SUBJECT: Consider Award of Contract for the Installation of a
Pump and Related Equipment for Water Well #3 at Arroyo
Vista Community Park.
BACKGROUND
1. The property conveyed to the City by Urban West Communities for
Arroyo Vista Community Park included two existing water wells
used in the past to supply irrigation water to the agricultural
uses on the property. Although the water extracted from these
wells is high in Boron and thus not suitable for drinking, it
was determined that this ground water could be used to provide
irrigation water to the park. The design for the park called
for the construction of an irrigation system supplied by these
wells.
2 . These water wells were in excess of forty (40) years old.
Accordingly, the City Council authorized staff to proceed with
a water well rehabilitation program which included the
following improvements:
- the removal, inspection and evaluation of Water Well #2;
- based on that analysis, it was decided to replace Well #2
rather than attempt to rehabilitate it;
- the destruction and capping of water well #2;
- the replacement of the pump motor for Well #1 with a new 40
HP submersible pump;
- the preparation of a design and the award of a construction
contract for the drilling of a new Well #3;
- the subject project to install the pump, piping and related
equipment required to make Well #3 operational.
3 . In December of 1994 the City Council accepted the improvements
and authorized the recordation of a Notice of Completion for
the drilling of Water Well #3 at Arroyo Vista Community Park.
4 . In September of 1995 the City Council approved the plans and
specifications for the subject follow-up project to install the
well pump and related equipment. Upon completion of the
subject project, the water well rehabilitation program will be
completed.
avpwel7.awd 000055
9�-io3
Arroyo Vista Community Park Well #3
December 1995
Page 2
DISCUSSION
A. Purpose
The primary purpose for using the on-site water wells is cost
effectiveness. A comparison of the estimated cost of well
water and domestic water is summarized as follows:
Domestic Water City Water
Description Service Costs ($) Well Costs ($)
Calleguas Municipal Water 70,000 0
District Connection Fees
Water Works District #1 19,000 0
Capital Connection fees
Water meter installation 1,500 0
charges
Water usage per year 30,000 1,000
Phase I (33 acres)
Water usage per year 60,000 2,000
Total Park (69 acres)
Water well maintenance 0 1,000
and operation (electrical
energy, oil, etc. )
B. Design
A summary of the elements included in the subject project
design is as follows:
1. Location: See map attached as Exhibit 'A. '
2. Pump Motor: 40 HP submersible pump motor.
3 . Piping: Pipes, valves, gauges and related equipment
required to connect Well #3 to the exiting irrigation system
controls at Well #1.
4. Electrical Service: An electrical meter, control panel,
underground conduits and related equipment.
5. Electrical Controls: A sub-panel, underground conduits and
related equipment required to operate the new well from the
existing control system at Well #1.
avpwel7.awd 000050
Arroyo Vista Community Park Well #3
December 1995
Page 3
C. Bid Results
Bids for the subject project were received and opened on
December 5, 1995. A tabulation of the bid results is attached
as Exhibit 'B' .
D. Qualifications
It has been determined that the apparent low bidder, Clearwater
Constructors, is qualified to construct the subject project.
Said bidder has confirmed that their bid is valid and that they
are prepared to proceed with the construction of the project.
E. Fiscal Impact
1. Total Project Cost Estimate: A summary of the total cost
for both the well drilling project and the subject project
for the installation of the pump and related equipment, is
as follows:
Element Prior Years ($) FY 1995/96 ($1 Total ($1
Well Drilling Project
Design 17,000 17,000
Construction 42,800 42,800
Inspection 13,620 13,620
Sub-Total 73,420 0 73,420
Subject Pump Installation
& Hook-up Project
Design 6,200 700 6,900
Construction 38,165 38,165
Constr. Contingency (10%) 3,815 3,815
Inspection 6,320 6,32Q
Sub-Total 6,200 49,000 55,200
Total 79,620 49,000 128,620
3 . Budget: The approved FY 1995/96 Budget [05-400-903-0115]
for this element of Arroyo Vista Community Park Improvements
is $56,000.
avpwel7.awd
000057
,
Arroyo Vista Community Park Well #3
December 1995
Page 4
F. Schedule
It is anticipated that construction of the subject project will
begin in January and be completed in February.
RECOMMENDATION
Staff recommends that the City Council take the following actions:
1. Award a contract to Clearwater Constructors in the amount of
$38,165.00, for the construction of the subject project;
2. Approve a ten per cent contingency for the project and
authorize the City Manager to approve additional work, if
required, for an amount not to exceed ten per cent of the
contract; and,
3. Authorize the Mayor to sign necessary contract documents.
00005E
avpwel7.awd
•
7CONSTRUCTION
WATR SUPPLY
•
•
(tire hydrant)
ep\11°
F •oo I
�O(O G'� PARK doll s
... airy AR Y
■u •C� nr ";11 "•� '.
f 211
w....wrwr.r I I I 1 1• .S IeERr./l • t rte`
. wr rrrr
1` )..RK , a t FIII I I
,BASEBALL r_� t It II
1r, .. .
•
A c i -- O r BASEBALL BASEBALL 1 I I /
,i ��i _ 1 `-"'' r, `DIAb3 D D SEBIAD i
Ess -� .(;J`,
'---4 I/4 as 9C4ktt"'-
Ida
(active)
�K poijl�0 PARK WELL No.1
P
•
PARK WELL No.2 WELL NO. 3
Arroyo Vista Community Park
i
C
C NORTH
C
NOT TO SCALE �y�
c^ SITE PLAN �1,
1
I.
r
Exhibit 1
CITY OF MOORPARK Bidder VENDOR 1 VENDOR 2 VENDOR 3 VENDOR 4
Bid Results
NAME: Clearwater Constructors ARA Engineering Contrac Turf Construcion
AVCP Well #3 ADDRESS: Engineer's Estimate 2646 Palma Dr. #160 6910 Oran Circle 1535 Flynn Rd
PUMP CITY, STATE: Ventura, CA 93003 Buena Park, CA 90621 Camarillo, CA 93012
PHONE NUMBER: (805) 650-2520 (714) 521-9061 (805) 432-9876
December 5, 1995 CONTACT PERSON: Mark Buchanon Ali Yazdanshenas Robert Taylor
ITEM DESCRIPTION Est Qty Units UNIT $ TOTAL BID UNIT $ TOTAL BID UNIT $ TOTAL BID UNIT $ TOTAL BID UNIT $ TOTAL BID
1 Mobilization 1 LS 2,000 2,000.00 3,720.00 3,720.00 15000 15,000.00 1000 1,000.00 0.00
2 Piping 1 LS 18,000 18,000.00 19,666.00 19,666.00 12900 12,900.00 28655 28,655.00 0.00
3 Mechanical Equip. 1 LS 18,000 18,000.00 5748.00 5,748.00 15000 15,000.00 10000 10,000.00 0.00
4 Electrical Service 1 LS 15,000 15,000.00 3795.00 3,795.00 3000 3,000.00 5350 5,350.00 0.00
5 Electrical Controls 1 LS 10,000 10,000.00 4215.00 4,215.00 2500 2,500.00 11600 11,600.00 0.00
5b Protective Coating 1 LS 1 1.00 1,020.00 1,020.00 500 500.00 500 500.00 0.00
6 Release 1 LS 1 1.00 1.00 1.00 1 1.00 1 1.00 0.00
g!
5
ir
Total 63,002.00 38,165.00 48,901.00 57,106.00 0.00 -