HomeMy WebLinkAboutAGENDA REPORT 1998 0819 CC REG ITEM 10BTO:
FROM:
DATE:
AGENDA REPORT
CITY OF MOORPARK
The Honorable City Council
I T 10 •b•
(;► 3` (IF 110ORPARK, CALTFORNIA
Citi, Coounciii rNieeflnR
of I • "i_y
ACTION: �bDroyeA �z -aff
recommerda +ion
IV
Kenneth C. Gilbert, Director of Public Works
July 29, 1998 (Council Meeting 8- 19 -98)
"01,—
SUBJECT: Discussion of Possible Redesign of the Spring Road Bridge
Reconstruction Project
• • - � •
1. Design: A summary of the development of the design for the
subject project is attached as Exhibit 1.
2. Prior Rejection of Bids
On January 7, 1998, the City Council authorized staff
to advertise for receipt of bids.
• On May 14, 1998, bids were opened and tabulated.
• On June 3, 1998, the City Council considered and then
rejected the bids due to construction scheduling
problems.
1. Background: During the bidding process last May, comments
were received suggesting that the cost of the project could
be reduced if the bridge were redesigned. At its meeting
of June 3rd, the City Council directed staff to prepare a
report discussing the pros and cons of pursuing this
suggestion.
2. Current Design: The current design calls for a cast -in-
place box girder bridge deck with one center pier wall
support in the middle of the bridge span.
3. Alternate Design: The suggested alternative design would
call for a clear -span bridge deck (no center pier support) ,
using pre -cast concrete girders. This design option would
require the elevation of the bridge deck to be raised
s ll '10 "', Ii
Spring Road Bridge
August 19, 1998
Page 2
C.
approximately three feet (31). The raising of the roadway
surface on the bridge deck would require raising the bridge
approaches north and south of the bridge. This would
require the removal and reconstruction of the existing
street improvements (curbs, gutters and sidewalks) north
and south of the bridge.
4. Pros and Cons of Redesign: Attached as Exhibit 2 is a list
of pros and cons for not changing the design, as well as a
list of pro and cons for redesigning the bridge.
5. Redesign Effort: The cost to redesign the bridge is
estimated to be approximately $80,000. The amount of time
required to complete such a redesign is approximately 90
days.
6. Cost Reduction Incentive Plan (CRIP): An alternative to
redesigning the bridge would be to simply rely upon the
provisions of the specifications pertaining to "Cost
Reduction Incentives." Those provisions allow a contractor
to propose an alternative design which will result in a
reduction of the total cost of construction. In such case,
the design for the proposed change(s) is prepared by the
contractor, at the contractor's cost. The City has no
obligation to approve the proposed changes. However, if
approved, one -half of the cost savings is paid to the
contractor. Using this approach the City could avoid the
risk of paying for a redesign, and then being faced with a
low bid which does not generate a cost savings which
exceeds the redesign costs.
7. Conclusion
Although the cost of a clear -span bridge is estimated to be
less than a box girder bridge with a center pier support,
the costs associated with the reconstruction of certain
street improvements and the increased cost of certain
retaining walls is estimated to equal or exceed these cost
savings. Even if there were to be a slight net
construction cost savings, it is not anticipated that the
savings would exceed the cost of the redesign. It is
recommended below, therefore, that the project not be
redesigned.
The City Council is reminded that it is often misleading to
compare the bid results of a re- advertised project with the
original bid amounts. There are often a number of changed
conditions affecting the bid amounts, beyond just competitive
spgbrgll � j r ,
spring Road Bridge
August 19, 1998
Page 3
forces. With regard to the subject project, one such
difference will be that the plans and specifications will be
slightly revised (see below).
