due to the fact that the bridge does not cross the arroyo
at a right angle, the design length for the new bridge is
one hundred forty -six feet (1461). This is the minimum
length necessary to accommodate the proposed one hundred
twenty -five feet (125' ) width for the bottom of the future
channel to be constructed by the Ventura County Flood
Control District (VCFCD). This proposed bridge length
will require the construction of vertical channel walls
under the bridge. With this design it will not be
possible to construct a future levy trail which would dip
under the bridge structure. Any future trail system would
have to cross Spring Road at grade.
In order to accommodate a future levy trail which could be
constructed under the bridge, it would be necessary to
lengthen the bridge span by approximately eight feet (81).
It is anticipated that this additional bridge length would
increase the above mentioned estimated construction costs
by approximately $50,000.
1. Survey: Completed.
2. Right -of -Way Acquisition: None required for bridge.
Some may be required for utility access road
relocation.
3. Utility Relocation: Scope to be determined.
sprgbrge
�,3
Spring Road Bridge Design
July 1995
Page 6
4. Geotechnical Analysis: '2ompleted. Seismic safety
analysis to be performed..
5. Hydrology Analysis: Initial information obtained from
VCFCD. Final hydrology analysis to be performed after
bridge alignment and design is determined.
6. Alignment: It is recommended that design Alternate #1
(bridge at centerline of street) be selected.
7. Road Closure: It is recommended that the Spring Road
be closed during construction.
8. Trails: It recommended that the bridge length be
increase to accommodate possible future trials under
the bridge.
Staff recommends that the City Council take the following
actions:
1. Approve the bridge alignment described by Alternate #1
(bridge to be located at the centerline of the street).
2. Approve the closure of Spring Road during construction.
3. Approve a bridge length which will accommodate the future
construction of a trail under the bridge.
4. Approve the conceptual design for the subject project
based on the Conclusions stated M this report.
sprgbrgs
0001.1.4