Loading...
HomeMy WebLinkAboutAGENDA REPORT 1996 0619 CC REG ITEM 10HiTEM AGENDA REPORT C = TY OF MOORPARK TO: The Honorable City Council FROM: Kenneth C. Gilbert, Director of Public Works DATE: June 7, 1996 (Council Meeting 6- 19 -96) SUBJECT: Consider Approval of the City's Pavement System BACKGROUND Management In April 1995 the City Council authorized staff to proceed with the steps necessary to develop a Pavement Management System for the City. DISCUSSION A. Pavement Management Systems Public Works Departments can no longer afford to manage street pavement on a hit and miss basis or to merely wait to respond to complaints of pot holes. Proper street maintenance requires the use of a computerized program to assist in the performance of a number of tasks, including: 1) the gathering of data on the condition of all City streets; 2) the objective analysis of that data for the purpose of categorizing all City streets according to their condition and /or repairs needed; 3) the development of a street inventory pertaining to condition, width, traffic volume, etc.; and, 4) the listing of street resurfacing needs, in priority order by need or condition, for each street resurfacing program (reconstruction, overlay, patching, crack filling, slurry seal, etc.) This technique has been the "state of the art" for a number of years. It is used by most cities and counties as a tool in providing an objective analysis of street conditions for the purpose of developing street maintenance budgets and street repair recommendations. The Federal Intermodal Surface Transportation Efficiency Act ( ISTEA) recognizes the value of this tool and requires that all local agencies receiving ISTEA monies implement such a program by January 1997. The City has received approval of a Surface Transportation Program (STP) [an element of the ISTEA program] grant in the amount of $480,000, as partial funding for the 1995 Asphalt Overlay Project, and must, therefore, establish a Pavement Management System in order to comply with grant requirements. PME2 0 00 4c l Pavement Management System June 1996 Page 2 Absent these federal requirements, staff would still recommend the establishment of a Pavement Management System. Such a program offers many benefits. Of particular value is the ability to provide policy makers, as well as the general public, objective recommendations for street repair projects. If such a system had been in place in past years, the justification for certain staff recommended street resurfacing projects would have been more clearly stated. All of the street resurfacing needs of the City would be objectively evaluated, scored, ranked and prioritized. The projects recommended to the community and the City Council by staff would be presented in light of this comprehensive street resurfacing needs analysis. B. Contract The actions taken by the City Council in April 1995, included approval of the selection of Dwight French & Associates (DFA) to prepare a Pavement Management System for the City. The services which have and /or will be provided to the City by DFA include the following: 1. Program Description: • an inventory of street segments for the entire City (includes an analysis of every street in the City); • a description of a each segment; • a segment numbering system; • traffic data; • a condition survey; • unit costs for various repair methods; • a Pavement Condition Report; • street repair recommendations; • a seven -year street improvement plan; and, • Survey and Operations Manuals. 2. Program Maintenance: In order to protect the City's initial investment by assuring that the system is updated and maintained properly, DFA will provide the City with forms and procedures for the submittal to the City Manager, of Annual Compliance Reports confirming that these update tasks have been performed. 3. Training: As required by the contract, DFA provided some training to City staff on performing field investigations and pavement evaluations. C. Completed Program DFA has completed and delivered the draft Pavement Management System. A copy of the Executive Summary is attached as Exhibit 1. P=2 Pavement Management System June 1996 Page 3 D. Committee Review On May 28, 1996, John Whitman, of DFA, gave a presentation to the City Council Transportation and Streets Committee (Councilmembers Hunter and Brown) on the subject program. The Committee was given an opportunity to review hard copies of the work product (charts and maps), plus witness the operations of the associated computer software. The Committee was quite impressed and requested that some form of that presentation be made to the full City Council. E. Presentation Mr. John Whitman of DFA will be present to give a brief presentation to the City Council on the Pavement Management System. Various maps produced by the program will be available. In addition, demonstrations of the computer program will be given to those interested during a break or at other convenient times. If possible an interface between the computer program and the community telecast will be established to allow the viewing public to see some of the cap[ability of this program. F. Future Program Updates 1. Pavement Evaluations: The above mentioned training demonstrated that the art and science of pavement evaluation is very technical in nature. It is a skill which must be used on a regular basis if is to be developed to a useful level of consistency required to yield comparable results. For these reasons it is not recommended that the City attempt to undertake the future field inspections and pavement evaluations required to maintain and update the pavement condition inventory. Rather, it is recommended that the City utilize DFA, or another qualified firm, to periodically provide these services. 2. Database: The data gathering and analysis elements of this program uses dBase software. All future revisions and /or entries to the data base, such as the addition of new street segments or a change in the street condition (e.g. slurry seal applied) will be performed by City Public Works personnel. 