Even if the City Council does not direct a redesign of the
bridge, it will be necessary to make certain changes to the
plans and specs prior to re- advertising the project. of this
project. Those changes are summarized as follows:
1. South Bridge Approach: Carlsberg's plans for the
construction of improvements to Spring Road extended all
the way to, and merged with, the City's bridge
reconstruction plans. Carlsberg must proceed with the
construction of those street improvements in the next few
months, prior to the reconstruction of the bridge. In that
those plans do not "merge" with the existing elevation,
width and alignment of the south bridge approach, it will
be necessary for the southerly one to two hundred feet
(100' - 2001) of these improvements to be deferred. It is
the intent of Carlsberg to pay the City an in -lieu amount
equaling the total cost (design, construction and
inspection) of the deferred improvements. The "deferred"
south bridge approach will then be added to the City's
project.
.11
It is the intent of Carlsberg to provide an additional plan
sheet for these deferred improvements. The Engineering
Department will review and approve this design change and
incorporate it into the City's design package. As stated
above, any cost associated with this work will be funded by
Carlsberg.
2. Minor Corrections: During the bidding process last May, a
number of comments and corrections were received from
various plan holders. Many of those comments and suggested
corrections generated one or more addenda to the plans. It
is the intent of staff to require the Engineer to
incorporate those and other relevant and /or necessary
changes into the revised final plans and specs. It is
anticipated that, with few exceptions, there will be no
additional cost to the City for the Engineering design time
required to make these changes to the plans and
specifications.
3. Language Changes: It is the intent of the Director of
Public Works to provide certain additional and /or amending
language to the specification regarding project schedule
and a number of other matters needing clarification.
JUL; ? 0 -,,,1
�J -.-- 2
Spring Road Bridge
August 19, 1998
Page 4
E. Fiscal Impact
1. Project Cost Estimate: The current project cost estimate
is summarized as follows:
Element Total ($)
Construction 2,238,807
Contingency 223,881
Sub -Total Construction 2,462,688
Design Cost 99,183
Design Support Costs 34,150
Admin & Inspection Costs 142,499
Project Contingency (FY98/99) 50,000
Total 2,788,520
2. Funding Sources: The City is in receipt of a federal grant
in the amount of $404,800 for this project. The remainder
of the project funding will come from the Spring Road /
Tierra Rejada Road AOC. As discussed in prior reports, at
the time of the award of a contract for this project, it
may be necessary for the City Council to approve an inter -
fund loan (from the Los Angeles Avenue AOC) to fully fund
this project. Anticipated future revenues to the Spring
Road / Tierra Rejada Road AOC are sufficient to fully re-
pay that loan.
3. Current Budget: The figures in the FY 1998/99 Budget were
based upon a presumption made last April that contracts for
construction and construction engineering would have been
awarded prior to the end of FY 1997/98. If that had
occurred all of those costs would have been encumbered in
FY 1997/98. Accordingly, only $50,000 was budgeted in FY
1998/99 as a contingency for additional or unforeseen
expenses.
4. Additional Design Costs: As discussed above, it is
necessary for the design engineer to make certain changes
to the contract documents prior to the project being re-
advertised for receipt of bids. The current budget amount
is sufficient to cover those additional design costs.
5. Future Budget Amendment: It is the intent of staff to
request approval of a budget amendment at the time the bid
results are presented to the City Council.
JIG
Spring Road Bridge
August 19, 1998
Page 5
F. Schedule
The bid / award sc
• 11/04/98:
• 01/07/99:
• 01/20/99:
• 03/01/99:
• 04/15/99:
:hedule for the subject project is as follows:
City Council approves plans and
authorizes staff to advertise for bids
open bids
award contract
Notice to Proceed
commence excavation work in the arroyo
RECOMMENDATIONS
Staff recommends that the City Council take the following actions:
1. Direct staff not to redesign the project.
2. Direct staff to proceed with making certain minor changes to
plans and specifications as described in this report.
3. Direct staff to present the revised plans and specifications to
the City Council for approval and authorization to advertise,
consistent with the schedule set forth in this report.
opgbrgll ( _
_ ,T„� Y3
Exhibit 1: Design Background
Page 1
1. Design Engineer: In September 1994, the City Council
selected the firm of Dwight French and Associates (DFA) to
prepare the design plans and specifications for the
replacement of the Spring Road Bridge across the Arroyo
Simi. When Dwight French & Associates was absorbed by
Charles Abbott Associates (CAA), CAA assumed the
responsibility for completing the design.
