AGENDA REPORT of
C 2 TY OF MOORPARK
T Ot!
TO: The Honorable City Council 1_ ', ltd
FROM: Kenneth C. Gilbert, Director of Public Works
DATE: March 8, 1996 (Council Meeting 3-20-96)
SUBJECT: Consider Budget Adjustment for Certain Capital
Improvement Projects
DISCUSSION
A. Overview
This request approval of an adjustment to the approved amount
of the appropriation and FY 1995/96 Budget for certain street
improvement projects. The primary purpose of these adjustments
is to clarify the funding sources and amounts for certain
projects funded by Community Development Block Grant (CDBG)
funds and by the State Local Transportation Partnership Program
(SLTPP) .
B. Funding Summary
Attached as Exhibit 'A is a summary of the requested budget
adjustments. Also included in Exhibit 'A' for reference is the
anticipated amounts to be budgeted for the subject projects for
FY 1996/97.
C. Detail
The following is a brief explanation of the requested budget
adjustments for each of the project listed in Exhibit 'A' .
1 . Poindexter Right Turn
• This project moves the curb on the west side of
Moorpark Avenue just north of Poindexter Avenue in
order to accommodate southbound right-turn traffic at
this intersection. The design is almost completed and
it is anticipated that construction will be completed
this fiscal year.
• The project is not presently funded in the FY 1995/96
Budget. It is requested that the project be funded
from the source which funded the initial construction
of the traffic signal at this intersection, that being
the Los Angeles Avenue AOC (Fund 027) .
bgt_963
000034,34,
Budget Adjustment
March 1996
Page 2
2. Everett Storm Drain Outlet
• This project provides for the reconstruction of the
outlet storm drain line between the detention basin
located north of Everett Street and the storm drain in
Everett Street.
• The project is currently funded from the Gas Tax Fund.
It is recommended that the primary funding source for
this project be the CDBG fund.
• CDBG program restrictions prevent the City from
charging non-construction costs to the CDBG fund.
Accordingly, it is recommended that current year
funding be restricted to design costs only, and that
these costs be funded from Fund 011 - Local
Transportation Fund.
• Construction (funded by CDBG) and construction
engineering (funded by LTF) costs will be budgeted next
year.
3 . Wicks Road Slope Stabilization
• This project provides for the construction of slope
stabilization measures along the south side of Wicks
Road.
• This project is currently funded by the CDBG Fund.
CDBG program restrictions prevent the City from
charging non-construction costs to the CDBG fund.
Accordingly, it is recommended that current year
funding be restricted to design costs only, and that
these costs be funded by the Moorpark Redevelopment
Agency (MRA) .
• Construction costs (funded by CDBG) and construction
engineering costs (funded by MRA) will be budgeted next
year.
4. Wicks Road Pavement Rehabilitation
• This project provides for the rehabilitation of the
asphalt pavement on Wicks Road.
• The project is currently not funded. It is recommended
that the primary funding source for this project be the
CDBG fund.
• CDBG program restrictions prevent the City from
charging non-construction costs to the CDBG fund.
Accordingly, it is recommended that current year
funding be restricted to design costs only, and that
these costs be funded by the Moorpark Redevelopment
Agency (MRA) .
• Construction costs (funded by CDBG) and construction
engineering costs (funded by MRA) will be budgeted next
year.
bgt_963 000035
Budget Adjustment
March 1996
Page 3
5. Valley Road
• This project calls for the rehabilitation of the
pavement within the existing forty feet (401 ) right-of-
way on Valley Road.
• The project is currently funded by the CDBG Fund. CDBG
program restrictions prevent the City from charging
non-construction costs to the CDBG fund. Accordingly,
it is recommended that current year funding be
restricted to design costs only, and that these costs
be funded by the Moorpark Redevelopment Agency (MRA) .
• Construction costs (funded by CDBG) and construction
engineering costs (funded by MRA) will be budgeted next
year.
6. Alleys (First St. to Flory Ave. )
• This project calls for the rehabilitation of the
pavement in the alleys east of Moorpark Avenue between
First Street and Los Angeles Avenue, including the
construction of ribbon gutters and other required
drainage improvements.
• The project is currently funded by the MRA. It is
recommended that current year funding be restricted to
anticipated design costs only.
• In addition to MRA funding, this project will receive
partial funding (approximately 20%) from a State grant
under Cycle 7 of the State-Local Transportation
Partnership Program (SLTPP) . The budget for FY 1996/97
will reflect both of these funding sources.
7. Maureen Lane (S/O L. A. Ave. )
• This project calls for the rehabilitation of the
pavement on Maureen Lane south of Los Angeles Avenue.
Street improvements will be restricted to the current
pavement width of twenty-four feet (241 ) . Construction
will also include the replacement of the storm drain
catch basin at the south end of the street.
• The project is currently funded by the MRA. Current
year funding of $50,000 is for design costs only. It
is recommended that current year funding be reduced to
reflect actual year-end anticipated design costs.
• In addition to MRA funding, this project will receive
partial funding (approximately 20%) from a State grant
under Cycle 7 of the State-Local Transportation
Partnership Program (SLTPP) . The budget for FY 1996/97
will reflect both of these funding sources.
bgt_963 .00OIU;3 i,v
Budget Adjustment
March 1996
Page 4
8. Bonnie View Street
• This project calls for the rehabilitation of the
pavement on Bonnie View Street. Roadway improvements
will be restricted to the present configuration of the
right-of-way widths, slopes and curve radii .