3. Mapping: The mapping element of the program utilizes AutoCad software. When it becomes necessary to add new street segments to the program, it is recommended that the City retain the services of DFA, or another qualified firm, to update the AutoCad program. It is the intent of staff to develop a recommended developer fee designed to recover these costs, and to have the work performed as a part of reviewing as -built plans prepared by developers. In the rare instance where a new street is added by a City project, the map revisions would be a part of the construction engineering. pm ®Z 000463 Pavement Management System June 1996 Page 4 G. Inventories The layout and format of the database used for the pavement condition inventory has been structured to be compatible with the development of a Public Works Inventory. It is the intent of staff to develop, with the assistance of DFA, a number of such inventories for a number of areas, to possibly include some or all of the following: • Speed zones (speed limit signs) • STOP signs • Other Traffic Regulatory Signs • Striping and Markings • Pavement repair history • Street trees • Bus routes, signs, benches, shelters, etc. • Street Sweeping Parking Restriction signs • Truck Routes, signs etc. H. Fiscal Impact 1. Initial Set -up Costs: The costs the City has or will incur for DFA to establish the subject program is $39,990. 2. Update Costs: In order to properly utilize and maintain this program it is recommended that certain elements of the program be updated on an annual, bi- annual and five -year basis. The average annual cost for these services is approximately $4,000. 3. Inventories: DFA costs to assist in the development of the dBase templates for a number of Public Works inventories is estimated to cost less than $500. 4. Special Mapping Services: DFA costs to provide special mapping services (Speed Zone Map, etc.) to the City could range from $500 to $2,000. 5. Budget: Any of the above mentioned costs incurred in FY 1996/97 or subsequent years will be charged to the line item budget provided for Engineering studies (03- 142 -641). RECOMMENDATION Staff recommends that the City Council approve the subject Pavement Management System. Attachments PM92 000464 fy1�.yr i The City of Moorpark has responsibility for maintenance and rehabilitation of approximately 81.5 miles of streets throughout the City. The total replacement value of this street system is estimated to be more than $65 million, including curb, gutter and sidewalk. To assist in meeting that responsibility, the City is using a computerized approach to examine funding policies and to develop a Street Rehabilitation /Overlay Program. This approach uses the City's new Pavement Management System (PMS). This new PMS is composed of the following major elements. • A complete field inventory of all city streets, which recorded data for street dimensions, as well as street conditions. • A determination of the rehabilitation needs for each street based on its physical conditions. • A prioritization of each street rehabilitation program based on the traffic volume on the street, the construction cost of the recommended improvement and the amount of added life achieved by the improvement to each street. • Graphical as numerical presentation of street conditions, improvements and priorities. This approach assures the City that it will receive the maximum return on street rehabilitation expenditures. The PMS rates all streets in Moorpark and assigns a condition rating from 0 to 100 for each street segment. The range of conditions is as follow: EXCELLENT (90 - 100) The street surface has few very minor or no defects and rides like a new street. Generally, only minor routine maintenance is needed. pma*=028a.sum GOOD (80 - 89) The street has some surface defect which generally indicates the need for surface treatment. The street performs well with minor roughness and tire noise. FAIR (70 - 79) The street has cracking, settling and surface distortions, generally indicating the need for increasing surface treatment such as cape sealing, overlaying or slab replacement. There may be some noticeable roughness in ride quality. POOR (60 - 69) The street has major cracking, settling and surface distortions indicating the need to repair defects and provide additional pavement structure. There is noticeable roughness and tire noise. CRITICAL (0 - 59) The street no longer has structural integrity with missing paving material and rough ride characteristics. The street requires major rehabilitation and perhaps reconstruction. The current local street system conditions in Moorpark are as follows: Of course the street system in Moorpark deteriorates every day. Deterioration results from the following: • _ heavy traffic including trucks and buses; • the sun's rays hardening the asphalt; • other weather conditions including rain; 2 Percentage Miles of Street System EXCELLENT 47.3 58% GOOD 24.8 30% FAIR 4.5 6% POOR' 1.9 2% CRITICAL 2.9 4% 81.5 100% Of course the street system in Moorpark deteriorates every day. Deterioration results from the following: • _ heavy traffic including trucks and buses; • the sun's rays hardening the asphalt; • other weather conditions including rain; 2 • utility company operations which involve cutting the asphalt; and • other spot emergencies such as fires and chemical spills. Generally public works' professionals believe that a city street system should have the following spread of conditions. EXCELLENT 20-30% GOOD 30-50% FAIR 20-30% POOR 0% CRITICAL 0% Compared to this standard, Moorpark's street system is generally in better condition than a typical city street system. However, Moorpark should rehabilitate all poor and critical sections of streets. It is not necessarily the best policy for a city to rehabilitate all critical and poor sections of streets with available revenues, particularly if the projected revenue stream is not sufficient to cover all street rehabilitation needs. It is better to perform a cost benefit analysis to guide street prioritization because the cost of repairing a good street may be only $.07 - $10 per square foot, while the cost of repairing a critical street may be $2.50 - $4.00 per square foot. The following