2. Existing Bridge Dimensions:
• Bridge Length: 122'
• Bridge Width: 28'
• Travel Lanes: 2 ea. 14' wide
• Median: None
• Bike Lanes: None
• Sidewalks: 2 ea. 2' wide
3. Future Bridge Dimensions:
• Bridge Length: 150'
• Bridge Width: 50'
• Travels Lanes: 2 ea. 12' wide
• Median: 1 ea. 4' wide
• Bike Lanes: 2 ea. 8' wide
• Sidewalks: 2 ea. 8' wide
4. Bridge Support: The existing bridge is supported by the
bridge abutments plus three sets of pier columns placed in
the water course. The new bridge will be supported by the
bridge abutments plus only one center pier wall. Unlike
the sets of pier columns, the center pier wall will be
designed to prevent the collection of debris.
5. Piles: The foundations for the bridge abutments, as well
as the center pier wall, will require driving approximately
2,600 linear feet of piles.
6. Design Requirements: The development of the project design
required undertaking and completing a number of tasks
including:
• Survey
• Roadway Alignment
• Right -of -Way Requirements
• Utility Impacts
• Hydrology & Geotechnical Analysis
• Seismic / liquefaction analysis
• Bridge Structural Design
• Interface with future trail system
• Preparation of plans / profiles
• Traffic control (road closure analysis)
• Construction cost estimate
• Cost est. for bridge widening (grant amount)
• Road widening northwest of bridge
• Striping plans
spgbrgli <1 ' ALa
uV'.a.' ^.a d
Exhibit 1: Design Background
Page 2
7. Levee Trail: One of the transportation goals of the City
is to have a Levee Trail along the Arroyo Simi through the
City, similar to the "river- side" trail in the City of Simi
Valley. The City has received approval of a grant to
perform a study to determine the feasibility of extending
this trail system easterly to Madera Road in the City of
Simi Valley. The bridge design provides for this future
levee trail system by including trail ramps which will go
under the bridge on the north side of the Arroyo.
8. Street Improvements North of the Bridge: The project
includes the construction of full -width street improvements
on the west side of Spring Road just north of the bridge.
These improvements include the construction of a storm
drain to replace the current open culvert, and the
construction of street widening to include a sidewalk to
connect the sidewalk on the new bridge to the sidewalk
along the frontage of Gateway Plaza shopping center.
9. Center Median: The Spring Road street improvements to be
constructed by the developer of the Carlsberg Specific Plan
include the construction of a raised center median along
the entire length of Spring Road south of the bridge. As
mentioned above, the bridge replacement project includes
the construction of a center raised median on the bridge.
The project also includes the extension of the raised
center median north of the bridge to the south side of the
southerly Spring Road entrance to the Moorpark Plaza
shopping center.
The design of the existing and future roadway just south of
the bridge has both a horizontal and a vertical curve. Due
to these geometrics of the roadway, as well as the fact
that the median is not wide enough to accommodate left turn
lanes, the median to be constructed by Carlsberg will not
include median breaks to allow left turn movements into and
out of driveways located on both sides of the street just
south of the bridge. Turning movements into and out of
these driveways will be restricted to right turns only.
This design is consistent with the median design near the
Tierra Rejada Road bridge.
10. Future Channel Widening: The project design is compatible
with both the existing arroyo channel as well as the
proposed design for a future project by the Ventura County
Flood Control District (VCFCD) to widen and lower the
channel to hold 100 year storm flows. Said future
improvements will include a drop structure just upstream of
the bridge.
spgbrgil
11. Street Right -of -Way: The VCFCD has granted the City a
street easement deed which provides for full -width street
right -of -way on the east side of Spring Road across the
Exhibit 1: Design Background
Page 3
arroyo. This easement was required for the construction of
the bridge project. In that the VCFCD is not the fee owner
of the Arroyo on the west side of Spring Road, that agency
could not grant the City a like street easement to provide
a full -width street right -of -way on the west side of the
street. However, this additional west -side street right -
of -way is not required for the subject project. It would
be required for any future widening of the bridge to four
lanes.