• The project is currently not funded. It is recommended
that anticipated current year design costs be funded by
the MRA.
• It is the intent of staff to propose that FY1996/97
project costs also be funded by the MRA, with partial
funding of construction costs (approximately 200) to
come from a State grant under Cycle 7 of the State-
Local Transportation Partnership Program (SLTPP) .
RECOMMENDATION (Roll Call Vote)
Staff recommends that the City Council approved the changes to the
appropriation and budget amounts for FY 1995/96 for certain
projects as listed in Exhibit 'A' and summarized as follows:
1) Poindexter Right Turn
27-142-903-0420: from $0 to $30,000 ($30,000 increase) ;
2) Everett Storm Drain Outlet
03-142-903-0398: from $80,000 to $0 ($80,000 decrease)
11-142-903-0398: from $0 to $20,000 ($20,000 increase) ;
3) Wicks Road Slope Stabilization
01-170-903-0372: from $0 to $10,000 ($10,000 increase) ;
18-142-903-0372: from $150,000 to $0 ($150,000 decrease)
4) Wicks Road Pavement Rehabilitation
01-170-903-0382: from $0 to $20,000 ($20,000 increase) ;
5) Valley Road
01-170-903-0405: from $0 to $20,000 ($20,000 increase) ;
18-142-903-0405: from $100,000 to $0 ($100,000 decrease) ;
6) Alleys (First St. to Flory Ave. )
01-170-903-0397: from $50,000 to $5,000 ($45,000 decrease) ;
7) Maureen Lane (S/O L. A. Ave. )
01-170-903-0395: from $50,000 to $5,000 ($45,000 decrease) ;
8) Bonnie View St.
01-170-903-xxxx: from $0 to $5,000 ($5,000 increase) ;
bgt_969
00003 i
11-Mar-96 Page 1
March 1996 Budget Adjustment
FY1995/96 FY1995/96 & FY 1996/97 Funding Summary
--------------------------------------- Proposed --------------------------------------------------------------------
Project Current Change Revised FY1996/97 18:CDBG 14:SLTPP 11:LTF 27:L A AOC MRA Total
-------------------------------- ----------- ----------- ----------- ---------- --------- --------- --------- --------- --------- ----------
1 Poindexter Right Turn
27-142-903-0420 0 30,000 30,000 0 30,000 30,000
2 Everett Storm Drain
03-142-903-0398 80,000 (80,000) 0 0
11-142-903-0398 0 20,000 20,000 20,000 40,000
18-142-903-0398 0 0 0 80,000 80,000
----------- ----------- ----------- ---------- --------- ---------
80,000 (60,000) 20,000 100,000 80,000 40,000 120,000
3 Wicks Slope Stabilization
01-170-903-0372 0 10,000 10,000 20,000 30,000
18-142-903-0372 150,000 (150,000) 0 120,000 120,000
----------- ----------- ----------- ---------- --------- --------
150,000 (140,000) 10,000 140,000 120,000 30,000 150,000
4 Wicks A/C Pavement Rehab
01-170-903-0382 0 20,000 20,000 20,000 40,000
18-142-903-0382 0 0 0 120,000 120,000
----------- ----------- ----------- ---------- --------- ---------
0 20,000 20,000 140,000 120,000 40,000 160,000
5 Valley Road
01-170-903-0405 0 20,000 20,000 20,000 40,000
18-142-903-0405 100,000 (100,000) 0 150,000 150,000
----------- ----------- ----------- ---------- --------- --------- t l
100,000 (80,000) 20,000 170,000 150,000 40,000 190,000
6 Alleys Cf
01-170-903-0397 50,000 (45,000) 5,000 240,000 245,000
14-142-903-0397 0 0 0 60,000 60,000
----------- ----------- ----------- ---------- --------- --------- rtj
50,000 (45,000) 5,000 300,000 60,000 245,000 305,000
rj
N
11-Mar-96 Page 2
March 19% Budget Adjustment
FY1995/% FY1995/96 & FY 1996/97 Funding Summary
--------------------------------------- Proposed --------------------------------------------------------------------
Project Current Change Revised FY1996/97 18:CDBG 14:SLTPP 11:LTF 27:L A AOC MRA Total
-------------------------------- ----------- ----------- ----------- ---------- --------- --------- --------- --------- --------- ----------
7 Maureen Lane
01-170-903-0395 50,000 (45,000) 5,000 120,000 125,000
14-142-903-0395 0 0 0 30,000 30,000
----------- ----------- ----------- --------- --------- ---------
50,000 (45,000) 5,000 150,000 30,000 125,000 155,000
8 Bonnie View
01-110-903-.... 0 5,000 5,000 60,000 65,000
14-142-903-.... 0 0 0 15,000 15,000
----------- ----------- ----------- ---------- --------- ---------
0 5,000 5,000 75,000 15,000 65,000 80,000
430,000 (315,000) 115,000 1,075,000 470,000 105,000 40,000 30,000 545,000 1,190,000
1,190,000