TO: The Honorable City Council 4 _
FROM: Kenneth C. Gilbert, Director of Public Works .� �,,,�'�,
DATE: January 5, 1996 (Council Meeting 1-17-96)
SUBJECT: Consider Authorizing Recordation of the Notice of
Completion for Sidewalk Construction Project 95-1
DISCUSSION
A. Background
Last November the City Council awarded a contract for the
construction of sidewalks on Harry Street, Esther Street,
Sherman Avenue and High Street. That work is now completed.
B. Fiscal Impact
1. Total Construction Contract Costs: A summary of the final
costs to Kalban, Inc. for the sidewalk construction project
is as follows:
Description Costs ($)
Bid Amount 52 ,534
Quantity Adjustments 2,782
Change Order #1 6,337
Change Order #2 2,565
Total 64,218
a. Change Order #1 ($6,337) : Addition sidewalks on High
Street and a net reduction in the total amount of root
barriers required for the project.
b. Change Order #2 ($2,565) : Kalban was retained to
construct a yard drain on property located at the
northeast corner of High Street and Bard Street. [Note: This
work was required by (and funded by) the Street Reconstruction Project. Kalban was selected
to perform the work because their bid was much lower than the amount quoted by the contractor
for the Street Reconstruction Project.]
2. Total Sidewalk Project Construction Costs: A summary of the
total cost for the subject contract is as follows:
Description Costs ($)
Total Construction Contract 64,218
Less Street Reconstruction (2,565)
Net Sidewalk Contract Construction Cost 61,653
sher.cmp 000055
Sidewalk Construction
January 1996
Page 2
3. Total Project Construction Costs: In addition to actual
sidewalk construction contract costs, the City incurred a
number of other construction related costs. All of these
costs, including the Kalban contract are summarized as
follows:
Description Vendor Costs ($)
Construction Contract Kalban, Inc. 61,653
Misc. Concrete Work Quigley 1,025
Tree Removal Bob's Tree Service 6,100
Other Removals Simi Valley Base 110
Equipment Rental Baker's 520
Misc. Materials Whitaker's 9
Misc. Materials Accurate Welding 10
In House Labor * City $2,000
Sub-Total $71,427
Future Additional Sidewalk Work 8,573
Total $80,000
Note: * 100 hours @ $20.00 / hr.
3. Total Project Costs: A summary of total project costs is
summarized as follows:
Description Costs ($)
Design 0
Misc. (Printing, etc. ) 300
Construction 80,000
Contract Administration & Inspection 5,995
Total 86,295
4. SB-821 Grant: The City is in receipt of an SB-821 grant in
the amount of $40,000 to fund one-half of the construction
cost for the subject project.
5. Budget: A comparison of budgeted and actual expenses for
the project is as follows:
Funding Source Budget Actual
Grant: 15-142-903-0325 40,000 40,000
MRA: 01-170-903-0325 60,000 46,295
Total $100,000 $86,295
No Budget Amendments are recommended.
sher.cmp 000050
.
Sidewalk Construction
January 1996
Page 3
RECOMMENDATION
Staff recommends that the City Council take the following actions:
1. Accept the work as completed, subject to satisfactory
completion of the maintenance period.
2. Instruct the City Clerk to file the Notice of Completion for
the project.
3 . Authorize the release of the retention upon satisfactory
clearance of the thirty five (35) day lien period.
sher,cmp