12. Temporary Construction Easement: A -C Construction, the
owner of the property on the west side of Spring Road just
north of the Arroyo, has granted to the City a temporary
construction easement required for the proposed street and
related improvements in that area.
13. Environmental Clearance: In April of 1997 the City Council
approved Resolution No. 97 -1306 approving the Mitigated
Negative Declaration for the subject project and adopting
a Mitigation Monitoring Program related thereto.
14. Permits: The City retained the services of a consultant to
obtain certain permits required for this project. Those
efforts included submittal of applications and the securing
of permits (where required) from a number of agencies
including:
• the U. S. Army Corp of Engineers: permit not required;
• the State Regional Water Quality Control Board: permit
issued; and,
• the California Fish & Game Department: permit issued.
In addition to those consultant efforts, staff sought and
obtained permits from the following agencies:
• Caltrans (traffic detour signs); and,
• VCFCD Encroachment Permit
15. Utility Cells: There are eight (8) utility cells located
within the bridge structure. Four of the cells are to be
used for utilities and four will remain empty and available
for possible future use. The cells to be occupied will be
used for gas, telephone, water and sewer.
16. Utility Conflicts:
• Water:
- County Waterworks District No. 1: An existing
water line on the bridge will be abandoned during
the bridge reconstruction project. A new water
line will be placed in one of the utility cells
within the bridge structure. The City's project
will include the placement of a sleeve within a
utility cell to receive the future new water line.
All City design and construction costs for this
work will be reimbursed by the District. The work
spgblgll , • o
��.si-
Exhibit 1: Design Background
Page 4
required to place the new water line will be done
by a separate contractor retained by the District.
- Calleguas: There are no Calleguas facilities
within the existing bridge or planned to be placed
within the future bridge. Calleguas recently
completed the reconstruction of an east -west
running water distribution line located just south
of the bridge.
• Sewer: There is an existing sewer line attached to the
east side of the existing bridge. This facility will
be replaced by County Waterworks District No. 1. The
City's project will include the placement of a sleeve
within one of the utility cells within the bridge
structure, to receive the future new sewer line. All
City design and construction costs for this work will
be reimbursed by the District. All work required to
remove the old sewer line, place a temporary sewer line
and install the new sewer line will be done by a
separate contractor retained by the District.
• Gas: There is a gas main attached to the existing
bridge. This facility will be abandoned during the
bridge reconstruction project. The Southern California
Gas Company will install a new gas line to be located
within a utility cell in the bridge structure. All
work will be done by the utility company.
Shell Oil: The Shell Oil Company recently abandoned a
fuel transport line attached to the bridge and
constructed a new replacement line which extends under
the Arroyo.
Telephone: Existing telephone conduits located under
the Arroyo immediately upstream of the bridge will
remain in place. Bridge structural elements have been
designed to "bridge" these facilities. The City
Council has approved a "Build Over" Agreement between
the City and Pacific Bell Company regarding this
element of the work.
Electrical: All existing electrical facilities in the
vicinity of the bridge are overhead and are not
affected by the project. No additional street lights
are proposed to be installed on or near the bridge.
Should there be a need for the placement of underground
electrical facilities at any point in the future, such
lines could be placed in an empty utility cell, if one
is still available.
• Cable T. V.: There are no existing cable facilities in
the vicinity of the project.
spynrqu
Exhibit 2: Pros and Cons of Re- Design
Page 1
Pros & Cons to Staying with the Current Design: some of the pros
and cons of keeping the current design are listed as follows:
Pros -- Keeping the current design:
1 adds no new design cost;
2 does not expose the City to a possible slippage of schedule
due to delays caused by unforseen problems arising from the
redesign process;
3 leaves the elevation of the street unchanged:
- no reconstruction of existing street improvements to
match higher bridge deck elevation;
- no increase in related construction costs;
- no vertical curve problems; and,
- no need to raise the height of the retaining walls
northwest of the bridge; and,
4 avoids redesign of utility accommodation.