table shows the average cost of repair for one mile of Moorpark local streets by condition rating. A systematic approach can assure a city of wise street investment policies, allow decision making to include the benefits as well as costs of improvements and factor in the number of citizens using a specific street. AVERAGE ESTIMATED REPAIR/REHABILITATION COST PER MILE BY CONDITION RATING Average Repair Condition Cost Per Mile Critical $750,000 Poor $250,000 Fair $125,000 Good $85,000 Excellent $15,000 Rehabilitation strategies for Moorpark are defined as follows: ASPHALTIC CONCRETE STREETS Slurry Seal (SS) This low cost treatment consists of a mixture of liquid asphalt and sand which is spread on the existing surface. This treatment is intended to seal small cracks in the pavement and retards the destructive oxidation of the sun. This treatment has a life of 5 to 7 years. Thin (OL) This treatment consists of the application of up to 2 Overlay inches of asphalt hot mix to the existing structure. This treatment adds significant strength to the existing surface. A thin overlay has a life of approximately 10 years. Overlay with (OS) This treatment consists of placing a geotechnical Stress Relief fabric on the existing pavement to retard the existing cracks from reflecting through to the new surface. An asphalt concrete overlay is then applied on top of the fabric adding significant strength to the pavement structure. This treatment has a life of 10 to 15 years. Structural Overlay (SO) This treatment consists of the application of more than 2 inches of asphalt hot mix to the existing surface. This treatment requires grinding of the existing pavement to allow the new material to match existing curb and gutter elevations. A structural overlay has a life of 10 to 12 years. Reconstruction (RS) This treatment consists of removing existing pavement and base (which no longer has structural integrity) and replacing with a new pavement section. This treatment may also necessitate replacing curb and gutter. This treatment has a life of 15 to 20 years. 4 TAT-ION NEED The PMS has helped the City identify the current pavement condition and total backlog of rehabilitation needs for Moorpark's street system. The PMS defines backlog as all work necessary at the start of the condition survey to bring the arterial street system to an acceptable level of condition as portrayed on page 3 of this report. In other words, all streets would be in fair to excellent condition if the backlogged work were performed. Based on the PMS, only 6% of the street network has deferred maintenance, which needs to be brought to an acceptable condition. To eliminate the deferred maintenance backlog will cost approximately $1.63 million, including curb and gutter. The total rehabilitation needs for the City are $6.65 million now and an additional $900,000 over the next 10 years, for a total need of $7.5 million. With the current annual funding of $700,000, the current rehabilitation needs can generally be met during the next 10 years, assuming the annual funding levels keep pace with inflation. If it is assumed that annual inflation is 3.5 %, the annual funding will need to grow to $987,000/ year by the year 2005. EHABILITATION PROGRAM The City's PMS establishes priorities for each street segment. The prioritization process is based on the philosophy that funding should be spent on projects which will best protect the existing investment in the street system and benefit the maximum number of citizens. Using this philosophy, higher priorities are assigned to streets which serve the highest traffic volumes and require less expensive rehabilitation. Therefore, a local street with a high volume of traffic, which only requires a thin overlay, will receive a higher priority than a local street which requires complete reconstruction. In the beginning of selecting projects from the priority list, engineering judgment must be used. Currently, several projects have been designed and will be constructed over the next few months. These streets were listed at the top of the priority list. After these streets were placed on the list, the City staff and the Consultant determined logical construction projects built around the highest priority street segments and developed on priority streets as identified by the Pavement Management System. Priority street rehabilitation projects for local streets are listed in Table 1. In addition, an annual slurry seal program, consisting of approximately 15 miles of streets per year, is planned. 5 The City will have the PMS software installed on Public Works computers. With this new capability, the 5 -year Program will be updated on an annual basis. The major actions in this update process are: • Update traffic counts semi - annually. • Adjust unit costs annually. • Re- inventory condition of arterials and collectors every two (2) years and residential streets every five (5) years. • Rerun the PMS where there have been significant changes in costs, conditions, or traffic. • Annually close the fiscal year and add other years of projects from the most current priority listing. • Present the updated 5 -Year Program with next year's rehabilitation project program to the City Council annually. Over a period of years, as the PMS develops a history of street conditions, it will become readily apparent as to how the City's street system is performing, based on actual funding levels. Funding policy can be set on a very rational basis of the desired performance level of City streets. K*JD"I,&-K9IZ The street system in Moorpark consists of 81.5 miles of streets. The total street rehabilitation needs is $1.6 million. Backlog is defined as the total amount of rehabilitation work necessary to bring the street network to an acceptable condition level -- that is, no critical or poor segments and a distribution of all segments in Excellent, Good and Fair conditions. By eliminating the backlog, all segments of the system will have a condition rating of 70 or better. The current funding of $700,000 /year is adequate for City street needs, assuming that the annual funding keeps pace with inflation. 6 000470