HomeMy WebLinkAboutAGENDA REPORT 1996 0207 CC REG ITEM 07CTO: FROM: DATE: SUBJECT: DISCUSSION AGENDA REPORT C Z Z'Y OF MOORPARK The Honorable City Council Kenneth C. Gilbert, Director of Public Works Y January 29, 1996 (Council Meeting 2 -7 -96) Consider Bids for the Construction of a Temporary Traffic Signal at the Intersection of Tierra Rejada Road and Moorpark Road A. Backaround On December 6, 1995, the City Council approved the plans and specifications for the subject project and authorized staff to advertise for bids. The purpose of this project is to address traffic congestion on the south leg of the intersection. It is understood that the County of Ventura is proceeding with a project for the reconstruction and realignment of Moorpark Road. If the ultimate road alignment for this project causes the intersection with Tierra Rejada Road to be relocated to the west, the subject traffic signal will be removed. The project design calls for the installation of traffic detector loops for north bound traffic and for west -to -south left turn traffic. The project also calls for the installation of a left -turn GREEN ARROW for west -to -south left turn traffic and a right -turn GREEN ARROW for north -to -east right turn traffic. C. Signal Controller The traffic signal controller has already been purchased by the City and is not a part of the subject contract. The County of Ventura has agreed to acquire this traffic signal controller when and if the subject traffic signal is removed. They have agreed to pay the City an amount equal to ninety percent (90%) of the actual purchase price of $5,778. D. Cooperative Agreement The County of Ventura has also agreed the cost of this traffic signal. A pertaining to this sharing of costs is City Council as a separate item. mpk_tk4 . aYd to pay for one -third of Cooperative Agreement to be presented to the U3UU43 96 -ad ITEM7 C• Acf;" N: Kenneth C. Gilbert, Director of Public Works Y January 29, 1996 (Council Meeting 2 -7 -96) Consider Bids for the Construction of a Temporary Traffic Signal at the Intersection of Tierra Rejada Road and Moorpark Road A. Backaround On December 6, 1995, the City Council approved the plans and specifications for the subject project and authorized staff to advertise for bids. The purpose of this project is to address traffic congestion on the south leg of the intersection. It is understood that the County of Ventura is proceeding with a project for the reconstruction and realignment of Moorpark Road. If the ultimate road alignment for this project causes the intersection with Tierra Rejada Road to be relocated to the west, the subject traffic signal will be removed. The project design calls for the installation of traffic detector loops for north bound traffic and for west -to -south left turn traffic. The project also calls for the installation of a left -turn GREEN ARROW for west -to -south left turn traffic and a right -turn GREEN ARROW for north -to -east right turn traffic. C. Signal Controller The traffic signal controller has already been purchased by the City and is not a part of the subject contract. The County of Ventura has agreed to acquire this traffic signal controller when and if the subject traffic signal is removed. They have agreed to pay the City an amount equal to ninety percent (90%) of the actual purchase price of $5,778. D. Cooperative Agreement The County of Ventura has also agreed the cost of this traffic signal. A pertaining to this sharing of costs is City Council as a separate item. mpk_tk4 . aYd to pay for one -third of Cooperative Agreement to be presented to the U3UU43 96 -ad Traffic Signal @ Moorpark Rd & Tierra Rejada Rd January 1996 Page 2 Bids for this project were received and opened on January 29, 1996. A summary of the bids received is as follows: Bidder Amount ($) Engineer's Estimate 27,000 TDS Engineering 25,994 Taft Electric 29,991 Cameron Webster Construction 30,795 Comet Electric 33,501 ON941", .. It has been determined that the apparent low bidder, TDS Engineering, is qualified to perform the work. Said bidder has confirmed their bid and their desire to proceed with the construction of the project. E. Fiscal Impact 1. Total Project Cost Estimate: An estimate of the total project cost is as follows: Estimated Element Cost (S) • Design 4,040 • Printing, Advertising, etc. 500 • Traffic Signal Controller 5,778 • Construction 25,995 • Construction Contingency (10 %) 2,687 • Admin & Inspection 3,000 Total 42,000 2. Participation by the County of Ventura: The County of Ventura has tentatively agreed to fund one -third (A) of the cost of the project. It is anticipated that, with the assistance of Supervisor Mikels' office, the Board of Supervisors will approve the Cooperative Agreement for this funding at their meeting scheduled later this month. a) The estimated amount of the County's share of project cost is as follows: Element • Total Estimated Cost • Less controller costs sub -total • County share (,A of 36,222) • Signal controller Total apk_tr4. swd Estimated 42,000 5,7791 36,222 12,074 ** 5,200 17,274 ** $5,778 x 0.9 = $5,200 000044 Traffic Signal @ Moorpark Rd & Tierra Rejada Rd January 1996 Page 3 b) Net Cost to the City is as follows: Estimated Element Cost fS • Total Estimated Cost 42,000 • Less County Share (12,074) sub -total 29,926 • Less future reimbursement for traffic signal controller (5,200) Total 24,726 3. Budget Background: Last July the City Council approved an appropriation and budget amendment for the subject project in the amount of $70,000 (26- 142 - 903 - 0413), to be funded by a loan from the Gas Tax fund to the Tierra Rejada Road/ Spring Road AOC. That action was based on an assumption that the amount which would be received in the future from the County of Ventura for the traffic signal controller, would be approximately $35,000, leaving a net cost to the City of $35,000. A summary of the budget amendment required reflect these revised assumptions is as follows: Current Current Budget 70,000 (28,000) 42,000 Less County Participation 0 (12,074) (12,074} Net City Costs 70,000 (40,074) 29,926 Less future refund fro& the (35,000) 28,800 (5,200) County of Ventura for the signal controller Net cost to the City 35,000 (10,274) 24,726 4. Summary: It is recommended that the amount budgeted for this project for FY 1995/95 Budget be reduced to the current total project cost estimate of $42,000. As discussed above, it is anticipated that a portion of these costs are to be off -set by a contribution from the County of Ventura. In the event this County funding is not approved, the total project costs ( less the future reimbursement for the traffic signal controller) would be borne by the City. *Pk- tra.AW 000045 Traffic Signal @ Moorpark Rd & Tierra Rejada Rd January 1996 Page 4 RECO RMDEED ACTIONS Staff recommends that the City Council take the following actions: 1) Award a contract to TDS Engineering, Inc. in the amount of $25,995.00 for the subject project; 2 ) approve a ten per cent contingency for the project and authorize the City Manager to approve additional work, if required, for an amount not to exceed ten per cent of the contract; and, 3) Authorize the City Manager to sign necessary contract documents. 4) Amend the total amount of the appropriation and budget for this project as follows: Acc. # 026 - 142 -903 -0413: from $70,000 to $42,000 ($28,000 decrease). aplttt4. atr8 000046