Cons -- Keeping the current design:
1 retains the center pier support
- added center pier construction cost;
- potential construction problems and cost overruns;
Pros & Cons of Redesigning the Bridge: Some of the pros and cons
of redesigning the bridge to delete the center pier support are
listed as follows:
Pros -- The redesign:
epgbrgll
1 eliminates pile driving and related pier foundation
construction in the middle of the arroyo and related
potential dewatering problems;
2 eliminates the cost of the center pier wall construction;
3 improves hydraulic;
4 eliminates possible cause of blockage by debris collection
on center pier support;
5 reduces amount or degree of intrusion of construction
activity in the watercourse;
6 may shorten the construction time by eliminating the cast -
in -place construction effort;
Exhibit 2: Pros and Cons of Re- Design
Page 2
7 eliminates falsework for cast -in -place box girder deck;
8 eliminates need for the construction of temporary pier
foundations in the arroyo for the falsework;
9 may have a lower estimated construction cost [Note: cost
savings is expected to be offset by redesign costs plus the
added cost ofraising the street];
Cons -- The redesign:
1 adds cost [approx. $80,000] for the redesign of the bridge;
2 opens the door to unknown factors which could come up
during the redesign process:
- could lead to additional design and /or construction
costs;
- could delay the bidding process;
- could cause a delay to the start of construction which
would extend construction into the 1999/2000 wet
season;
- Note: the amount of time required to redesign the
bridge is currently estimated to be ninety (90) days;
3 adds cost related to the reconstruction of existing street
improvements to raise the elevation of the roadway at the
bridge approaches:
- approximate length of the street reconstruction at the
north end of the bridge is three hundred feet (3001);
- approximate length of the street reconstruction at the
south end of the bridge is one hundred feet (1001);
- adds the need to design vertical curves (slope) in the
roadway in a manner which safely handles traffic
- adds the need to construct higher retaining walls on
the west side of the street north of the bridge;
4 adds unknown scheduling factors associated with the
ordering, fabrication and delivery of the pre -cast concrete
beams, which could delay the completion of the project;
5 requires the redesign of the methods to be used to
accommodate utilities on the bridge:
- current design provides for the placement of certain
utilities within the hollow box girders;
- new design would provide for the attachment of the
utilities to the beams;
- adds need to interface with all affected utilities.
Note: It is presumed that the redesign will not affect (or will
have little effect) on the design for the bridge abutments,
including the need to drive piles as a part of the
construction of the foundations.
spgbrgll
Exhibit 3: Additional Plan Changes
August 19, 1998
The plans and specifications require certain changes prior to the
re- advertising of this project. Those changes are summarized as
follows:
1. South Bridge Approach: Carlsberg's plans for the
construction of improvements to Spring Road extended all
the way to, and merged with, the City's bridge
reconstruction plans. Carlsberg must proceed with the
construction of those street improvements in the next few
months, prior to the reconstruction of the bridge. In that
those plans do not "merge" with the existing elevation,
width and alignment of the south bridge approach, it will
be necessary for the southerly one to two hundred feet
(100' - 2001) of these improvements to be deferred. It is
the intent of Carlsberg to pay the City an in -lieu amount
equaling the total cost (design, construction and
inspection) of the deferred improvements. The "deferred"
south bridge approach will then be added to the City's
project.
It is the intent of Carlsberg to provide an additional plan
sheet for these deferred improvements. The Engineering
Department will review and approve this design change and
incorporate it into the City's design package. As stated
above, any cost associated with this work will be funded by
Carlsberg.
2. Minor Corrections: During the bidding process last May, a
number of comments and corrections were received from
various plan holders. Many of those comments and suggested
corrections generated one or more addenda to the plans. It
is the intent of staff to require the Engineer to
incorporate those and other relevant and /or necessary
changes into the revised final plans and specs. It is
anticipated that some -- but not all -- of the effort
necessary to make these plan changes will require minor
additional design costs.
3. Language Changes: It is the intent of the Director of
Public Works to provide certain additional and /or amending
language to the specification regarding project schedule
and a number of other matters needing clarification.
epgbrgil