HomeMy WebLinkAboutAGENDA REPORT 1993 0804 CC REG ITEM 08LITE�• Z :'
AGENDA REPORT
C = TY O F MOORPARK
TO: The Honorable City Council
FROM: Kenneth C. Gilbert, Director of Public Works
DATE: July 28, 1993 (Council Meeting 8 -4 -93)
SUBJECT: Consider Approval of a Change to the Proposed
Design for Phase II of the Charles Street
Improvements
BACKGROUND
In September of 1992, the City Council awarded a contract for
the Phase I improvements to Charles Street. That project
called for the reconstruction of Charles Street, including
the construction of a storm drain, from Moopark Avenue to
Bard Street. The scope of that project was determined by the
amount of CDBG funds then available to perform this work.
There are now sufficient CDBG and redevelopment agency funds
available to proceed with the construction of the remainder
of the Charles Street reconstruction project. This requests
approval of a modification to the design concept approved for
the phase 1 construction.
DISCUSSION
A. Previous Design Concept
chesb
As you may recall, the design concept for the Charles
Street project called for the following improvements:
• a thirty -six feet (361) wide street (curb -to -curb)
within the sixty feet (601) right -of -way;
• four feet (41) wide sidewalks constructed at the
property line; and,
• an eight -feet wide (81) parkway between the curb and
sidewalk.
The placement of the sidewalk was adjusted where
necessary in order to preserve existing street trees.
MOORPARK, CALIFORNIA
City Council Mseflng
of 199,��
ACTION: 6'2
V 17T.QJ1tei�e""".' Xi
Charles Street
August 1993
Page 2
B. Conflicts
The draft design previously prepared for the easterly
portion of this project shows the sidewalks located at
the property line as discussed above. That design shows
a number of conflicts between the proposed construction
and existing topography and /or private improvements which
encroach into the street right -of -way. These problems
include the following:
• a handicap access ramp encroaching into the right -
of -way on the north side of the street at 459
Charles;
• a driveway with a very steep grade on the north side
of the street at 437 Charles (moving the sidewalk to
the curb will provide more room for the required
transition between the proposed and existing
improvements);
• extensive fill material required on the south side
of the street at 410 Charles;
• a block wall and grade separation requiring fill
material on the south side of the street at 470
Charles;
• a slope encroaching into the right -of -way on the
north side of the street at 471 Charles; and more.
C. Proposed Change
Most if not all of the identified conflicts can be
avoided if the sidewalk were to be placed adjacent to the
curb. As with the initial design, this will not be a
strict rule as the sidewalk will be moved, where
required, to avoid existing trees.
It is estimated that this will decrease construction
costs by at least $30,000. It is recommended, therefore,
that the design concept be revised to allow for the
placement of the sidewalks at the curb from Bonnie View
Street easterly to Spring Road.
D. Street Width Inconsistency
The existing width of Charles Street just east of
Magnolia Street is forty feet (401) wide instead of the
thirty -six (361) feet wide section used throughout the
chas6
Charles Street
August 1993
Page 3
rest of the project. This inconsistency was created when
the street improvements in front of the Tafoya Terrace
Housing Project were constructed. It is not recommended
that the street be reconstructed in this area to narrow
the street.
E. Committee Review
At a recent meeting of the Public Works, Facilities and
Solid Waste Committee (Mayor Pro tem Montgomery and
Councilmember Wozniak) the proposed changes to the
conceptual design were discussed. The Committee
recommended approval of the proposed change to the
conceptual design.
F. Spring Road Storm Drain and Street Improvements
The Central City Drainage Study (excerpt attached) shows
the need for the construction of a storm drain in Spring
Road from High Street northerly to Charles Street. In
addition, pavement, curb, gutter and sidewalk is required
on the west side of Spring Road south of Charles Street.
Staff considered the feasibility of adding this work to
the Charles Street project. That analysis looked at a
number of questions including a review of CDBG funding
constraints, federal regulations applicable to the
Charles Street project, off -site improvements on the west
side of Spring Road, etc. It is the recommendation of
staff that this construction be deferred at this time and
considered in conjunction with other projects which may
be undertaken by the Moorpark Redevelopment Agency (MRA)
in the near future.
G. Fiscal Impact
The estimated construction cost for Phase 2 Charles
Street improvements is $400,000. A more accurate total
project cost estimate will be provided to the City
Council with the final design and request for
authorization to advertise.
ches6
Charles Street
August 1993
Page 4
H. Schedule
With this design clarification, finalization of the
design will proceed. It is anticipated that the design
for this project will be completed and brought to the
City Council in September for approval and authorization
to advertise for receipt of bids.
Staff and the Public Works, Facilities and Solid Waste
Committee recommend approval of the revised design concept
for the Charles Street improvements as described in
Section C of this report.
chea6
Exhibit 1
Exerpt from Central City Master drainage Study:
Problem Areas:
7. The culvert at the intersection of Charles Street and
Moorpark Road consists of a 36" CMP which cannot carry
the flows from the 10 year storm. Storm waters
frequently exceed its capacity and flood across Charles
Street and onto the residential property on the
downstream side of Charles Street.
The solution to this problem is to replace the 36" CMP
with a 36" RCP with an improved inlet that is capable
of accepting the flow as shown on Plate 2B. A 36" RCP
can carry twice as much water as a 36" CMP.
c
9.f:0
U RV'63 �lN� f:1fJ
lr.